Question

Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Cos...

Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars

Costs

Treatment

Yr 1

Yr2

Yr3

A

100

700

400

B

400

300

200

Benefits

Treatment

Yr 1

Yr2

Yr3

A

300

400

900

B

500

600

100

A.        Assuming a discount rate of 5% and no discounting applied in Yr 1, calculate the present value of net benefits for each treatment.

Ans.

B.        If the treatments are stopped after Yr 2, which treatment do you prefer?  Why?

C.        Assume a really large discount rate-- 100%.  Calculate the present value of net benefits (use all three years and don't discount for the first year)

D.        How does the higher discount rate affect the net present value?  Does it affect which treatment you prefer?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Bock1 Micrasaft Excel Hcme Insert Page Laynin Famulas Data Revew Viw Devploper E AitoSum Ci Caibri A A Wrap Text Normal 1 Gen

Part A of the above question has been on the calculation A of the excel. Given that discount rate of 5% and no discounting done on the first year, net present value of benefits can be done as as seen the image above.

Net present values of benefits and cost of both treatment has been done separately. To find net present benefit of treatment A and B, i have used the NPV function of the excel. Keep in mind that we are not discounting year 1 of benefits and cost. So what we are doing is discounting benefits and cost to year 1. i.e discounting year 2 and 3 rates to year 1.

Net present value of treatment A (NPV A) = J5+NPV(C13,K5:L5)

= 1497.28

Net present value of treatment B (NPV B) = J6+NPV(C13,K6:L6)

= 1162.13

In the above calculation keep in mind that we need to sum present values of benefits of year 2 and 3 with benefits of year 1 to find correct answer. I have done the same in the above equations. As we can see from the calcualtions, NPV of A is greater than NPV of B. We need to choose treatment with highest NPV. Therefore treatment offer better value.

For deeper understanding, I have found NPV values of cost too.

NPV cost treatment A = D5+NPV(C13,E5:F5)

= 1129.48

NPV cost treatment B = D6+NPV(C13,E6:F6)

= 867.12

While doing NPV cost of treatments keep in mind the concepts of discounting year 2 and 3 rates to year 1, as discussed in NPV calculation of benefits. As you can see NPV of cost of A is greater than B. Does it mean treatment B is better? To find that out, subtract cost from benefits of each treatment, as shown in the imgae

Net benefits treatment A = NPV of benefit - NPV of cost

= C14-C18

= 1497.28 - 1129.48

= 367.80

Net benefits of treatment B = NPV of benefits - NPV of cost

= C15-C19

= 1162.13 - 867.12

= 295.01

Therefore treatment A offer better value for money than B.

Part B

Bock1 Micrasaft Fxcel Ное Insert Page Laynin Famulas Data Revew Viw Devploper E AitoSum Caibri A A Wrap Text Normal 1 General

Calculations regarding part B of the question is done on Calculation B on the image.

The question says, treatments are stopped after year 2, which means we have consider cost and benefits till year 2 only. We can avoid year 3 for this part of the question. i.e we need to discount only year 2 cost and benefits to year 1. For this i have calculated NPV of both cost and benefits of treatment A and B. Using same discount rate 5%.

NPV of benefits treatment A = J5+NPV(C13:K5)

= 680.95

NPV benefits treatment B = J6+NPV(C13+K6)

= 1071.43

NPV cost of treatment A = D5+NPV(C13,E5)

= 766.67

NPV cost of treatment B = D6+NPV(C13,E6)

= 685.71

One this is done subtract cost from benefit to reach a final decision.

Benefit - cost treatment A = NPV benefit - NPV cost

= 680.95 - 766.67

= -85.71

Benefit - cost treatment B = NPV benefit - NPV cost

= 1071.43 - 685.71

= 385.71

Treatment A give negative benefits (cost is more than benefits) Treatment B gives positive return of 385.71, so we choose Treatment B. (benefit is more than the cost incurred).

Part C.

Bock1 Micrasaft Fxcel Ное Insert Page Laynin Famulas Data Revew Viw Devploper E AitoSum Caibri A A Wrap Text Normal 1 General

Solution to part c of the problem has been shown in calculation c in the above image.

The question says we now use discount rate of 100%. Keep in mind the concepts i said in part A of the question, find Net present value of benefit can be done as

NPV benefit Treatment A = J5+NPV(C33,K5:L5)

= 725

NPV benefit treatment B = J6+NPV(C33,K6:L6)

= 825

Part D

There exist inverse relation between NPV and discount rate. Higher the discount rate lower will be the NPV and vise versa.

Higher the discount rate, lower is amount i have to invest today to get same amount that i could get by investing more at lower interest rate.

Higher discount rate have impact on our decision making on the treatment we prefer. At 100% discount rate

NPV of benefit of treatment A = 725

NPV of benefit of treatment B = 825

Now look at benefit of treatment A and B at 5% discount rate

NPV benefit treatment A = 1497.28

NPV benefit treatment B = 1162.13

As we can see at higher discount rate treatment B offers better value for money than A. When discounting rate fall, present value of future benefits will go up (time value of money comes down).

Add a comment
Know the answer?
Add Answer to:
Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Cos...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 7. Consider a highway project with the following costs and benefits. This representation of costs and...

    7. Consider a highway project with the following costs and benefits. This representation of costs and benefits assumes the costs occur immediately and the benefits occur at the end of year 1, end of year 2 and the end of year 3. Year 0 Costs $470,000 Benedi 0 $275.00 $295.005$315.000 $275,000$295,000 S315,000 (a) Calculate the net present value of the project. Assume a discount rate of 4%. Now suppose all the benefits occur at the start of each period. What...

  • 13. The benefits and costs in millions of dollars of two restoration projects are as follows:...

    13. The benefits and costs in millions of dollars of two restoration projects are as follows: Benefits Year 0 50 30 100 Year 1 50 30 50 Year 2 50 30 Costs Benefits Year 3 50 30 125 15 25 Costs 50 40 15 a. Using a discount rate of 5% compute the net present value of each of the two alternatives. Explain your results.

  • Assuming 10% as the annual rate of discount or interest, calculate the net present value for...

    Assuming 10% as the annual rate of discount or interest, calculate the net present value for the following project: Initial investment (an outflow) $ 40000 Revenue yr 1: $ 80000                                   Costs yr 1: $ 60000 Revenue yr 2: $100000                                   Costs yr2: $60000 Revenue yr 3: $120000                                   Costs yr 3: $ 70000

  • You have the following table of costs and benefits for alternative treatments Treatment # Cost Effectiveness...

    You have the following table of costs and benefits for alternative treatments Treatment # Cost Effectiveness (life years gained) 1 100000 5 2 200000 3 3 400000 10 4 500000 20 A.        Which treatment(s) if any, is strongly dominated? B.        Which treatment(s) if any is weakly dominated? C.        Calculate incremental cost effectiveness ratios. D.        Assuming that a life year is considered to be worth up to 100000, which interventions would you choose, in the absence of budgetary constraints? E.         How might budgetary constraints affect your...

  • Consider two treatments for lung cancer: (1) radiation and chemotherapy and (2) immunotherapy. Treatment 1 costs...

    Consider two treatments for lung cancer: (1) radiation and chemotherapy and (2) immunotherapy. Treatment 1 costs $30,000. Treatment 2 costs $75,000. With treatment 1, there is a 75% chance the patient will be alive in year 1 and a 50% chance in year 2, but the patient will die in year 3. The quality of life is poor with treatment 1, 50% of full health in both years. With treatment 2, there is 50% chance of being alive in year...

  • 2. The government is contemplating project A that yields the following stream of benefits and costs....

    2. The government is contemplating project A that yields the following stream of benefits and costs. Project A Year 2 S10,0000 0 Benefits0 $2,000 $4,000 $6,000 (a) Find the net present value and the benefit cost ratio for this project, assuming a discount rate of 5%. (b) Re-calculate the net present value assuming a discount rate of (i) 3%, (ii) 8 % and (iii) 10%. Use a graph to illustrate how the net present value of the project is affected...

  • Question Two Using information about the estimated costs, estimated benefits and a discount rate of 9%...

    Question Two Using information about the estimated costs, estimated benefits and a discount rate of 9% for Project XYZ, calculate the discount factor for each year, the discounted costs, the discounted benefits, the return-on-investment (ROI) and the net-present value (NPV). In which year does the payback occurs? Total Year 0 1 2 3 4 5 175,000|22,500|22,500122,500122,500 22,500 Estimated Costs Discount Factor Discounted Costs 080,000|80,00080,000|80,000 80,000 Estimated Benefits Discount Factor Discounted Benefits Discounted Benefits - Costs D Cumulative Benefits-Costs 21 21...

  • Look at the table below with benefits and costs of a proposed project over 3 years....

    Look at the table below with benefits and costs of a proposed project over 3 years. What’s the net present value of the project assuming a 5% discount rate? Look at the table below with benefits and costs of a proposed project over 3 years. Year Benefits Costs / 1 2 125 150 250 75 25 3 / 100 / What's the net present value of the project assuming a 5% discount rate? Select one: O a. -$10.6 O b....

  • A project where the projected costs and benefits are spread over five years with the following...

    A project where the projected costs and benefits are spread over five years with the following data: • Estimated costs are $100,000 in Year 1 and $25,000 each for years 2, 3, 4, and 5. • Estimated benefits are $0 in Year 1 and $80,000 each for years 2, 3, 4, and 5. • Use a discount rate of 8% 1.Calculate the following: a. Calculate cash flow b. Show the discount factor c. Show discounted costs and discounted benefits d....

  • The following information has been gathered on the costs and effectiveness of the two treatments, A and B. In this pro...

    The following information has been gathered on the costs and effectiveness of the two treatments, A and B. In this problem, costs and consequences are not discounted. Treatment A Treatment B Mortality rate 2% 5% Life expectancy for survivors 30 years 20 years Initial treatment cost $20,000 $10,000 Follow up costs, year 1 $5,000 $1,000 Annual follow up costs, all subsequent years $1,000 $500 Calculate the incremental cost and incremental benefit of the treatment alternatives. DC = DE = What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT