Answer
Hazardous Waste Disposal Costs | $620,000 | $ 2.16 | per direct labor hours | ||
No. of DLHs | 287,400 | ||||
Product: | Activity Driver | OH $ per DLH | Total Overhead Costs | Units Produced | OH Cost per unit |
Chairs | 272,000 | 2.16 | $587,520 | 218,000 | $ 2.70 |
Tables | 15,400 | 2.16 | $33,264 | 19,000 | $ 1.75 |
Hazardous Waste Disposal Costs | $620,000 | $ 442.86 | per pound disposed off | ||
No. of pound disposed of | 1,400 | ||||
Product: | Activity Driver | OH $ per DLH | Total Overhead Costs | Units Produced | OH Cost per unit |
Chairs | 600 | $ 442.86 | $265,716 | 218,000 | $ 1.22 |
Tables | 800 | $ 442.86 | $354,288 | 19,000 | $ 18.65 |
--Requirement 3
>Assignment based on Direct Labor hours as there is not much difference between overhead cost per unit for tables and chairs.
Saved Smythe Co. makes furniture. The following data are taken from its production plans for the...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,620,000 630,000 Expected production Direct labor hours required Hazardous waste disposed Chairs 207,000 units 256,000 DLH 400 pounds Tables 14,000 units 16,000 DLH 500 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,380,000 615,000 Expected production Direct labor hours required Hazardous waste disposed Chairs 203,000 units 256,000 DLH 600 pounds Tables 16,000 units 16,000 DLH 700 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,280,000 615,000 Expected production Direct labor hours required Hazardous waste disposed Chairs 211,000 units 262,000 DLH 200 pounds Tables 8,000 units 15,600 DLH 1,100 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,870,000 605,000 Expected production Direct labor hours required Hazardous waste disposed Chairs 217,000 units 268,000 DLH 300 pounds Tables 15,000 units 16,000 DLH 1,100 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs $5,300,000 625,000 Hazardous waste disposal costs Chairs Tables 23,000 units 15,800 DLH 200 pounds 213,000 units 254,000 DLH 600 pounds Expected production Direct labor hours required Hazardous waste disposed Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on di rect labor hours ОН...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs $ 5,600,000 Hazardous waste disposal costs 615,000 Chairs Tables Expected production 205,000 units 17,000 units Direct labor hours required 254,000 DLH 15,800 DLH Hazardous waste disposed 500 pounds 800 pound 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs $5,310,0e0 620,000 Hazardous waste disposal costs Chairs Tables Expected production Direct labor hours required Hazardous waste disposed 218,000 units 272,000 DLH 600 pounds 19,e00 units 15,400 DLH 800 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. 0 Activity...
Smythe Co. makes furniture. The following data are taken from its production plans for the year Direct labor costa Hazardous waste disposal coata $5,900, 000 615,000 Chairs 202,000 units 268,000 DLH 300 pounds Tablea 16,000 units 15, 400 DLH 500 pounda Expected production Direct labor hours required Hazardous waste disposed Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours....
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,820,000 625,000 Expected production Direct labor hours required Hazardous waste disposed Chairs 214,000 units 264,000 DLH 200 pounds Tables 13,000 units 16,200 DLH 300 pounds Required: Rectangutes 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product...
Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costa Hazardous waste disponal conta $5,090,000 610,000 Expected production Direct labor hours required Hazardous waste disponed Chairs 213,000 units 270.000 DLH 200 pounds Tables 16,000 units 15, 200 DLH 400 pounds Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs are assigned using a single plantwide overhead rate based on direct labor hours. Product...