1) Predetermine overhead rate = 100800/84000 = 120% of direct material used
2) Overhead applied = (26000+132000-17000)*1.2 = 169200
Actual overhead = 173600
Under applied overhead = 173600-169200 = 4400
3) Schedule of cost of goods manufactured
Direct material | ||
Beginning raw material | 26000 | |
Raw material purchase | 132000 | |
Raw material available for use | 158000 | |
Less; Ending raw material | -17000 | |
Material used | 141000 | |
Direct labor | 80000 | |
Manufacturing overhead | 169200 | |
Total manufacturing cost | 390200 | |
Beginning work in process | 49000 | |
Total cost of work in process | 439200 | |
Less: Ending work in process | -37000 | |
Cost of goods manufactured | 402200 | |
4) Unadjusted cost of goods sold = 71000+402200-56000 = 417200
5) Calculate following
Direct material | 8800 |
Direct labor | 17640 |
Manufacturing overhead (8800*1.2) | 10560 |
Ending work in process | 37000 |
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $130,200 of manufacturing overhead for an estimated allocation base of $93,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 137,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $117,000 of manufacturing overhead for an estimated allocation base of $90,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 137,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $111,800 of manufacturing overhead for an estimated allocation base of $86,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 136,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $123,200 of manufacturing overhead for an estimated allocation base of $88,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: $ 139,000 $ 84,000 Purchase of raw...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $130,200 of manufacturing overhead for an estimated allocation base of $93,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: $ 136,000 Purchase of raw materials Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $111.800 of manufacturing overhead for an estimated allocation base of $86,000 direct material dollars to be used in production. The company has provided the following data for the just completed year. $ 134,000 $ 82,000 Purchase of raw...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $128,800 of manufacturing overhead for an estimated allocation base of $92,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 133,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $111,800 of manufacturing overhead for an estimated allocation base of $86,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: $ 133,000 $ 82,000 Purchase of raw...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $127,400 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 139,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $118,300 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 135,000 Direct...