An “integrated” project management approach is one that: Develops new products with the use of multi-functional...

  1. An “integrated” project management approach is one that:
    1. Develops new products with the use of multi-functional teams
    2. Exposes the front-loading of baselines
    3. Allows the project to equate the defined scope with authorized resources, both within the master schedule
    4. Focuses on performance that falls outside of a predetermined baseline
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Develops new products with the use of multi-functional teams

Reason : Integrated project management means that one creates a project which has never done before. Client tells his requirements and according to that one preforms work. Thus new products are created here

Add a comment
Know the answer?
Add Answer to:
An “integrated” project management approach is one that: Develops new products with the use of multi-functional...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT