Question

(b) A company is evaluating a project for which the costs and expected cash flows are as follows: Year 0 Year 1 Year 2 Year 3
(b) PRA Ltd is evaluating between two mutually exclusive projects. The expected cash flows for the projects are as follows: P
0 0
Add a comment Improve this question Transcribed image text
Answer #1

DISCOUNTED PAYBACK PERIOD PAYBACK PERIOD Discounting Factor @ 10% CUMULATIVE CASH FLOWS CUMULATIVE CASH FLOWS 2 YEAR 30 CASH

Ε 4 A B C D DISCOUNTED PAYBACK PAYBACK PERIOD PERIOD Discounting CUMULATIVE CUMULATIVE YEAR CASH FLOWS Factor @ 10% PRESENT V

DISCOUNTING FACTOR = 8%

N DISCOUNTED PAYBACK PERIOD PAYBACK PERIOD 2 YEAR Discounting Factor @ 8% CUMULATIVE CASH FLOWS CUMULATIVE CASH FLOWS 4 1 CAS

N YEAR K DISCOUNTED PAYBACK PAYBACK PERIOD PERIOD Discounting CUMULATIV CASH FLOWS Factor @8% PRESENT VALUE CUMULATIVE CASH F

B)

A 2 PROJECT A 3 YEAR Discounting Factor @ 10% O Nm CASH FLOWS -2000000 900000 1135000 | 2000000 =1/(1.1)^A5 =1/(1.1) A6 =1/(1

A 2 PROJECT A 3 YEAR CASH FLOWS Discounting Factor @ 10% PRESENT VALUE 0 -20,00,000.00 1.00 -20,00,000.00 1 9,00,000.00 0.91

CALCULATION OF PBP FOR PROJECT A & B

C 1 PROJECT A CALCULATION OF PBP Discounting Factor @ 10% CUMULATIVE CASH FLOWS 2 YEAR 30 4 1 5 2 CASH FLOWS -2000000 900000

B 1 PROJECT A CALCULATION OF PBP 2 YEAR CUMULATIVE CASH FLOWS Discounting Factor @ 10% PRESENT VALUE CASH FLOWS 0 -20,00,000.

PROJECT B CALCULATION OF PBP YEAR Discounting Factor @ 10% CUMULATIVE CASH FLOWS CASH FLOWS -2000000 1400000 1135000 1000000

G H PROJECT B CALCULATION OF PBP YEAR 0 CUMULATIVE CASH FLOWS Discounting Factor @ 10% PRESENT VALUE CASH FLOWS -20,00,000.00

PROJECT B SHOULD BE CHOSEN AS PAYBACK PERIOD IS LESS THAN THAT OF PROJECT A.

Add a comment
Know the answer?
Add Answer to:
(b) A company is evaluating a project for which the costs and expected cash flows are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year...

    (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...

  • (b) A company is evaluating between two mutually exclusive projects. The required initial investments and the...

    (b) A company is evaluating between two mutually exclusive projects. The required initial investments and the expected net cash flows from the projects are as follows: Project 1 Project 2 0 -$4,000,000 - $4,000,000 1 $1,900,000 $1,100,000 2 $2,255,000 $1,900,000 3 $2,000,000 $2,000,000 The company accepts any project for which the payback period is within 3 years, Which of these projects should be chosen using the payback period as the capital budgeting measure? (3 marks) An Australian multinational company is...

  • you are considering a project with an initial cash outlay of $74,000 and expected cash flows...

    you are considering a project with an initial cash outlay of $74,000 and expected cash flows of $23,680 at the end of each year for six years. the discount rate for the project is 9.7 percent. a. what are the project's payback discounted payback periods? - if the discount rate for this project is 9.7 percent, the discounted payback period of the project is how many years? b. what is the projects NPV? c. what is the project's PI? d....

  • software company is evaluating the following projects with estimated cash flow (in $): Year (t) Project...

    software company is evaluating the following projects with estimated cash flow (in $): Year (t) Project A Project B Project C 0 -100,000 -100,000 -120,000 1 30,000 30,000 40,000 2 40,000 30,000 40,000 3 40,000 30,000 40,000 4 40,000 30,000 40,000 5 100,000 130,000 120,000 Calculate the net profit, payback period, return on investment (ROI), and net present value (NPV) of all projects. Discount rate= 3.00% a) Show your calculated discount rate and fill in the table. Project A Project...

  • This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows...

    This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...

  • Your firm is considering two projects with the following cash flows: Cash flows from project B...

    Your firm is considering two projects with the following cash flows: Cash flows from project B (£000) (500) 200 250 170 25 30 Year Cash flows from project A (£000) 0(500) 167 180 160 100 100 4 1. Calculate the ARR and payback rule 2. If the appropriate discount rate is 12%, rank the two projects 3. Which project is preferred if you rank by IRR? 4. Calculate the discount rate (r) for which the NPVs of both projects are...

  • You are evaluating a project that will cost $493,000, but is expected to produce cash flows...

    You are evaluating a project that will cost $493,000, but is expected to produce cash flows of $128,000 per year for 10 years, with the first cash flow in one year. Your cost of capital is 11.3% and your companys preferred payback period is three years or less. a. What is the payback period of this​ project? b. Should you take the project if you want to increase the value of the​ company? If you want to increase the value...

  • The cash flows associated with three independent projects (in millions) are as follows Net Cash Flows Proiect Alpha Project Beta Proiect Gamma Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 $1,500,000...

    The cash flows associated with three independent projects (in millions) are as follows Net Cash Flows Proiect Alpha Project Beta Proiect Gamma Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 $1,500,000 $300,000 S500,000 S500,000 $400,000 $300,000 $400,000 $100,000 S200,000 $200,000 $100,000 S200,000 $7,500,000 $2,000,000 S3,000,000 S2,000,000 S1,500,000 $5,500,000 a) Calculate the payback period of each investment b) Which investments does the company accept if the cut-off payback period is three years? What if the cut-off is...

  • You are evaluating a project that will cost $504,000, but is expected to produce cash flows...

    You are evaluating a project that will cost $504,000, but is expected to produce cash flows of $123,000 per year for 10 years, with the first cash flow in one year. Your cost of capital is 10.9% and your company's preferred payback period is three years or less. a. What is the payback period of this project? b. Should you take the project if you want to increase the value of the company? a. What is the payback period of...

  • (b) Suppose a Spanish investor is considering the following investments: Investment A: This is the ordinary...

    (b) Suppose a Spanish investor is considering the following investments: Investment A: This is the ordinary share of a matured company. The market price for this security is €40 per share. The company is expected to pay €4 dividend per share one year from now and its expected growth rate for foreseeable future is 4%. Investment B: This is the ordinary share of a fast-growing company. The market price for this security is €40 per share. The company expects to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT