On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. T
L oure & VILLE DE Complete this question by entering your answers in the tabs below. Req 1 and 3 Reg 2 Calculate the amount o
Required: 1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest metho
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Mason Manufacturing Company
Computation of the interest to be capitalised for 2021- specific interest method
Fraction
Expenditure date Accumulated expd. Num. Den. Avg. accumulated expd.
jan. 1,2021 1090000 12 12 1090000
march 1,2021 780000 10 12 650000
June 30,2021 980000 6 12 490000
Oct. 1, 2021 780000 3 12 195000
3630000 2425000
Total Capitalised interest for 2018 = 3630000 * 16 % = $ 580800
Computation of the interest to be capitalised for 2022 - specific interest method
Fraction
Expenditure date Accumulated expd. Num. Den. Avg. accumulated expd.
Jan. 1, 2022 4210800 9 9 4210800 ( 3630000 + 580800 = 4210800 )
Jan. 31,2022 297000 8 9 264000
April 30, 2022 630000 5 9 350000
Aug. 31, 2022 927000 1 9 103000
6064800 4927800
Weighted Average rate of all other debt
2000000 10% 200000
8000000 12% 960000
10000000 1160000
1160000 / 10000000 = 11.60 %
Interest capitalisation ( 2022 )
3300000 16% 528000 9 divided by 12 396000
1627800 11.60% 188824.8 9 divided by 12 141619
4927800 537619
Cost of building
Expenditures in 2021 3630000
Intt. Capitalised in 2021 580800
Expenditures in 2022 1854000
Intt. Capitalised in 2022 537619
Total cost of building 6602419
Interest expense for 2021
3300000 * 16% = 528000
2000000 * 10 % 200000
8000000 * 12 % 960000
1688000
Less:- Intt. Capitalised in 2021 580800
2021 expense 1107200
Interest expense for 2022
3300000 * 16% = 528000
2000000 * 10 % 200000
8000000 * 12 % 960000
1688000
Less:- Intt. Capitalised in 2022 537619
2022 expense 1150381
The required answers are highlighted in yellow colour.
Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: $1,e9e, eee 780,000 98e, eee 780,eee 297,eee 630,eee 927,e00 January 1, 2021 March 1, 2021 June 30, 2021 October 1, 28e21 January 31, 2022 April 30, 2822 August 31, 2022 es On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1.850,000 1.500.000 1,700,000 1.500.000 405,000 738.000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% Interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office hea...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% Interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $1,850,000 1,500,000 1,700,000 1,500,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 405,000 738,000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,870,000 1,560,000 1,760,000 1,560,000 414,000 747,000 1,044,000 On January 1, 2021, the company obtained a $4,600,000 construction loan with a 15% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT