Question

Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements:

  1. The finished goods inventory on hand at the end of each month must equal 4,000 units of Supermix plus 20% of the next month’s sales. The finished goods inventory on June 30 is budgeted to be 19,000 units.

  2. The raw materials inventory on hand at the end of each month must equal one-half of the following month’s production needs for raw materials. The raw materials inventory on June 30 is budgeted to be 114,000 cc of solvent H300.

  3. The company maintains no work in process inventories.

A monthly sales budget for Supermix for the third and fourth quarters of the year follows.

Budgeted Unit Sales
July 75,000
August 80,000
September 90,000
October 70,000
November 60,000
December 50,000

Required:

1. Prepare a production budget for Supermix for the months July, August, September, and October.

3. Prepare a direct materials budget showing the quantity of solvent H300 to be purchased for July, August, and September, and for the quarter in total.

1 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Pearl Products Limited
Production Budget
July August September October
Budgeted unit sales 75000 80000 90000 70000
Add: Desired units of ending finished goods inventory 20000 22000 18000 16000
Total needs 95000 102000 108000 86000
Less: Units of beginning finished goods inventory 19000 20000 22000 18000
Required production in units 76000 82000 86000 68000
3
Pearl Products Limited
Direct Materials Budget
July August September Third Quarter
Units of raw materials needed to meet production 228000 246000 258000 732000
Add: Desired units of ending raw materials inventory 123000 129000 102000 102000
Total units of raw materials needed 351000 375000 360000 834000
Less: Units of beginning raw materials inventory 114000 123000 129000 114000
Units of raw materials to be purchased 237000 252000 231000 720000
Add a comment
Know the answer?
Add Answer to:
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...

  • Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic cen...

    Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT