Check my work During March, the company worked 22,000 machine-hours and produced 16,000 units. The company had originally pla
24,000 machine-hours during March. Required: 1. Prepare a flexible budget for March. 2. Prepare a report showing the spending
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

1.) Flexible budget

FAB Corporation

Flexible Budget

For the Month Ended March 31

Machine hours =22,000

Utilities (16,100 +$ 0.14 × 22,000) $19,180
Maintenance (38,300+ $1.50 × 22,000) $71,300
Supplies (0.60 × 22,000) $13,200
Indirect labor (94,400 +$2.10 × 22,000) $140,600
Depreciation $68,400
Total $312,680

2.) Spending variance

FAB Corporation

Spending variance

For the Month Ended March 31

Spending variance Actual Results (given) Flexible Budget (as calculate in part 1)
Utilities $2,080 U $21,260 $19,180
Maintenance $3,200 F $68,100 $71,300
Supplies $1,000 U $14,200

$13,200

Indirect labor $5,100 U $145,700 $140,600
Depreciation $1,700 U $70,100 $68,400
Total $6,680 U $319,360 $312,680
Add a comment
Know the answer?
Add Answer to:
You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing E overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and &#3...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs.:"You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a 'ex ble budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs. You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do w...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT