Trico Company set the following standard unit costs for its
single product.
Direct materials (30 Ibs. @ $5.00 per Ib.) | $ | 150.00 |
Direct labor (7 hrs. @ $14 per hr.) | 98.00 | |
Factory overhead—variable (7 hrs. @ $7 per hr.) | 49.00 | |
Factory overhead—fixed (7 hrs. @ $9 per hr.) | 63.00 | |
Total standard cost | $ | 360.00 |
The predetermined overhead rate is based on a planned operating
volume of 80% of the productive capacity of 61,000 units per
quarter. The following flexible budget information is
available.
Operating Levels | ||||||
70% | 80% | 90% | ||||
Production in units | 42,700 | 48,800 | 54,900 | |||
Standard direct labor hours | 298,900 | 341,600 | 384,300 | |||
Budgeted overhead | ||||||
Fixed factory overhead | $ | 3,074,400 | $ | 3,074,400 | $ | 3,074,400 |
Variable factory overhead | $ | 2,092,300 | $ | 2,391,200 | $ | 2,690,100 |
During the current quarter, the company operated at 90% of capacity
and produced 54,900 units of product; actual direct labor totaled
316,300 hours. Units produced were assigned the following standard
costs.
Direct materials (1,647,000 Ibs. @ $5.00 per Ib.) | $ | 8,235,000 |
Direct labor (384,300 hrs. @ $14 per hr.) | 5,380,200 | |
Factory overhead (384,300 hrs. @ $16 per hr.) | 6,148,800 | |
Total standard cost | $ | 19,764,000 |
Actual costs incurred during the current quarter follow.
Direct materials (1,364,000 Ibs. @ $7.80 per lb.) | $ | 10,639,200 |
Direct labor (316,300 hrs. @ $11.10 per hr.) | 3,510,930 | |
Fixed factory overhead costs | 2,348,400 | |
Variable factory overhead costs | 2,742,200 | |
Total actual costs | $ | 19,240,730 |
Problem 23-4A Computation of materials, labor, and overhead variances LO P2, P3
Required:
1. Compute the direct materials cost variance,
including its price and quantity variances.
2. Compute the direct labor cost variance,
including its rate and efficiency variances.
3. Compute the overhead controllable and volume
variances.
Standard DATA for | 54900 | units | |
Quantity (SQ) | Rate (SR) | Standard Cost | |
[A] | [B] | [A x B] | |
Direct Material | ( 30lbs x 54900 units)=1647000lbs | $ 5.00 | $ 8,235,000.00 |
Direct labor | ( 7hr x 54900 units)=384300hr | $ 14.00 | $ 5,380,200.00 |
Variable Overhead | ( 7hr x 54900 units)=384300hr | $ 7.00 | $ 2,690,100.00 |
Actual DATA for | 54900 | units | |
Quantity (AQ) | Rate (AR) | Actual Cost | |
Direct Material | 1364000 | $ 7.80 | $ 10,639,200.00 |
Direct labor | 316300 | $ 11.10 | $ 3,510,930.00 |
Variable Overhead | 316300 | $ 8.67 | $ 2,742,200.00 |
Hrs | Rate | Amount | |
Budgeted Fixed Overhead | 341600 | $ 9.00 | $ 3,074,400.00 |
Standard Fixed Overhead or Fixed Overhead absorbed | 384300 | $ 9.00 | $ 3,458,700.00 |
Actual Fixed Overhead incurred | 316300 | $ 7.43 | $ 2,348,700.00 |
1.
Material Cost Variance | ||||||
( | Standard Cost | - | Actual Cost | ) | ||
( | $ 8,235,000.00 | - | $ 10,639,200.00 | ) | ||
-2404200 | ||||||
Variance | $ 2,404,200.00 | Unfavourable-U |
Material Price Variance | ||||||
( | Standard Rate | - | Actual Rate | ) | x | Actual Quantity |
( | $ 5.00 | - | $ 7.80 | ) | x | 1364000 |
-3819200 | ||||||
Variance | $ 3,819,200.00 | Unfavourable-U | ||||
Material Quantity Variance | ||||||
( | Standard Quantity | - | Actual Quantity | ) | x | Standard Rate |
( | 1647000 | - | 1364000 | ) | x | $ 5.00 |
1415000 | ||||||
Variance | $ 1,415,000.00 | Favourable-F |
2.
Labor Cost Variance | ||||||
( | Standard Cost | - | Actual Cost | ) | ||
( | $ 5,380,200.00 | - | $ 3,510,930.00 | ) | ||
1869270 | ||||||
Variance | $ 1,869,270.00 | Favourable-F |
Labor Rate Variance | ||||||
( | Standard Rate | - | Actual Rate | ) | x | Actual Labor Hours |
( | $ 14.00 | - | $ 11.10 | ) | x | 316300 |
917270 | ||||||
Variance | $ 917,270.00 | Favourable-F | ||||
Labour Efficiency Variance | ||||||
( | Standard Hours | - | Actual Hours | ) | x | Standard Rate |
( | 384300 | - | 316300 | ) | x | $ 14.00 |
952000 | ||||||
Variance | $ 952,000.00 | Favourable-F |
3.
Variable Overhead Rate Variance | ||||||
( | Standard Rate | - | Actual Rate | ) | x | Actual Labor Hours |
( | $ 7.00 | - | $ 8.67 | ) | x | 316300 |
-528100 | ||||||
Variance | $ 528,100.00 | Unfavourable-U | ||||
Variable Overhead Efficiency Variance | ||||||
( | Standard Hours | - | Actual Hours | ) | x | Standard Rate |
( | 384300 | - | 316300 | ) | x | $ 7.00 |
476000 | ||||||
Variance | $ 476,000.00 | Favourable-F | ||||
Variable Overhead Spending Variance | ||||||
( | Standard Cost | - | Actual Cost | ) | ||
( | $ 2,690,100.00 | - | $ 2,742,200.00 | ) | ||
-52100 | ||||||
Variance | $ 52,100.00 | Unfavourable-U | ||||
Fixed Overhead Variance | ||||||
( | Standard Fixed Overhead or Fixed Overhead absorbed | - | Actual Fixed Overhead incurred | ) | ||
( | $ 3,458,700.00 | - | $ 2,348,700.00 | ) | ||
1110000 | ||||||
Variance | $ 1,110,000.00 | Favourable-F | ||||
Fixed Overhead Production Volume Variance | ||||||
( | Standard Fixed Overhead or Fixed Overhead absorbed | - | Budgeted Fixed Overhead | ) | ||
( | $ 3,458,700.00 | - | $ 3,074,400.00 | ) | ||
384300 | ||||||
Variance | 384300 | Favourable-F | ||||
Fixed Overhead Production Budget Variance | ||||||
( | Budgeted Fixed Overhead | - | Actual Fixed Overhead incurred | ) | ||
( | $ 3,074,400.00 | - | $ 2,348,700.00 | ) | ||
725700 | ||||||
Variance | 725700 | Favourable-F |
Note no. | Explanation |
1 | Standard data is calculated by considering budgeted data and using actual data. |
2 | Variance refers to the difference between Standard cost and Actual cost. |
3 | If Actual cost is MORE than Standard Cost, the Variance is said to be UNFAVOURABLE. |
4 | If Actual cost is LESS than Standard Cost, the Variance is said to be FAVOURABLE. |
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) $ 150.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $7 per hr.) 49.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 360.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 66,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-Variable (7 hrs. @ $6 per hr.) Factory overhead-Fixed (7 hrs. @ $9 per hr.) Total standard cost $144.00 98.00 42.00 63.00 $347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget information is...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.00 per Ib.) $ 120.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—Variable (7 hrs. @ $7 per hr.) 49.00 Factory overhead—Fixed (7 hrs. @ $11 per hr.) 77.00 Total standard cost $ 344.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 63,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (6 hrs. @ $14 per hr.) 84.00 Factory overhead—variable (6 hrs. @ $7 per hr.) 42.00 Factory overhead—fixed (6 hrs. @ $9 per hr.) 54.00 Total standard cost $ 324.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 57,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...
Trico Company set the following standard unit costs for its single product. Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00 Direct labor (6 hrs. @ $6 per hr.) 36.00 Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00 Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00 Total standard cost $ 177.00 The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...
Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-variable (5 hrs. @ $8 per hr.) Factory overhead-fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is...