a.Project M
Net present value is solved using a financial calculator. The steps to solve on the financial calculator:
Net Present value of cash flows at 17% required rate of return is $46,667.37.
Project N
Net present value is solved using a financial calculator. The steps to solve on the financial calculator:
Net Present value of cash flows at 17% required rate of return is $49,009.92
b.Project M
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 35.73%.
Project N
Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 24.12%.
c.Project N should be accepted since it has the highest net present value.
In case of any query, kindly comment on the solution.
Bausch Company is presented with the following two mutually exclusive projects. The required return for both...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 13 percent. Year Project M -$135,000 65,000 83.000 74,000 60,000 Project N -$370,000 145,000 195.000 130.000 125,000 2 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 17 percent. Year O-NM Project M $138,000 64,700 82,700 73,700 59.700 Project N -$367,000 146,500 192,000 131,500 122.000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g. 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M. -$142,000 64,300 82,300 73,300 59,300 Project N. -$363,000 148,500 188,000 133,500 118,000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M. -$142,000 64,300 82,300 73,300 59,300 Project N. -$363,000 148,500 188,000 133,500 118,000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M Project N 0 –$139,000 –$356,000 1 63,600 152,000 2 81,600 181,000 3 72,600 137,000 4 58,600 111,000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year ہے 40 points Project M -$140,000 61,500 73,400 68,100 40,500 Project N -$359,000 159,300 168,400 154,800 110,400 یہ بیا هم eBook Print References a. What is the IRR for each project? (Do not round Intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do...
Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year Project M Project N 0 -$125,000 -$310,000 1 57,000 135,000 2 64,000 161,000 3 59,000 129,000 4 34,000 92,000 Required: (a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR Project M% Project N % (b) What is the NPV for each...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Project N Project M -S140,000 61,500 73,400 68,100 40,500 -$359,000 159,300 168,400 154,800 110,400 a. What is the IRR for each project? b. What is the NPV for each project? C. Which, if either, of the projects should the company accept?
Tyde Company is presented with the following two mutually exclusive projects. The required return for both projects is 14 percent. Year. PROJECT A. PROJECT B 0. -$140,000. -$365000 1. 64,500. 147,500 2. 82,500. 190,000 3. 73,500. 132,500 4. 59,500. 120,000 a. What is the IRR for each project? ( Do not round intermediate calculations and enter answer as a percent rounded to 2 decimal places) b. What is the NPV for each project? c. Which, if either, of the projects...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 13 percent Year Project FProject G -S127,000 197,000 44,000 59.000 86,000 116,000 131,000 64,000 46,000 56,000 51,000 46,000 a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Project F Project G years years b. Calculate the NPV for both projects. (Do not...