Question

Problem 15-01A (Part Level Submission) Lott Company uses a job order cost system and applies overhead to production on the ba

1 0
Add a comment Improve this question Transcribed image text
Answer #1
  • Requirement [a]

Predetermined Overhead Rate = ($848400 estimated overhead / $ 707000 estimated direct labor cost) x 100
= (848400 / 707000) x 100
= 120% Answer

Add a comment
Know the answer?
Add Answer to:
Problem 15-01A (Part Level Submission) Lott Company uses a job order cost system and applies overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2-1A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 2-1A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,200, direct labor $12,120, and manufacturing overhead $16,160. As of January 1, Job No. 49 had been completed at a cost of $90,900 and was part of finished goods inventory....

  • Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was a $16,200...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...

  • Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $25,000, direct labor $15,000, and manufacturing overhead $20,000. As of January 1, Job 49 had been completed at a cost of $112,500 and was part of finished goods inventory. There was...

  • Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on...

    Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,400, direct labor $12,240, and manufacturing overhead $16,320. As of January 1, Job 49 had been completed at a cost of $91,800 and was part of finished goods inventory. There was a $15,300 balance in the Raw Materials Inventory account. During the...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,200, direct labor $12,720, and manufacturing overhead $16,960. As of January 1, Job 49 had been completed at a cost of $95,400 and was part of finished goods inventory. There was a $15,900...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,600, direct labor $13,560, and manufacturing overhead $18,080. As of January 1, Job 49 had been completed at a cost of $101,700 and was part of finished goods inventory. There was a $16,950...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT