Question

Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32 setups and 3Required: 1. Compute: (a) the total overhead spending variance, (b) the overhead efficiency variance, and (c) the total overhCompute: (a) the total overhead spending variance, (b) the overhead efficiency variance, and (c) the total overhead flexible-Assume that the company uses only machine hours as the activity measure to apply both variable and fixed overhead, and that iAssume that the company uses only machine hours as the activity measure to apply both variable and fixed overhead, and that i

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Dear Student , Please see below answer line by line . Below answer little lengthy because in the Question , asked three  Variance  in part 1 and part 2 . All number are based on Question . Where ever need formula I updated the same and explain also . I used a,b c -- d to easy reference and calculation purpose .

Any doubt,please drop me message

Student as per HomeworkLib policy , I have answered 2 question with 6 sub part . I will provide last one shortly . Please review line wise

Thank you

Alden company uses three - level of Factory Overhead variance
32 set up
32000 Machine Hrs
Manufacture - 6400 unit
On the above information basis - calculate
Manufacturing hrs / Unit 5.00 32000/6400
Total Standard machine hr require to unit Manufacture-Hrs 24000
Manufacturing hrs / Unit 5.00
Number of unit           4,800 24000/5
After machine hr base activity , we need to determined Set up per unit  
Set up                         32
Manufacturing unit           6,400
Budgeted unit per set Up                            200
Numbe of Unit manufactured based on above set up                     24 4800/200
Need to derived spending Variance  
Fixed overhead $
Actual total number of set up                              28
Per set up cost $                            550
                     15,400 a
Actual Overhead
per machine hr $                                 6
Machine hrs actually worked                      27,000
                 1,62,000 b
(6*27000)
variable OH(a+b) $                  1,77,400
Fixed overhead $                  2,76,400
Actual Overhead $                  4,96,000
Need to derived spending Variance  
(Variable OH + Fixed OH )- ( actual OH)
variable OH(a+b) $ 1,77,400
Fixed overhead $ 2,76,400
Total OH   4,53,800
Less  
Actual Overhead $ 4,96,000
Spending Variance - $     -42,200 Unfavorable  
Efficiency variance  
Fixed overhead $ 2,76,400
variable OH(a+b) $ 1,77,400
Fixed overhead $ 2,76,400
TotalOH 4,53,800
Number of Unit manufactured based on above set up                     24
( As above)
Per set up $                  550
Total Standard machine hr require to unit Manufacture-Hrs            24,000
per machine hr $                                 6
Efficiency variance $           -20,200 Unfavorable  
('24*550)+(6*24000)+ $276400-$453800
Flexible Budget variance  
This is sum of Spending + Efficiency Variance  
Spending Var $ -42,200
Efficiency variance $ -20,200
Flexible Budget variance $ -62,400 Unfavorable  
Part 2 answer
The budgeted total fixed overhead $                  1,74,000
Standard overhead rate per set up $                        3,750
Actual Overhead $                  4,96,000
Actual total number of set up                              28
Standard overhead rate per set up $                        3,750
Total ( 28*3750) $                  1,05,000 A
Per machine hr $                                 6
Machine hr actually worked hrs                      27,000
Total ( 27000*6) $                  1,62,000 B
The budgeted total fixed overhead $                  1,74,000 C
Actual Overhead $                  4,96,000 D
Spending Variance $ A+B+C-D
Spending Variance $                    -55,000 Unfavorable  
Efficiency variance  
Numbe of Unit manufactured based on above set up                           24
( As above)
Standard overhead rate per set up $                        3,750
Total ( 24*$3750) $                      90,000 A
Per machine hr $                       6
Total Standard machine hr require to unit Manufacture-Hrs             24,000
Total ( 6*$24000) $         1,44,000 B
The budgeted total fixed overhead $         1,74,000 C
As per calculation  
Total ( as above)             4,41,000 D
($105000+$162000+$174000)
Efficiency variance   (A+B+C)-D
Efficiency variance $               -33,000 Unfavorable  
This is sum of Spending + Efficiency Variance  
Spending Var $               -55,000
Efficiency variance $               -33,000
Flexible Budget variance $               -88,000 Unfavorable  
Add a comment
Know the answer?
Add Answer to:
Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 32...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity i...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 26 setups and 26,000 machine hours to manufacture 6,500 units for the year. Selected data for 2019 follow Budgeted fixed factory overhead: $ 54,600 178,000 Setup cost Other $232,600 $481,000 Total factory overhead cost incurred Variable factory overhead rate: $ 400 $6.00 30,000 34,500 Per setup Per machine hour Total standard machine hours allowed for the units manufactured Machine hours actually worked Actual total number...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 28...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 28 setups and 28,000 machine hours to manufacture 5,600 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 84,000 Other 186,000 $ 270,000 Total factory overhead cost incurred $ 490,000 Variable factory overhead rate: Per setup $ 850 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 25,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40 setups and 40,000 machine hours to manufacture 8,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 76,800 Other 230,000 $ 306,800 Total factory overhead cost incurred $ 484,000 Variable factory overhead rate: Per setup $ 550 Per machine hour $ 4.00 Total standard machine hours allowed for the units manufactured 28,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 20...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 20 setups and 20,000 machine hours to manufacture 5,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 57,000 Other 184,000 $ 241,000 Total factory overhead cost incurred $ 491,000 Variable factory overhead rate: Per setup $ 800 Per machine hour $ 6.00 Total standard machine hours allowed for the units manufactured 24,000 hours Machine hours actually worked...

  • Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000...

    Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 376,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,200 machine hours and incurred $637,000 in total manufacturing overhead cost to manufacture 42,010 units. Actual fixed overhead cost for the year was $386,000. Required: Determine for...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead 40,000 units 2 $3.00 per machine hour $352,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 87,000 machine hours and incurred $619,000 in total manufacturing overhead cost to manufacture 42,190 units. Actual fixed overhead cost for the year was $371,000. Required: Determine for the...

  • Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000...

    Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 296,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 86,300 machine hours and incurred $565,000 in total manufacturing overhead cost to manufacture 42,120 units. Actual fixed overhead cost for the year was $308,000. Required: Determine for...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $368,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 88,000 machine hours and incurred $636,000 in total manufacturing overhead cost to manufacture 43,000 units. Actual fixed overhead cost for the year was $380,000. Required: Determine for the year:...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $840,000, of which $595,000 is fixed overhead. A total of 119,300 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $262,000, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT