Using this information:Answer the following, Please explain briefly.
Answer :-
a)1)The balance in Work in Process Inventory on January 1 if this was the only unfinished job :-
Balance in Work in Process on January 1 = Beginning balance of direct materials + Beginning balance of direct labor + Beginning balance of manufacturing overhead
Given , Beginning balance of direct Materials = $6,700
Beginning balance of direct labor = $6,000
Beginning balance of manufacturing overhead = $4,200
Balance in Work in progress on January 1 = $6,700 + $6,000 + $4,200
Balance in Work in progress on January 1 = $16,900
a)2)If manufacturing overhead is applied on the basis of direct labor cost,the overhead rate was used in each year -
To calculated the Overhead rate in Last year we will take the beginning balance of Manufacturing Overhead and Direct Labor cost.
Overhead rate in Last year = Beginning balance of Manufacturing Overhead /Beginning balance of direct labor.
Beginning balance of direct labor = $6,000
Beginning balance of manufacturing overhead = $4,200
Overhead rate in Last year = $4,200 / $6000
Overhead rate in Last year = 70%
Now we calculated the Overhead rate of current year ,for this I have taken Total Manufacturing Overhead and Total Direct Labor cost.
Overhead rate in Current year = Manufacturing Overhead / Direct Labor cost
Manufacturing Overhead = $11,700
Direct Labor = $16,000
Overhead rate in Current year = $11,700 / $16,000
Overhead rate in Current year = 73%
.
(b)Journal entries at January 31 to record the current year’s transactions pertaining to Job No. 92.
Date | Account Titles and Explanation | Debit | Credit |
Jan.31 | Work in Process Dr. | $15,200 | |
To Raw Material Inventory | $15,200 | ||
(To record raw materials used for completion of Job) | |||
Jan.31 | Work in Process Dr. | $16,000 | |
To Factory labor cost | $16,000 | ||
(To record factory labor used) | |||
Jan.31 | Work in Process. Dr. | $11,700 | |
To Manufacturing Overhead | $11,700 | ||
(To record manufacturing overhead) | |||
Jan.31 | Finished Goods Inventory Dr. | $42,900 | |
To Work in Process | $42,900 | ||
(To record job completed) |
In the above Journal entries, Finished Goods Inventory is equal to Total Cost for completion of Job.
Using this information:Answer the following, Please explain briefly. A job order cost sheet for Ryan Company...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...
Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job: Direct materials $13,900 Direct labor 20,000 Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...
A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,300 6,000 4,200 8 6,000 12 7,000 5,600 25 2,500 27 4,000 3,200 13,800 17,000 13,000 Cost of completed job: Direct materials $13,800 Direct labor 17,000 Manufacturing overhead 13,000 Total cost $43,800 Unit cost ($43,800 ÷ 2,000) $21.90 (a) On the basis of the foregoing data, answer the following questions. (1) What...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...