Creative Web Design | ||||
Answer 1 | ||||
Allocation of Overhead | Car City | Jan's Flowers | Happy | Note |
Design Hours | 90.00 | 60.00 | 40.00 | A |
Rate per Design Hour | 22.00 | 22.00 | 22.00 | B |
Overhead allocated | 1,980.00 | 1,320.00 | 880.00 | C=A*B |
Answer 2 | ||||
Calculation of cost of Finished jobs | ||||
Car City | Jan's Flowers | Total | ||
Direct Labor cost | 2,430.00 | 1,200.00 | 3,630.00 | D |
Overhead allocated | 1,980.00 | 1,320.00 | 3,300.00 | See C |
Cost of Finished jobs | 4,410.00 | 2,520.00 | 6,930.00 | E=C+D |
Journal Entry | ||||
Account | Debit $ | Credit $ | ||
Completed Jobs | 6,930.00 | |||
Work In process | 6,930.00 | |||
Creative Web Design uses a job-order costing system to track the costs of its web design...
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Project Williams Chandler Nguyen Designer-hours 300 180 220 Direct materials $ 5,800 $ 2,800 $ 4,600 Direct labor $ 3,400 $ 2,000 $ 2,500 Actual overhead costs were $33,000...
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 330 210 250 $6,100 $3,100 $4,900 $3,700 $2,300 $2,800 Actual overhead costs were $36,000 for May. Overhead costs are applied...
Exercise # 5-10 Kareen CUT Asal as Sed Income Costs of subcontracted work. Din tal casts Shto overhead... Total cost to January 31. records of Eccles EXERCISE EXERCISE 5-10 Schedules of Cast of Goods Manufactured and Cost of Goods Statement (106) The following data from the just completed year are taken from the accounting reco Company Sales .. $643,000 90.000 132,000 100,000 43,000 210,000 220,000 Direct labour cost.... Raw material purchases Selling expenses... Administrative expenses.. Manufacturing overhead applied to work...
Che Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 320 200 240 $6,000 $ 3,000 $ 4,800 $ 3,600 $2,200 $ 2,700 Actual overhead costs were $35,000 for...
Applying Overhead in a Service Company: Journal Entries (L04, LOS, LOB] Vista Landscaping uses a job-order costing system to track the costs of its landscaping projects The company provides garden design and installation services for its clients. The table below provides data concerning the three landscaping projects that were in progress during April. There was no work in process at the beginning of April Project Harris Chan James Designer- hours 120 100 90 Actual overhead costs were $30,000 for April....
Management Accounting I'd be grateful if someone could show how to approach this management accounting problem. Thanks in advance. Local Landscaping uses a job-order costing system to track the costs of its landscaping projects. The company provides complete garden design and landscaping services. The following table provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials cost Direct labour cost. Williams 200 $4,800...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company's inventory balances were as follows: Raw materialsS Work in process 25,000 Finished goods38,100 ş 50,500 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company's predetermined overhead rate of $11.75 per direct labor-hour was based on a cost formula that estimated $470,000 of total manufacturing overhead for an estimated activity level of 40,000 direct labor-hours. The following...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow: Job Cost Sheet Job 105 Job 106 Job 107 November costs incurred: Direct materials $ 19,900 $ 12,700 $ 0...
The Polaris Company uses a job-order costing system. The following transactions occurred in October a. Raw materials purchased on account, $210,000. b. Raw materials used in production, $191,000 ($152,800 direct materials and $38,200 indirect materials). C. Accrued direct labor cost of $49,000 and indirect labor cost of $20,000 d. Depreciation recorded on factory equipment, $105,000 e. Other manufacturing overhead costs accrued during October. $130,000. f. The company applies manufacturing overhead cost to production using a predetermined rate of $7 per...
Pearson Architectural Design uses a job-order costing system and applies s o overhead to jobs on the basis of direct staff cost diferent from the names used in manufacturing companies. The following costs were recorded in January Cost of contacted work comparable mat De c osts comparable to director Stadio Overhead comparable to manufacturing overhead cost applied Cost of work completed compare to cost of goods manufactured) 50.000 There were no beginning inventories in January At the end of January,...