Dear Student , Please see below answer line by line . Below answer little lengthy because in the Question , asked three Variance in part 1 and part 2 . All number are based on Question . Where ever need formula I updated the same and explain also . I used a,b c -- d to easy reference and calculation purpose .
Any doubt,please drop me message
Student as per HomeworkLib policy , I have answered 2 question with 6 sub part . I will provide last one shortly . Please review line wise
Thank you
Alden company uses three - level of Factory Overhead variance | ||||||
32 set up | ||||||
32000 Machine Hrs | ||||||
Manufacture - 6400 unit | ||||||
On the above information basis - calculate | ||||||
Manufacturing hrs / Unit | 5.00 | 32000/6400 | ||||
Total Standard machine hr require to unit Manufacture-Hrs | 24000 | |||||
Manufacturing hrs / Unit | 5.00 | |||||
Number of unit | 4,800 | 24000/5 | ||||
After machine hr base activity , we need to determined Set up per unit | ||||||
Set up | 32 | |||||
Manufacturing unit | 6,400 | |||||
Budgeted unit per set Up | 200 | |||||
Numbe of Unit manufactured based on above set up | 24 | 4800/200 | ||||
Need to derived spending Variance | ||||||
Fixed overhead $ | ||||||
Actual total number of set up | 28 | |||||
Per set up cost $ | 550 | |||||
15,400 | a | |||||
Actual Overhead | ||||||
per machine hr $ | 6 | |||||
Machine hrs actually worked | 27,000 | |||||
1,62,000 | b | |||||
(6*27000) | ||||||
variable OH(a+b) $ | 1,77,400 | |||||
Fixed overhead $ | 2,76,400 | |||||
Actual Overhead $ | 4,96,000 | |||||
Need to derived spending Variance | ||||||
(Variable OH + Fixed OH )- ( actual OH) | ||||||
variable OH(a+b) $ | 1,77,400 | |||||
Fixed overhead $ | 2,76,400 | |||||
Total OH | 4,53,800 | |||||
Less | ||||||
Actual Overhead $ | 4,96,000 | |||||
Spending Variance - $ | -42,200 | Unfavorable | ||||
Efficiency variance | ||||||
Fixed overhead $ | 2,76,400 | |||||
variable OH(a+b) $ | 1,77,400 | |||||
Fixed overhead $ | 2,76,400 | |||||
TotalOH | 4,53,800 | |||||
Number of Unit manufactured based on above set up | 24 | |||||
( As above) | ||||||
Per set up $ | 550 | |||||
Total Standard machine hr require to unit Manufacture-Hrs | 24,000 | |||||
per machine hr $ | 6 | |||||
Efficiency variance $ | -20,200 | Unfavorable | ||||
('24*550)+(6*24000)+ $276400-$453800 | ||||||
Flexible Budget variance | ||||||
This is sum of Spending + Efficiency Variance | ||||||
Spending Var $ | -42,200 | |||||
Efficiency variance $ | -20,200 | |||||
Flexible Budget variance $ | -62,400 | Unfavorable |
Part 2 answer | ||||||
The budgeted total fixed overhead $ | 1,74,000 | |||||
Standard overhead rate per set up $ | 3,750 | |||||
Actual Overhead $ | 4,96,000 | |||||
Actual total number of set up | 28 | |||||
Standard overhead rate per set up $ | 3,750 | |||||
Total ( 28*3750) $ | 1,05,000 | A | ||||
Per machine hr $ | 6 | |||||
Machine hr actually worked hrs | 27,000 | |||||
Total ( 27000*6) $ | 1,62,000 | B | ||||
The budgeted total fixed overhead $ | 1,74,000 | C | ||||
Actual Overhead $ | 4,96,000 | D | ||||
Spending Variance $ | A+B+C-D | |||||
Spending Variance $ | -55,000 | Unfavorable | ||||
Efficiency variance | ||||||
Numbe of Unit manufactured based on above set up | 24 | |||||
( As above) | ||||||
Standard overhead rate per set up $ | 3,750 | |||||
Total ( 24*$3750) $ | 90,000 | A | ||||
Per machine hr $ | 6 | |||||
Total Standard machine hr require to unit Manufacture-Hrs | 24,000 | |||||
Total ( 6*$24000) $ | 1,44,000 | B | ||||
The budgeted total fixed overhead $ | 1,74,000 | C | ||||
As per calculation | ||||||
Total ( as above) | 4,41,000 | D | ||||
($105000+$162000+$174000) | ||||||
Efficiency variance | (A+B+C)-D | |||||
Efficiency variance $ | -33,000 | Unfavorable |
This is sum of Spending + Efficiency Variance | ||
Spending Var $ | -55,000 | |
Efficiency variance $ | -33,000 | |
Flexible Budget variance $ | -88,000 | Unfavorable |
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 26 setups and 26,000 machine hours to manufacture 6,500 units for the year. Selected data for 2019 follow Budgeted fixed factory overhead: $ 54,600 178,000 Setup cost Other $232,600 $481,000 Total factory overhead cost incurred Variable factory overhead rate: $ 400 $6.00 30,000 34,500 Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 28 setups and 28,000 machine hours to manufacture 5,600 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 84,000 Other 186,000 $ 270,000 Total factory overhead cost incurred $ 490,000 Variable factory overhead rate: Per setup $ 850 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 25,000 hours Machine hours actually worked...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40 setups and 40,000 machine hours to manufacture 8,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 76,800 Other 230,000 $ 306,800 Total factory overhead cost incurred $ 484,000 Variable factory overhead rate: Per setup $ 550 Per machine hour $ 4.00 Total standard machine hours allowed for the units manufactured 28,000 hours Machine hours actually worked...
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 20 setups and 20,000 machine hours to manufacture 5,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 57,000 Other 184,000 $ 241,000 Total factory overhead cost incurred $ 491,000 Variable factory overhead rate: Per setup $ 800 Per machine hour $ 6.00 Total standard machine hours allowed for the units manufactured 24,000 hours Machine hours actually worked...
Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 376,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,200 machine hours and incurred $637,000 in total manufacturing overhead cost to manufacture 42,010 units. Actual fixed overhead cost for the year was $386,000. Required: Determine for...
Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead 40,000 units 2 $3.00 per machine hour $352,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 87,000 machine hours and incurred $619,000 in total manufacturing overhead cost to manufacture 42,190 units. Actual fixed overhead cost for the year was $371,000. Required: Determine for the...
Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 296,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 86,300 machine hours and incurred $565,000 in total manufacturing overhead cost to manufacture 42,120 units. Actual fixed overhead cost for the year was $308,000. Required: Determine for...
Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $368,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 88,000 machine hours and incurred $636,000 in total manufacturing overhead cost to manufacture 43,000 units. Actual fixed overhead cost for the year was $380,000. Required: Determine for the year:...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $840,000, of which $595,000 is fixed overhead. A total of 119,300 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $262,000, and...