Materials Variances Cinturon Corporation produces high-quality leather belts. The companys plant in Boise uses a standard co

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

Material Price Variance $ -300,500.00 Favourable-F
Material usage variance $         98,000.00 Unfavourable-U
Total Material Variance $ - 202,500.00 Favourable-F

Working

Material Price Variance
( Standard Rate - Actual Rate ) x Actual Quantity
( $                    4.00 - $                     3.00 ) x 300500
300500
Variance $       3,00,500.00 Favourable-F
Material Usage Variance
( Standard Quantity - Actual Quantity ) x Standard Rate
( 276000 - 300500 ) x $              4.00
-98000
Variance $           98,000.00 Unfavourable-U
Material Total Variance
( Standard Cost - Actual Cost )
( $   11,04,000.00 - $       9,01,500.00 )
202500
Variance $       2,02,500.00 Favourable-F

.

Standard DATA for 92000 Belts
Quantity (SQ) Rate (SR) Standard Cost
[A] [B] [A x B]
Direct Material ( 3 strips x 92000 Belts)=276000 strips $                   4.00 $      11,04,000.00

.

Actual DATA for 92000 Belts
Quantity (AQ) Rate (AR) Actual Cost
Direct Material 300500 $            3.00 $      9,01,500.00
Add a comment
Know the answer?
Add Answer to:
Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...

    Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @$4) Direct labor (0.75 hr. $12) Total prime cost During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 281500 strips at $3.60 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 78,500 hours at $14.00...

  • Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...

    Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 290,500 strips at $3.00 per strip. There were no beginning or ending inventories of leather. Actual direct labor...

  • Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...

    Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor $12.00 Leather (3 strips @ $4) Direct labor (0.75 hr. @ $12) Total prime cost 9.00 $21.00 During the first month of the year, the Boise plant produced 92.000 belts. Actual leather purchased was 303,500 strips at $3.60 per strip. There were no beginning or ending inventories of leather. Actual direct labor...

  • Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...

    Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor Leather (3 strips@$4) $12.00 9.00 Direct labor (0.75 hr. @ $12) $21.00 Total prime cost During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 290,500 strips at $3.60 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 80,500...

  • Please answer the incorrect part. Materials Vallances Cinturon Corporation produces high-quality leather belts. The company's plant...

    Please answer the incorrect part. Materials Vallances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 305,500 strips at $3.60 per strip. There were no beginning or ending inventories...

  • Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise...

    Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (4 strips @ $4.00) $16.00 Direct labor (0.25 hr. @ $14.00) 3.50 Total prime cost $19.50 During the first month of the year, the Boise plant produced 35,000 belts. Actual leather purchased was 140,000 strips at $3.00 per strip. There were no beginning or ending inventories of leather....

  • Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...

    Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 287,500 strips at $4.50 per strip. There were no beginning or ending inventories of leather. Actual direct labor...

  • Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise...

    Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (4 strips @ $6.00) $24.00 Direct labor (0.75 hr. @ $13.00) 9.75 $33.75 Total prime cost During the first month of the year, the Boise plant produced 31,000 belts. Actual leather purchased was 130,000 strips at $3.10 per strip. There were no beginning or ending inventories of leather....

  • Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a sta...

    Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips 34) $12.00 Direct labor (0.75 hr. $12) 9.00 Total prime cost $21.00 During the first month of the year, Bolse plant produced 92,000 belts. Actual leather purchased was 287,500 strips at $3.60 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 78,200 hours...

  • Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system...

    Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 287,500 strips at $3.90 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 79,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT