Question

ACC 321 BBAs#5 - Problem (chapter 8) The following information was taken from the annual manufacturing overhead cost Budget o

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A)Overhead Rates =Estimated overhead /Estimated direct labor hours

Variable [33000/16500] $ 2 per DLH
Fixed      [20625/16500] $ 1.25 per DLH
Predetermined overhead rate $ 3.25 per DLH

B)

Applied overhead =Actual Output *standard hours per unit * Overhead rate

Standard hours per unit = 16500 / 4125 = 4 Hours per unit

Variable [4000*4*2] 32000
Fixed      [4000*4*1.25] 20000
Total Applied overhead 52000

C)

manufacturing overhead
Actual 54000 Applied 52000
Balance 2000 UnderApplied

Overhead is Under Applied by 2000

D)

Variable Fixed
Spending Variance

Actual cost -[Actual Hours *Standard variable overhead rate]

33375 - [16100*2]

33375- 32200

1175 U

Actual cost-Budgeted cost

20625 - 20625

0 None

Efficiency variance

Standard variable overhead rate[Actual hours -standard hours for actual output]

2[16100 - 16000]

2 * 100

200 U

-
Volume variance -

Budgeted fixed overhead -Applied fixed overhead

20625-20000

625 U

Total Variance 1375 U 625 U

Standard hours per unit = 16500 / 4125 = 4 Hours per unit

standard hours for actual output =Actual output 4000 units * 4 = 16000

e)

All of the variance calculated comes out to be unfavorable (neither is favorable ) So it means Management or production department is inefficient in their workings.

Production department is responsible for all such variances.

Add a comment
Know the answer?
Add Answer to:
ACC 321 BBAs#5 - Problem (chapter 8) The following information was taken from the annual manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information was taken from the annual manufacturing overhead cost budget of Waterway Industries. Variable...

    The following information was taken from the annual manufacturing overhead cost budget of Waterway Industries. Variable manufacturing overhead costs $52800 Fixed manufacturing overhead costs $26400 Normal production level in labor hours 22000 Normal production level in units 5500 Standard labor hours per unit 4 During the year, 5325 units were produced, 17240 hours were worked, and the actual manufacturing overhead was $78600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of...

  • The following information was taken from the annual manufacturing overhead cost budget of Sunland Company Variable...

    The following information was taken from the annual manufacturing overhead cost budget of Sunland Company Variable manufacturing overhead costs $46600 Fixed manufacturing overhead costs $27960 Normal production level in labor hours 23300 Normal production level in units Standard labor hours per unit 5825 4 During the year, 5650 units were produced, 18540 hours were worked, and the actual manufacturing overhead was $75600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of...

  • Predetermined OH Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine...

    Predetermined OH Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours: 40,000 44,000 48,000 52,000 Variable manufacturing overhead $80,000 $88,000 $96,000 $104,000 Fixed manufacturing overhead 325,000 325,000 325,000 325,000 Each product requires four hours of machine time, and the company expects to produce 10,000 units for the year. Production is expected to be evenly distributed throughout the year. a. Calculate separate predetermined variable and fixed OH rates using as the basis of application (1)...

  • Mercuri Company has gathered the following information: Variable manufacturing overhead costs $13,680 Fixed manufacturing overhead costs...

    Mercuri Company has gathered the following information: Variable manufacturing overhead costs $13,680 Fixed manufacturing overhead costs $10,710 Normal production level in labour hours 9,000 Standard labour hours 9,500 During the year, 3,050 units were produced, 10,900 hours were worked, and the actual manufacturing overhead was $21,800. Actual fixed overhead totalled $10,800. Mercuri applies overhead based on direct labour hours. Calculate the total, fixed, and variable predetermined overhead rates.(Round answers to 2 decimal places, e.g. 15.25.) Fixed predetermined ovehead rate $...

  • Just need the Manufacturing Overhead, Is this correct way to set it up? Morton Company's budgeted...

    Just need the Manufacturing Overhead, Is this correct way to set it up? Morton Company's budgeted variable manufacturing overhead is $2.50 per direct labor-hour and its budgeted fixed manufacturing overhead is $360,000 per year. The company manufactures a single product whose standard direct labor-hours per unit is 3.5 hours. The standard direct labor wage rate is $10 per hour. The standards also allow 2 feet of raw material per unit at a standard cost of $6 per foot. Although normal...

  • Chubbs Inc.’s manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable Costs I...

    Chubbs Inc.’s manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable Costs Indirect materials$11,200 Indirect labor10,600 Utilities7,000 Maintenance5,700 Fixed Costs Supervisory salaries$35,600 Depreciation7,000 Property taxes and insurance7,100 Maintenance5,500 Actual variable costs were indirect materials $14,500, indirect labor $9,600, utilities $9,400, and maintenance $5,200. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $8,200. The actual activity level equaled the budgeted level. (a) Prepare a manufacturing overhead flexible budget report for...

  • 19. Gina Production Limited uses a standard costing system. The following information perta to 2011: Actual...

    19. Gina Production Limited uses a standard costing system. The following information perta to 2011: Actual overhead costs ($16,500 is fixed) $ 40,125 Actual direct labour costs (11,250 hours) $131,625 Standard direct labour for 5,500 units: Standard hours allowed 11,000 hours Labour rate $12.00 The overhead rate is based on an activity level of 10,000 hours. Standard cost data for 5,000 units is as follows: Variable overhead Fixed overhead Total overhead $22,500 13,500 $36.000 What is the fixed overhead volume...

  • Exercise 10-10 (Video) Chubbs Inc.’s manufacturing overhead budget for the first quarter of 2020 contained the following...

    Exercise 10-10 (Video) Chubbs Inc.’s manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable Costs Fixed Costs Indirect materials $11,300 Supervisory salaries $37,000 Indirect labor 10,000 Depreciation 6,100 Utilities 7,200 Property taxes and insurance 7,300 Maintenance 5,500 Maintenance 4,200 Actual variable costs were indirect materials $14,600, indirect labor $9,400, utilities $9,200, and maintenance $4,800. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $8,200. The actual activity level equaled the...

  • Chubbs Inc's manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable...

    Chubbs Inc's manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable Costs Fixed Costs Indirect materials $11300 Supervisory salaries $37,000 Indirect labor 10,800 Depreciation 6,000 Property taxes and insurance Utilities 7,200 7,400 Maintenance 5,900 Maintenance 5,000 Actual variable costs were indirect materials $14,600, indirect labor $9.400, utilities $9.600, and maintenance $5,100. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $8,700. The actual activity level equaled the budgeted level. All...

  • Sunland Inc.'s manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable...

    Sunland Inc.'s manufacturing overhead budget for the first quarter of 2020 contained the following data. Variable Costs Fixed Costs Indirect materials $11,100 Supervisory salaries Indirect labor 10,700 Depreciation Utilities 7,800 Property taxes and insurance Maintenance 5,700 Maintenance $35,400 7,500 7,300 4,000 Actual variable costs were indirect materials $15, 100, indirect labor $9,500, utilities $9.600, and maintenance $5,200. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $8,300. The actual activity level equaled the budgeted level....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT