Question

Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

Problem 16-3A (Part Level Submission)

Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows.

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Work in process units, July 1 0 0
Units started into production 24,600 19,680
Work in process units, July 31 3,690 615
Work in process percent complete 60 80

Cost Data—July

Work in process, July 1

$0 $0

Materials

467,400 354,240

Labor

288,312 135,300

Overhead

127,920 128,904

   Total

$883,632 $618,444

Collapse question part

(a1)

Correct answer. Your answer is correct.
For each plant compute the physical units of production.

T12 Tables

C10 Chairs

Units to be accounted for

Entry field with correct answer24600

Entry field with correct answer19680

For each plant compute equivalent units of production for materials and for conversion costs.

Materials

Conversion Costs

T12 Tables

Entry field with correct answer24600

Entry field with incorrect answer23,124

C10 Chairs

Entry field with correct answer19680

Entry field with incorrect answer19,557

Materials

Conversion Costs

Total Costs

Unit costs-T12 Tables $19Entry field with correct answer $18 $37
Unit costs-C10 Chairs $18 $13.51 $31.51

For each plant show the assignment of costs to units transferred out and in process.

T12 Tables

Costs accounted for:

   Transferred out

$

Entry field with incorrect answer

   Work in process

      Materials

$

Entry field with incorrect answer

      Conversion costs

Entry field with incorrect answer

Entry field with incorrect answer

         Total costs

$883,632Entry field with correct answer

C10 Chairs

Costs accounted for:

   Transferred out

$

Entry field with incorrect answer

   Work in process

      Materials

$

Entry field with incorrect answer

      Conversion costs

Entry field with incorrect answer

Entry field with incorrect answer

         Total costs

$618,444Entry field with correct answer
0 0
Add a comment Improve this question Transcribed image text
Answer #1

For each plant show the assignment of costs to units transferred out and in process.

T12 Tables

Costs accounted for:

   Transferred out (20910*37)

$773670Entry field with incorrect answer

   Work in process

      Materials (3690*19)

$70110

      Conversion costs (2214*18)

Entry field with incorrect answer39852

Entry field with incorrect answer109962

         Total costs

$883,632Entry field with correct answer

C10 Chairs

Costs accounted for:

   Transferred out (19065*31.51)

$600738

   Work in process

      Materials (615*18)

$11070

      Conversion costs (492*13.51)

6646.92

Entry field with incorrect answer17717

         Total costs

$618,444Entry field with correct answer
Add a comment
Know the answer?
Add Answer to:
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 25,000 20,000 Work in process units, July 31 3,750...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...

  • Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are...

    Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first processin products in two different manufacturing plants are as follows. Cutting Department g two T12-Tabes CIO-Chairs Production Date -July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 17,600 22,000 3,300 Cost Date-July Work in...

  • Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In...

    Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent...

  • Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at...

    Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incur uniformly, Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,400 3,360 17,920 560 60...

  • Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture...

    Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conver Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July 17,600 Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 550 Cost Data-July Work in process, July 1 Materials Labor Overhead Total 418,000 257,840 114,400 $790,240...

  • Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data...

    Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data for the first process in making two products in tw Cutting Department Plant 1 Plant 2 Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete T12-Tables c10-Chairs 0 17,500 700 80 G. 19,500 3,100 60 Cost Data-July Work in process, July1 s0 390,000 234, 700 112,240 $0 Materials 280,000 113,000 112,680 Labor Overhead...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 Production Data-July C10-Chairs T12-Tables Work in process units, July 1 Units started into production 22,000 17,600 Work in process units, July 31 3,300 550 Work...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 21,000 16,800 Work in process units, July 31 3,150...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT