Question

The following data apply to questions 6-8. Zeta Company budgets the following amounts for its Buildings & Grounds and Compute
Fixed Variable Buildings & Grounds $ 50,000 $90,000 Computer Services $100,000 $21,000 6. Total fixed costs allocated from Bu
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. Thanks!
Zeta Company Budgeted usages
Answer 6
Direct Method Building & Grounds Computer Signs Mailers Total
Building & Grounds                      0.20                        0.60                0.20                1.00
Building & Grounds %                        0.75                0.25                1.00
Fixed cost                   50,000.00      50,000.00
Allocation                 (50,000.00)              37,500.00     12,500.00                    -  
So answer is $ 37,500. Option D
Answer 7 Budgeted usages
Step Down Method Building & Grounds Computer Signs Mailers Total
Building & Grounds                      0.20                        0.60                0.20                1.00
Variable cost                   90,000.00      90,000.00
Allocation                 (90,000.00)            18,000.00              54,000.00     18,000.00                    -  
Computer Services                             0.15                        0.30                0.55                1.00
Computer Services %                        0.35                0.65                1.00
Variable cost            21,000.00      21,000.00
Total Variable cost            39,000.00
Allocation          (39,000.00)              13,764.71     25,235.29                    -  
So answer is $ 25,235. Option C
Answer 8 Budgeted usages
Reciprocal Method Building & Grounds Computer Signs Mailers Total
Building & Grounds                      0.20                        0.60                0.20                1.00
Computer Services                             0.15                        0.30                0.55                1.00
Variable cost                   90,000.00            21,000.00 111,000.00
Let variable cost of Building & Grounds be B&G and variable cost of Computer Services be CS.
So, CS= 21000+ 0.20 of B&G Option D
Add a comment
Know the answer?
Add Answer to:
The following data apply to questions 6-8. Zeta Company budgets the following amounts for its Buildings...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT