Question

Exercise 12-9 Allocating to smooth cost over varying levels of production LO 12-3 Production workers for Adams Manufacturing

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Month Allocated cost
January (15,000*12)/4,000 * 330 14,850
February (15,000*12)/4,000 * 550 24,750

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
Exercise 12-9 Allocating to smooth cost over varying levels of production LO 12-3 Production workers for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 4-8A Allocating to smooth cost over varying levels of production LO 4-3, 4-5 Production workers...

    Exercise 4-8A Allocating to smooth cost over varying levels of production LO 4-3, 4-5 Production workers for Vernon Manufacturing Company provided 450 hours of labor in January and 610 hours in February. Vernon expects to use 4,000 hours of labor during the year. The rental fee for the manufacturing facility is $14,000 per month. Required Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February?...

  • Production workers for Rooney Manufacturing Company provided 410 hours of labor in January and 680 hours...

    Production workers for Rooney Manufacturing Company provided 410 hours of labor in January and 680 hours in February. Rooney expects to use 4,000 hours of labor during the year. The rental fee for the manufacturing facility is $9,000 per month. Required Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February? (Do not round intermediate calculations.) 3:19 Allocated Cost Month January February

  • Production workers for Thornton Manufacturing Company provided 430 hours of labor in January and 660 hours...

    Production workers for Thornton Manufacturing Company provided 430 hours of labor in January and 660 hours in February. Thornton expects to use 4,000 hours of labor during the year. The rental fee for the manufacturing facility is $7,000 per month. Required Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February? (Do not round intermediate calculations.) points Month Allocated Cost (8 01:48:59 January February eBook...

  • Vernon Services Company has 51 employees, 25 of whom are assigned to Division A and 26...

    Vernon Services Company has 51 employees, 25 of whom are assigned to Division A and 26 to Division B. Vernon incurred $307,530 of fringe benefits cost during year 2. Required Determine the amount of the fringe benefits cost to be allocated to Division A and to Division B. Division Allocated Cost A B Production workers for Walton Manufacturing Company provided 330 hours of labor in January and 660 hours in February. Walton expects to use 4,000 hours of labor during...

  • xercise 4-11A (Algo) How the allocation of fixed cost attects a pricing decision LO 4-3 Adams...

    xercise 4-11A (Algo) How the allocation of fixed cost attects a pricing decision LO 4-3 Adams Manufacturing Co. expects to make 30,900 chairs during the year 1 accounting period. The company made 3.800 chairs in January. Materials and labor costs for January were $17,900 and $24,800, respectively. Adams produced 1,900 chairs in February Material and labor costs for February were $9,500 and $12,400, respectively. The company paid the $401.700 annual rental fee on its manufacturing facility on January 1, year...

  • newconnect.mheducation.com Chap 4A Seved Help Save & Exit Su Check my Production workers for Munoz Manufacturing...

    newconnect.mheducation.com Chap 4A Seved Help Save & Exit Su Check my Production workers for Munoz Manufacturing Company provided 4,800 hours of labor in January and 2,700 hours in February. The company, whose operation is labor intensive, expects to use 48,700 hours of labor during the year. Munoz paid a $107,140 annual premium on July 1 of the prior year for an insurance policy that covers the manufacturing facility for the following 12 months. Required Based on this information, how much...

  • Exercise 12-11 Allocating to solve a timing problem LO 12-3 Rundle Air is a large airline...

    Exercise 12-11 Allocating to solve a timing problem LO 12-3 Rundle Air is a large airline company that pays a customer relations representative $7,400 per month. The representative, who processed 1,110 customer complaints in January and 1,380 complaints in February, is expected to process 22,200 customer complaints during 2018. Required Determine the total cost of processing customer complaints in January and in February. Month Allocated Cost January February

  • Exercise 12-11 Allocating to solve a timing problem LO 12-3 Rooney Air is a large airline...

    Exercise 12-11 Allocating to solve a timing problem LO 12-3 Rooney Air is a large airline company that pays a customer relations representative $5,325 per month. The representative, who processed 1,180 customer complaints in January and 1,330 complaints in February, is expected to process 21,300 customer complaints during 2018 Required a. Determine the total cost of processing customer complaints in January and in February Month Allocated Cost January February

  • Exercise 12-11A (Algo) Allocating to solve a timing problem LO 12-3 Rooney Air is a large...

    Exercise 12-11A (Algo) Allocating to solve a timing problem LO 12-3 Rooney Air is a large airline company that pays a customer relations representative $13,825 per month. The representative, who processed 1,090 customer complaints in January and 1,370 complaints in February, is expected to process 23,700 customer complaints during the year Required a. Determine the total cost of processing customer complaints in January and in February Allocated Cost Month January February

  • Exercise 4-3A Allocating overhead cost to accomplish smoothing LO 4-2 Campbell Corporation expects to incur indirect...

    Exercise 4-3A Allocating overhead cost to accomplish smoothing LO 4-2 Campbell Corporation expects to incur indirect overhead costs of $145,200 per month and direct manufacturing costs of $22 per unit. The expected production activity for the first four months of 2017 is as follows: Estimated production in units January February March 4,400 7,600 4,800 April 7,400 Required a. Calculate a predetermined overhead rate based on the number of units of product expected to be made during the first four months...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT