Question

The table below presents the stream of costs and benefits for a resource development project. Use the table below to answer the following questions Year Benefits Costs 0 0 60 2 30 60 100 What is the net present value of the benefits at an interest rate of 5%? a. 118.75 b. 123.8:1 c. 119.217 d. 123.5 e. none of the above What is the net present value of the costs at an interest rate of 5%? a. 120 b. 119.0!5 C. 114.29 d. 117.14 e. none of the above Would you start the project or cancel the project at an interest rate of 5% (assuming you are rational and there are no other costs)? a. yes start the project b. no will not start the project c. cannot determine with the information provided Would you start the project or cancel the project at an interest rate of 10% (assuming you are rational and there are no other costs)? a. yes start the project b. no will not start the project c. cannot determine with the information provided

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

C

Working note:

NPV of benefits = 30/1.05 + 100/1.05^2 = $119.27

2.

D

Working note:

NPV of costs = 60 + 60/1.05 = $117.14

3.

A

I will start the project as NPV of benefits is greater than than the NPV of costs.

4.

B

Working note:

If R = 10%

Then,

NPV of the porject = 30/1.1 + 100/1.1^2 - (60+60/1.1) = - $4.62

I will not start the project as NPV of the project is negative.

Add a comment
Know the answer?
Add Answer to:
The table below presents the stream of costs and benefits for a resource development project. Use...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Look at the table below with benefits and costs of a proposed project over 3 years....

    Look at the table below with benefits and costs of a proposed project over 3 years. What’s the net present value of the project assuming a 5% discount rate? Look at the table below with benefits and costs of a proposed project over 3 years. Year Benefits Costs / 1 2 125 150 250 75 25 3 / 100 / What's the net present value of the project assuming a 5% discount rate? Select one: O a. -$10.6 O b....

  • 2. The government is contemplating project A that yields the following stream of benefits and costs....

    2. The government is contemplating project A that yields the following stream of benefits and costs. Project A Year 2 S10,0000 0 Benefits0 $2,000 $4,000 $6,000 (a) Find the net present value and the benefit cost ratio for this project, assuming a discount rate of 5%. (b) Re-calculate the net present value assuming a discount rate of (i) 3%, (ii) 8 % and (iii) 10%. Use a graph to illustrate how the net present value of the project is affected...

  • 3. Suppose a project under consideration has the following stream of benefits and costs. Year O...

    3. Suppose a project under consideration has the following stream of benefits and costs. Year O Costs $10,000 Benefits 4 S5,000 $2,000S4,000 S6,000 $8,000 S10,000 $2,000 (a) Find the net present value of the project assuming a discount rate of 5%. Is the project worthwhile? (b) Suppose you have discovered that the benefits of the project have been overestimated and a more accurate assessment suggests that the benefit in each year is half of the original estimate. Assuming a discount...

  • The table below lists the costs and benefits of five mutually exclusive projects. Project Costs Benefits...

    The table below lists the costs and benefits of five mutually exclusive projects. Project Costs Benefits A 9 12 B 6 5 C 3 4 D 9 11 E 4 6 (6 marks) Calculate the benefit-cost ratio (BCR) of each project: Project BCR A B C D E (6 marks) Use incremental benefit-cost analysis to determine the preferred project. Show your work. The preferred project is Project ___________

  • 7. Consider a highway project with the following costs and benefits. This representation of costs and...

    7. Consider a highway project with the following costs and benefits. This representation of costs and benefits assumes the costs occur immediately and the benefits occur at the end of year 1, end of year 2 and the end of year 3. Year 0 Costs $470,000 Benedi 0 $275.00 $295.005$315.000 $275,000$295,000 S315,000 (a) Calculate the net present value of the project. Assume a discount rate of 4%. Now suppose all the benefits occur at the start of each period. What...

  • A project costs 10 this year, has a benefit of 5 this year, and has a...

    A project costs 10 this year, has a benefit of 5 this year, and has a benefit of 6 next year. (a) Assuming that the interest rate is r= 1, what is the present value (sum of the dis- counted benefits minus costs) of the project? (b) For what value of interest rate r, the present value of the project will be exactly equal to zero?

  • A project costs 10 this year, has a benefit of 5 this year, and has a...

    A project costs 10 this year, has a benefit of 5 this year, and has a benefit of 6 next year. (a) Assuming that the interest rate is r= 1, what is the present value (sum of the dis-counted benefits minus costs) of the project? (b) For what value of interest rater, the present value of the project will be exactly equal to zero?

  • 1.2. Assume you need to evaluate an ecotouristic project. Each year the project requires maintenance costs...

    1.2. Assume you need to evaluate an ecotouristic project. Each year the project requires maintenance costs equal to $200 and you have benefits (income) of $500. Except for the first year when you invest $1,000 and you have zero income. The market interest rate is 5% What is the Net Present Value of this project? YEAR 1 INTEREST RATE 5% COSTS BENEFITS 1000 10 200 500 200 500 500 200 500 200 Assume you have certified coffee plantation project. Each...

  • 4. The government is contemplating a project that protects a wilderness area. The project's initial costs...

    4. The government is contemplating a project that protects a wilderness area. The project's initial costs incurred at time t-0 equal S375,000. Starting in year 1, the project is expected to produce annual net benefits of S100,000 into perpetuity (a) Calculate the net present value assuming a discount rate of 8%. Do you recommend going forward with this project? (b)There is some uncertainty about the estimates of initial costs and annual net benefits Research suggests that there is a 75%...

  • Problem 2: Cost-benefit Analysis. A project costs 10 this ycar, has a benefit of 5 this...

    Problem 2: Cost-benefit Analysis. A project costs 10 this ycar, has a benefit of 5 this ycar, and has a bencfit of 6 next ycar. (a) Assuming that the interest rate is r , what is the present value (sum of the dis- counted benefits minus costs) of the project? (b) For what value of interest rate r, the present value of the project will be exactly equal to zero?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT