Problem 16-3A (Part Level Submission)
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows.
c) Cost reconciliation
T12 Tables | ||
Cost accounted for | ||
Transferred out | 691900 | |
Work in process | ||
Material | 62700 | |
Conversion Cost | 35640 | 98340 |
Total Cost | 790240 |
c) Cost reconciliation
C10 Chairs | ||
Cost accounted for | ||
Transferred out | 537246 | |
Work in process | ||
Material | 9900 | |
Conversion Cost | 5944 | 15844 |
Total Cost | 553090 |
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...
Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conver Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July 17,600 Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 550 Cost Data-July Work in process, July 1 Materials Labor Overhead Total 418,000 257,840 114,400 $790,240...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 17,600 550 80 Cost Data-July...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 24,600 19,680 Work in process units, July 31 3,690...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 25,000 20,000 Work in process units, July 31 3,750...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 Production Data-July C10-Chairs T12-Tables Work in process units, July 1 Units started into production 22,000 17,600 Work in process units, July 31 3,300 550 Work...
Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incur uniformly, Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,400 3,360 17,920 560 60...
Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first processin products in two different manufacturing plants are as follows. Cutting Department g two T12-Tabes CIO-Chairs Production Date -July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 17,600 22,000 3,300 Cost Date-July Work in...
Problem 3-3A (Video) (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department T12-Tables Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 0 23,200 3,480 60 Cost Data-July $0 Work in...
Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent...