Question

Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $315,000, has a 4-year life, and requires $113,000 in pretax annual operating costs. System B costs $395,000, has a 6-year life, and requires $107,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 25 percent and the discount rate is 9 percent.

Calculate the EAC for both conveyor belt systems. (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Which conveyor belt system should the firm choose?
  • System B

  • System A

0 0
Add a comment Improve this question Transcribed image text
Answer #1

System A

Time line 0 1 2 3 4
Cost of new machine -315000
=Initial Investment outlay -315000
100.00%
Sales 0 0 0 0
Profits Sales-variable cost 0 0 0 0
Operating cost -113000 -113000 -113000 -113000
-Depreciation Cost of equipment/no. of years -78750 -78750 -78750 -78750 0 =Salvage Value
=Pretax cash flows -191750 -191750 -191750 -191750
-taxes =(Pretax cash flows)*(1-tax) -143812.5 -143812.5 -143812.5 -143812.5
+Depreciation 78750 78750 78750 78750
=after tax operating cash flow -65062.5 -65062.5 -65062.5 -65062.5
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -315000 -65062.5 -65062.5 -65062.5 -65062.5
Discount factor= (1+discount rate)^corresponding period 1 1.09 1.1881 1.295029 1.4115816
Discounted CF= Cashflow/discount factor -315000 -59690.367 -54761.8046 -50240.1877 -46091.92
NPV= Sum of discounted CF= -525784.27
Year or period 0 1 2 3 4
EAC -162293.127 -162293.127 -162293.127 -162293.1
Discount factor= (1+discount rate)^corresponding period 1.09 1.1881 1.295029 1.4115816
Discounted CF= Cashflow/discount factor -148892.777 -136598.878 -125320.072 -114972.5
NPV= -525784.27
EAC is equivalent yearly CF with same NPV = -162293.13

System B

Time line 0 1 2 3 4 5 6
Cost of new machine -395000
=Initial Investment outlay -395000
100.00%
Sales 0 0 0 0 0 0
Profits Sales-variable cost 0 0 0 0 0 0
Operating cost -107000 -107000 -107000 -107000 -107000 -107000
-Depreciation Cost of equipment/no. of years -65833.3333 -65833.3333 -65833.3333 -65833.33 -65833.33 -65833.33 5.82077E-11 =Salvage Value
=Pretax cash flows -172833.333 -172833.333 -172833.333 -172833.3 -172833.3 -172833.3
-taxes =(Pretax cash flows)*(1-tax) -129625 -129625 -129625 -129625 -129625 -129625
+Depreciation 65833.33333 65833.33333 65833.33333 65833.333 65833.333 65833.333
=after tax operating cash flow -63791.67 -63791.67 -63791.67 -63791.67 -63791.67 -63791.67
+Tax shield on salvage book value =Salvage value * tax rate 1.455E-11
=Terminal year after tax cash flows 0
Total Cash flow for the period -395000 -63791.67 -63791.67 -63791.67 -63791.67 -63791.67 -63791.67
Discount factor= (1+discount rate)^corresponding period 1 1.09 1.1881 1.295029 1.4115816 1.538624 1.6771001
Discounted CF= Cashflow/discount factor -395000 -58524.4679 -53692.1724 -49258.8737 -45191.63 -41460.21 -38036.89
NPV= Sum of discounted CF= -681164.24
Year or period 0 1 2 3 4 5 6
EAC -151844.985 -151844.985 -151844.985 -151845 -151845 -151845
Discount factor= (1+discount rate)^corresponding period 1.09 1.1881 1.295029 1.4115816 1.538624 1.6771001
Discounted CF= Cashflow/discount factor -139307.325 -127804.886 -117252.189 -107570.8 -98688.82 -90540.2
NPV= -681164.24
EAC is equivalent yearly CF with same NPV = -151844.98

Choose System B as it has smaller EAC

Add a comment
Know the answer?
Add Answer to:
Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

    Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $315,000, has a 4-year life, and requires $113,000 in pretax annual operating costs. System B costs $395,000, has a 6-year life, and requires $107,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever project is chosen, it will not be replaced when it wears out. The tax...

  • Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

    Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $320,000, has a 4-year life, and requires $117,000 in pretax annual operating costs. System B costs $400,000, has a 6-year life, and requires $111,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 21 percent and the discount rate is 10 percent. Calculate the...

  • Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

    Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System Acosts $365,000, has a 4-year life, and requires $153,000 in pretax annual operating costs. System B costs $445,000, has a 6-year life, and requires $147,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system, when one wears out, it must be replaced. Assume the tax rate is 25 percent and the discount rate is 11 percent. Calculate the EAC...

  • Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

    Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $290,000, has a 4-year life, and requires $93,000 in pretax annual operating costs. System B costs $370,000, has a 6-year life, and requires $87,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever project is chosen, it will not be replaced when it wears out. The tax...

  • Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System...

    Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $212,000, has a four-year life, and requires $68,000 in pretax annual operating costs. System B costs $300,000, has a six-year life, and requires $62,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever system is chosen, it will not be replaced when it wears out. The tax...

  • Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems, System...

    Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems, System A costs $240,000, has a four-year life and requires $75.000 in pretax annual operating costs System B costs $340,000, has a six-year life, and requires $69.000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over the lives and will have zero salvage Value Whichever project is chosen, it will not be replaced when it wears out. The tax...

  • Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System...

    Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $280,000, has a four-year life, and requires $85,000 in pretax annual operating costs. System B costs $396,000, has a six-year life, and requires $79,000 in pretax annual operating costs. Suppose LISC always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 35 percent and the discount rate is 9 percent. Calculate the EAC...

  • Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System...

    Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $360,000, has a four-year life, and requires $149,000 in pretax annual operating costs. System B costs $440,000, has a six-year life, and requires $143,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 24 percent and the discount rate is 10 percent. Calculate the...

  • Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System...

    Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $340,000, has a four-year life, and requires $133,000 in pretax annual operating costs. System B costs $420,000, has a six-year life, and requires $127,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 25 percent and the discount rate is 10 percent. Calculate the...

  • Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System...

    Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $335,000, has a four-year life, and requires $129,000 in pretax annual operating costs. System B costs $415,000, has a six-year life, and requires $123,000 in pretax annual operating costs. Suppose the company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 24 percent and the discount rate is 9 percent. Calculate the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT