Question text
Lance Production Company has the following information:
Standard fixed factory overhead rates per direct labor-hour |
$1.50 |
Standard variable factory overhead rates per direct labor-hour |
$5.00 |
Actual number of units produced |
6,000 units |
Actual factory overhead costs (includes $70,000 fixed) |
$78,000 |
Actual direct labor hours |
6,000 hours |
Standard factory overhead rates are based on a normal monthly
volume of 5,000 units (1 standard direct labor-hour per
unit).
What is Lance's variable overhead efficiency variance?
Select one:
A. $3,000 (F)
B. $4,000 (F)
C. $-0-
D. $6,000 (U)
Answer:-The correct option is C.$-0-.
Explanation:-
Variable Overhead Efficiency Variance= (Standard Hour-Actual Hour)* Standard Variable Overhead Rate
=((6,000 units *1)-6,000 hours) *$5
=0*$5
=$0
Kindly give thumbs up if u like my answer...Thanks!!!
Question text Lance Production Company has the following information: Standard fixed factory overhead rates per direct...
1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...
Harrangue Company's standard variable overhead rate is $6 per direct labor hour, and each unit requires 2 standard direct labor hours. During March, Harry recorded 6,000 actual direct labor hours, $37,000 actual variable overhead costs, and 2,900 units of product manufactured. What is the variable overhead efficiency variance for March for Harrangue? a.$2,200 (U) b.$1,200 (U) c.$600 (U) d.$2,200 (F) Synergy Manufacturing Company has a normal monthly activity of 7,500 units. Standard factory overhead rates are based on a normal...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
its of product w as Direct Materials. Direct Labor and Factory Overhead Cost lance is Macdna in processes a base chemical into plastic Standard costs and actual costs for Srect materials direct labor, and factory overhead incurred for the manufacture of Standard Costs Actual Costs Direct materials 207,200 lbs. at $5.00 205100 $4.80 Direct labor 15,500 $18.70 18.050 $18.90 Factory overhead Rates per direct labore based on 100% of a Capacity of 19.310 direct Variate , 3.20 Fedo, 15.10 158,610...
1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information. Direct labor (10,000 hours at $15 per hour) $150,000 Variable overhead $30,000 Fixed overhead $80,000 During May, 6,000 units were produced and the direct labor efficiency variance was $1,500 unfavorable. Based on this information, the actual number of direct labor hours used in...
14) Switsdorf Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable overhead costs. Actual variable overhead costs Standard variable overhead costs Actual direct labor hours Standard direct labor hours per unit Units produced $5,120 $3.00 per hour 2,000 hours 3 hours 1,000 What is the variable overhead efficiency variance? A) $2,000 Favorable C) $1,000 Favorable B) $3,000 Favorable D) $2,000 Unfavorable
Corporation makes a product with the following standards for direct labor and variable overhead: Standard Quantity or Hours Standard Price or Rate Direct labor 0.50 hours $ 30.00 per hour Variable overhead 0.50 hours $ 5.00 per hour In August the company produced 8,900 units using 4,620 direct labor-hours. The actual variable overhead cost was $21,714. The company applies variable overhead on the basis of direct labor-hours. The variable overhead efficiency variance for August is:
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.80 per direct labor-hour and the budgeted fixed manufacturing overhead is $612,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $5.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.40 per hour. The company planned to operate at a...
Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. $2.10 per Ib.) Direct labor (10 hrs. $8.80 per hr.1) Factory variable overhead (10 hrs. $4.00 per hr. Factory tixed overhead (10 hr. $1.80 per hr.) Standard cost s 42.00 88.00 40.00 18.00 $188.00 The $5.80 ($4.00+$1.80) total overhead rate per direct labor hour is based on an expected operating level equal to 70% of the factory's capacity of 70,000 units...
Chrisman Corporation makes a product with the following standard costs: Inputs Direct materials Direct labor Variable overhead Standard Quantity or Hours 8.8 pounds 1.4 hours 1.4 hours Standard Price or Rate $2.00 per pound $20.00 per hour $10.00 per hour The company reported the following results concerning this product in August. Actual output Raw materials used in production Raw materials purchased Actual direct labor hours Actual cost of raw materials purchased Actual cost of direct labor Actual cost of variable...