Ravelo Corporation has provided the following data from its activity-based costing system:
Activity Cost Pools |
Estimated Overhead Cost |
Expected Activity | |||
Assembly | $ | 506,520 | 48,000 | machine-hours | |
Processing orders | $ | 58,263 | 1,500 | orders | |
Inspection | $ | 81,589 | 1,510 | inspection-hours | |
Data concerning the company's product L19B appear below:
Annual unit production and sales | 510 | |||
Annual machine-hours | 1,070 | |||
Annual number of orders | 150 | |||
Annual inspection hours | 100 | |||
Direct materials cost | $ | 45.74 | per unit | |
Direct labor cost | $ | 18.45 | per unit | |
According to the activity-based costing system, the unit product cost of product L19B is closest to
Answer--------Unit product cost = $108.35
Working
Product L19B | |
Direct material | $ 45.74 |
Direct labor | $ 18.45 |
Overheads | $ 44.16 |
Total Cost | $ 108.35 |
.
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Assembly | Number of machine hour | $ 506,520 | 48000 | $ 10.55 | Per machine hour |
Processing orders | Number of Order | $ 58,263 | 1500 | $ 38.84 | Per Order |
Insection | Number of Inspection | $ 81,589 | 1510 | $ 54.03 | Per Inspection |
.
Cost assigned to Product L19B | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Assembly | $ 10.55 | 1,070.00 | $ 11,291 |
Processing orders | $ 38.84 | 150.00 | $ 5,826 |
Insection | $ 54.03 | 100.00 | $ 5,403 |
Total Overheads assigned | $ 22,521 | ||
Production | 510.00 | ||
Overhead cost per unit | $ 44.16 |
Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Estimated...
Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Assembly Processing orders Inspection Estimated Overhead Cost Expected Activity $503, 520 46,500 machine-hours $ 56,763 1,350 orders $ 80,089 1,360 inspection-hours Data concerning the company's product L19B appear below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 480 1,040 120 70 $42.74 per unit $15.45 per unit According to the activity-based costing system,...
Ravelo Corporation has provided the following data from its activity based costing system: Activity Cost Pools Assembly Processing orders Inspection Estimated Overhead Cost Expected Activity $510,520 50,000 machine-hours $ 60,263 1,700 orders $ 83,589 1,710 inspection-hours Data concerning the company's product L19B appear below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 550 1,110 190 140 $ 49.74 per unit $ 22.45 per unit According to the activity...
Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Assembly Processing orders Inspection Estimated Overhead Cost Expected Activity $502,520 46,000 machine-hours $ 56,263 1,300 orders $ 79,589 1,310 inspection-hours Data concerning the company's product L19B appear below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 470 1,030 110 60 $ 41.74 per unit $14.45 per unit According to the activity-based costing system,...
Ravelo Corporation has provided the following data from its activity-based costing system: Ravelo Corporation has provided the following data from its activity-based costing system: Estimated Overhead Activity Cost Pools Cost Expected Activity Assembly $510,520 50,000 machine-hours Processing orders $ 60,263 1,700 orders Inspection $ 83,589 1,710 inspection-hours Data concerning the company's product L19B appear below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 550 1,110 190 140 $...
Ravelo Corporation has provided the following data from its activity-based costing system: 8 01:55:06 Activity Cost Pools Assembly Processing orders Inspection Estimated Overhead Cost Expected Activity $502,520 46,000 machine-hours $ 56,263 1,300 orders $ 79,589 1,310 inspection-hours Data concerning the company's product L19B appear below: 470 1,030 110 Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 60 $41.74 per unit $14.45 per unit According to the activity-based costing...
Hello all, could someone please help me answer this question. Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Assembly Processing orders Inspection Estimated Overhead Cost Expected Activity $516,520 53,000 machine-hours $ 63,263 2,000 orders $ 86,589 2,010 inspection-hours Data concerning the company's product L19B appear below: 610 1,170 250 Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 200 $ 55.74 per...
6. Sarah Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Assembly .................. $387,000 25,000 machine-hours Processing orders ........ $68,510 1,700 orders Inspection $129,117 1,930 inspection-hours The company makes 240 units of product T91H a year, requiring a total of 550 machine-hours, 90 orders, and 40 inspection-hours per year. The product's direct materials cost is $16.98 per unit and its direct labor cost is $12.09 per unit. According to the activity-based...
Paparo Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Assembly Processing orders Inspection $ $ $ Total cost Total Activity 965,700 58,000 machine-hours 76,100 2,000 orders 105,156 1,380 inspection-hours Data concerning the company's product Q79Y appear below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 800 1,080 90 30 $53.00 per unit $41.21 per unit According to the activity-based costing system, the...
Paparo Corporation has provided the following data from its activity-based costing system: 4 Activity Cost Pool Assembly Processing orders Inspection Total Cost Total Activity $ 872,100 51,000 machine-hours $ 77,000 2,000 orders $ 113,337 1,470 inspection-hours Data concerning the company's product Q79Y ar below: Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 700 1,170 135 40 $ 46.00 per unit $41.39 per unit According to the activity-based costing...
Paparo Corporation has provided the following data from its activity-based costing system: Activity Total Cost Pool Cost Total Activity Assembly $ 891,800 52,000 machine-hours Processing orders $ 80,955 2,100 orders Inspection $ 114,256 1,480 inspection-hours Data concerning the company's product Q79Y appear below: 750 1,180 140 Annual unit production and sales Annual machine-hours Annual number of orders Annual inspection hours Direct materials cost Direct labor cost 45 $47.00 per unit $41.41 per unit According to the activity-based costing system, the...