Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows:
Amber Company produces iron table and chair sets. During October, Ambers costs were as follows: $2.20 per Ib. $7.40 per hour4. Compute the standard direct labor rate for October. (Round your answer to 2 decimal places.) Standard Direct Labor Rate 5.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Total purchases = 1105000*2.20 = $2431000

2. Direct material price variance = (2-2.20)*1105000 = $221000 Unfavorable

3. Material quantity variance = (960000-990000)*2 = $60000 Unfavorable

4. Direct labor price variance = (standard rate - actual rate)*actual hours

5400 = (Standard direct labor rate - 7.40)*9000

Standard direct labor rate = $8 per hour

5. Direct labor efficiency variance = (10000-9000)*8 = $8000 Favorable

Add a comment
Know the answer?
Add Answer to:
Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows: Amber...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance $ 1.30 per lb. $ 6.50 per hour $ 1.10 per lb. 870,000 lbs. 15,000 1,015,000 lbs. 7,000 900,000 lbs. $4,500 F Required: 1. Calculate the total...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance $ 1.90 per lb. $7.10 per hour $ 1.70 per lb. 930,000 lbs. 15,000 1,075,000 lbs. 8,000 960,000 lbs. $5,100 F Required: 1. Calculate the total cost...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance $ 1.30 per lb. $ 6.50 per hour $ 1.10 per lb. 870,000 lbs. 15,000 1,015,000 lbs. 7,000 900,000 lbs. $4,500 F Required: 1. Calculate the total...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price Actual direct labor Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance $ 2.60 per lb. $ 7.80 per hour $ 2.40 per lb. 1,000,000 lbs. 17,000 1,175,000 lbs. 13,000 1,030,000 lbs. $5,800 F Required: 1. Calculate the total cost...

  • Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows: Actual purchase price $ 3.00 per lb. Actual direct labor rate $ 8.20 per hour Standard purchase price $ 2.80 per lb. Standard quantity for sets produced 1,040,000 lbs. Standard direct labor hours allowed 21,000 Actual quantity purchased in October 1,295,000 lbs. Actual direct labor hours 17,000 Actual quantity used in October 1,070,000 lbs. Direct labor rate variance $6,200 F 3. Calculate the direct materials...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price $2.00 per lb. $7.20 per hour $1.80 per lb. 940,000 lbs 15,000 1,085,000 lbs 9,000 970,000 lbs $5,200 F Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance Required: 1. Calculate the total cost of purchases...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: $ 2.10 per lb $7.30 pe...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: $ 2.10 per lb $7.30 per hour $1.90 per lb. 950,000 lbs. 15,000 1,095,000 lbs 10,000 980.000 lbs. $5,300 F Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance Required: 1. Calculate the total cost of...

  • Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: $ 3.00 per lb. $ 8.20...

    Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: $ 3.00 per lb. $ 8.20 per hour $ 2.80 per lb. 1,040,000 bs. 21,000 1,295,000 lbs. 17,000 1,070,000 lbs. $6.200 F Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance Required: 1. Calculate the total...

  • E9-13 Determining Actual Costs, Standard Costs, and Variances [LO 9-3, 9-4] Amber Company produces iron table...

    E9-13 Determining Actual Costs, Standard Costs, and Variances [LO 9-3, 9-4] Amber Company produces iron table and chair sets. During October, Amber's costs were as follows: Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance $ 2.20 per Ib. $ 7.40 per hour $ 2.00 per lb. 960,000 lbs. 10,000 1,105,000...

  • E9-13 Determining Actual Costs, Standard Costs, and Variances [LO 9-3, 94] Amber Company produces iron table...

    E9-13 Determining Actual Costs, Standard Costs, and Variances [LO 9-3, 94] Amber Company produces iron table and chair sets. During October, Amber's costs were as follows $160 per lb. 56.80 per hour $1.40 perib 900,000 Actual purchase price Actual direct labor rate Standard purchase price Standard quantity for sets produced Standard direct labor hours allowed Actual quantity purchased in October Actual direct labor hours Actual quantity used in October Direct labor rate variance 1.045,000 lbs. 10,000 930.000 lbs $4,800 F...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT