3-17 Based on UIN MIT overhead for the actual level UI Calculating factory overhead: two variances Munoz Manufacturing Co. no
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Flexibke buget variance is $16500.

2. The production volume variance is 2000 units unfavourable(Actual units - Budgeted Units)

3. Factory overhead is underappliedby $11500.(Variablecost - $28500-$40000)

Actual Budgeted
Production 8000 units 8000 units
Direct labour hour used 13500 16000
Variable cost 28500 40000
Fixed Cost 52000 24000
80500 64000
16500
Add a comment
Know the answer?
Add Answer to:
3-17 Based on UIN MIT overhead for the actual level UI Calculating factory overhead: two variances...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • E8-17 Calculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of prod- uct...

    E8-17 Calculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of prod- uct X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are $2.50 and $1.50 per direct labor hour, respectively. Cost and production data for May follow: Production for the month... 9,000 units Direct labor hours used ..... 18,500 hours Factory...

  • Exercise 8-17 Calculating Factory Overhead: Two Variances Munoz Manufacturing Co. normally produces 10,000 units of product...

    Exercise 8-17 Calculating Factory Overhead: Two Variances Munoz Manufacturing Co. normally produces 10,000 units of product X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are $2.50 and $1.50 per direct labor hour, respectively. Cost and production data for May follow: Production for the month 9,000 units Direct labor hours used. 18,500 hours Factory overhead...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $124,200 Fixed factory overhead 52,000 Standard: 8,000 hrs. at $20 160,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $180,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...

    Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...

  • The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.05 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $8,000 The amount of the fixed factory overhead volume variance is a. $988 unfavorable b. $790 unfavorable c. $790 favorable d. $0

  • Question text Lance Production Company has the following information: Standard fixed factory overhead rates per direct...

    Question text Lance Production Company has the following information: Standard fixed factory overhead rates per direct labor-hour $1.50 Standard variable factory overhead rates per direct labor-hour $5.00 Actual number of units produced 6,000 units Actual factory overhead costs (includes $70,000 fixed) $78,000 Actual direct labor hours 6,000 hours Standard factory overhead rates are based on a normal monthly volume of 5,000 units (1 standard direct labor-hour per unit). What is Lance's variable overhead efficiency variance? Select one: A. $3,000 (F)...

  • The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.02 per hour Actual Costs     Total variable cost, $18,200     Total fixed cost, $8,100 The amount of the total factory overhead cost variance is a.$4,726 favorable b.$3,282 favorable c.$3,282 unfavorable d.$1,838 unfavorable

  • Problem 11A-8 Applying Overhead; Overhead Variances [LO11-3, LO11-4] Lane Company manufactures a ...

    Problem 11A-8 Applying Overhead; Overhead Variances [LO11-3, LO11-4] Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. Variable manufacturing overhead should be $2.40 per standard direct labor-hour and fixed manufacturing overhead should be $384,000 per year. The company's product requires 4 pounds of material that has a standard cost of $4.00 per pound and 1.5 hours of direct labor time that has a standard...

  • Overhead Application, Overhead Variances, Journal Entries Plimpton Company produces countertop ovens. Plimpton uses a standard costing...

    Overhead Application, Overhead Variances, Journal Entries Plimpton Company produces countertop ovens. Plimpton uses a standard costing system. The standard costing system relies on direct labor hours to assign overhead costs to production. The direct labor standard indicates that two direct labor hours should be used for every oven produced. The normal production volume is 100,000 units. The budgeted overhead for the coming year is as follows: Fixed overhead $770,000 Variable overhead 446,000* *At normal volume. Plimpton applies overhead on the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT