Question

Which of the following statements is CORRECT? a. Variable costs need to be considered in the analysis of a capital budgeting
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: b

Both variable and fixed costs should be considered in capital budgeting.

Variable costs directly vary with production units; this includes direct material cost, direct labor cost, variable overhead, etc.

Fixed costs are static irrespective of volume of production; this includes depreciation cost, salary of office staff, and rent of building.

These are required to calculate future net cash flows, which are discounted for present value.

Other options are not correct:

NPV and IRR both are required for expansion or replacement project but there may be conflict between these two methods. Incase of conflict NPV should be preferred than IRR.

Add a comment
Know the answer?
Add Answer to:
Which of the following statements is CORRECT? a. Variable costs need to be considered in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Variable CONES need to be considered in the project, but not fixed costs. b. Variable costs...

    Variable CONES need to be considered in the project, but not fixed costs. b. Variable costs and fixed costs need to be considered in the way capital budgeting project. The NPV criterion is preferable for evaluating expansion projects, IRR criterion is preferable for evaluating replacement projects The IRR criterion is preferable for evaluating expansion projects, while the NVP criterion is preferable for evaluating replacement projects e. None of the above. ii. Accelerated depreciation is usually preferred to straight-line depreciation because...

  • Which of the following statements regarding capital budgeting analysis is not most correct? NPV assumes reinvest...

    Which of the following statements regarding capital budgeting analysis is not most correct? NPV assumes reinvest at the opportunity cost of capital. IRR assumes reinvest at IRR. Reinvest at opportunity cost, r, is more realistic, so NPV method is best. None of the above statements is correct. TIA

  • Question text Which of the following statements is CORRECT? Select one: a. The discounted payback method...

    Question text Which of the following statements is CORRECT? Select one: a. The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. b. The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects. c. The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects....

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The longer a project's payback period, the more desirable the project is normally considered to be by this criterion. b. One drawback of the payback criterion for evaluating projects is that this method does not properly account for the time value of money. c. If a project's payback is positive, then the project...

  • Which of the following statements is CORRECT? The internal rate of return method (IRR) is generally...

    Which of the following statements is CORRECT? The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. The net present value method (NPV) is generally regarded by academics...

  • A key difference between a replacement project analysis and an expansion project analysis is that the...

    A key difference between a replacement project analysis and an expansion project analysis is that the net present value (NPV) technique that is used to evaluate capital budgeting projects should only be used to evaluate expansion projects, whereas either the NPV technique or the internal rate of return (IRR) technique can be used to evaluate replacement projects. True False

  • Which of the following statements is CORRECT? One reason some people prefer the MIRR to the...

    Which of the following statements is CORRECT? One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption. A project’s MIRR can never exceed its IRR. When evaluating mutually exclusive projects, the modified IRR (MIRR) always leads to the same capital budgeting decisions as the NPV method, regardless of the relative lives or sizes of the projects being evaluated. Both the regular and the modified IRR...

  • Which of the following statements is correct? The internal rate of return (IRR) does not allow...

    Which of the following statements is correct? The internal rate of return (IRR) does not allow you to determine whether mutually exclusive projects are acceptable. The net present value (NPV) is the only capital budgeting technique that allows you to determine which independent projects are acceptable. The net present value (NPV) technique provides an indication of the dollar benefit (on a present value basis) to the firm's shareholders of purchasing a capital budgeting project. A project's internal rate of return...

  • 11) Which of the following statements is TRUE about fixed and variable costs? a) Variable costs...

    11) Which of the following statements is TRUE about fixed and variable costs? a) Variable costs are constant in total and fixed costs are constant per unit. b) Both costs are constant when considered on a total basis. c) Both costs are constant when considered on a per unit basis. d) Fixed costs are constant in total and variable costs are constant per unit. Answer: (3 points) TEST 12) Marlowe Company currently leases a delivery truck from Burton Enterprises for...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's regular IRR is found by compounding the cash inflows at the cost of capital to find the terminal value (TV), then discounting this TV at the cost of capital. b. To find a project's IRR, we must find a discount rate that is equal to the cost of capital. c. If...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT