7. Consider a highway project with the following costs and benefits. This representation of costs and benefits assumes the costs occur immediately and the benefits occur at the end of year 1, end of year 2 and the end of year 3. Year 0 Costs $470,000 Benedi 0 $275.00 $295.005$315.000 $275,000$295,000 S315,000 (a) Calculate the net present value of the project. Assume a discount rate of 4%. Now suppose all the benefits occur at the start of each period. What happens to your net present value calculation? (b)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Net present value of the project = P0 + P1(1 + r)^-1 + P2(1 + r)^-2 + P3(1 + r)^-3

= -470,000 + 275,000(1 + 4%)^-1 + 295,000(1 + 4%)^-2 + 315,000(1 + 4%)^-3

= $347,201

b) When all benefits occur in the beginning of each period we have

Net present value of the project = P0 + P1 + P2(1 + r)^-1 + P3(1 + r)^-2

= -470,000 + 275,000 + 295,000(1 + 4%)^-1 + 315,000(1 + 4%)^-2

= $379,889

Net present value rises when benefits are received in the beginning of the year.

Add a comment
Know the answer?
Add Answer to:
7. Consider a highway project with the following costs and benefits. This representation of costs and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. The government is contemplating project A that yields the following stream of benefits and costs....

    2. The government is contemplating project A that yields the following stream of benefits and costs. Project A Year 2 S10,0000 0 Benefits0 $2,000 $4,000 $6,000 (a) Find the net present value and the benefit cost ratio for this project, assuming a discount rate of 5%. (b) Re-calculate the net present value assuming a discount rate of (i) 3%, (ii) 8 % and (iii) 10%. Use a graph to illustrate how the net present value of the project is affected...

  • The table below presents the stream of costs and benefits for a resource development project. Use...

    The table below presents the stream of costs and benefits for a resource development project. Use the table below to answer the following questions Year Benefits Costs 0 0 60 2 30 60 100 What is the net present value of the benefits at an interest rate of 5%? a. 118.75 b. 123.8:1 c. 119.217 d. 123.5 e. none of the above What is the net present value of the costs at an interest rate of 5%? a. 120 b....

  • Look at the table below with benefits and costs of a proposed project over 3 years....

    Look at the table below with benefits and costs of a proposed project over 3 years. What’s the net present value of the project assuming a 5% discount rate? Look at the table below with benefits and costs of a proposed project over 3 years. Year Benefits Costs / 1 2 125 150 250 75 25 3 / 100 / What's the net present value of the project assuming a 5% discount rate? Select one: O a. -$10.6 O b....

  • A project where the projected costs and benefits are spread over five years with the following...

    A project where the projected costs and benefits are spread over five years with the following data: • Estimated costs are $100,000 in Year 1 and $25,000 each for years 2, 3, 4, and 5. • Estimated benefits are $0 in Year 1 and $80,000 each for years 2, 3, 4, and 5. • Use a discount rate of 8% 1.Calculate the following: a. Calculate cash flow b. Show the discount factor c. Show discounted costs and discounted benefits d....

  • 3. Suppose a project under consideration has the following stream of benefits and costs. Year O...

    3. Suppose a project under consideration has the following stream of benefits and costs. Year O Costs $10,000 Benefits 4 S5,000 $2,000S4,000 S6,000 $8,000 S10,000 $2,000 (a) Find the net present value of the project assuming a discount rate of 5%. Is the project worthwhile? (b) Suppose you have discovered that the benefits of the project have been overestimated and a more accurate assessment suggests that the benefit in each year is half of the original estimate. Assuming a discount...

  • Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Cos...

    Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Costs Treatment Yr 1 Yr2 Yr3 A 100 700 400 B 400 300 200 Benefits Treatment Yr 1 Yr2 Yr3 A 300 400 900 B 500 600 100 A.        Assuming a discount rate of 5% and no discounting applied in Yr 1, calculate the present value of net benefits for each treatment. Ans. B.        If the treatments are stopped after Yr 2, which...

  • 6. The government is considering an early education project for children currently aged three. The project...

    6. The government is considering an early education project for children currently aged three. The project involves annual costs of S2500 for 5 years (starting t-1). Annual net benefits of S3000 start in year 15 (once the children reach the age of 22) and last for 20 years. Assume all benefits and costs are incurred at the end of the year. ustrate the timing of benefits and costs using a timeline. (b) (c) There is some uncertainty about the choice...

  • Using information about the estimated costs, estimated benefits and a discount rate of 9% for Project...

    Using information about the estimated costs, estimated benefits and a discount rate of 9% for Project XYZ, calculate the discount factor for each year, the discounted costs, the discounted benefits, the return-on-investment (ROI) and the net-present value (NPV). In which year does the payback occurs? Total | O 175,000 ? ? Estimated Costs Discount Factor Discounted Costs | 22.500,7 22,500 ? ? Year 2 | 22,500 ? ? 3 | 22,500 ? ? 4 22,500 ? ? | 5 |...

  • 4. The government is contemplating a project that protects a wilderness area. The project's initial costs...

    4. The government is contemplating a project that protects a wilderness area. The project's initial costs incurred at time t-0 equal S375,000. Starting in year 1, the project is expected to produce annual net benefits of S100,000 into perpetuity (a) Calculate the net present value assuming a discount rate of 8%. Do you recommend going forward with this project? (b)There is some uncertainty about the estimates of initial costs and annual net benefits Research suggests that there is a 75%...

  • Question Two Using information about the estimated costs, estimated benefits and a discount rate of 9%...

    Question Two Using information about the estimated costs, estimated benefits and a discount rate of 9% for Project XYZ, calculate the discount factor for each year, the discounted costs, the discounted benefits, the return-on-investment (ROI) and the net-present value (NPV). In which year does the payback occurs? Total Year 0 1 2 3 4 5 175,000|22,500|22,500122,500122,500 22,500 Estimated Costs Discount Factor Discounted Costs 080,000|80,00080,000|80,000 80,000 Estimated Benefits Discount Factor Discounted Benefits Discounted Benefits - Costs D Cumulative Benefits-Costs 21 21...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT