Question

13. The benefits and costs in millions of dollars of two restoration projects are as follows: Benefits Year 0 50 30 100 Year

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per the information given

Year

Year 0

Year 1

Year 2

Year 3

A

Benefits

50

50

50

50

Costs

30

30

30

30

Net Cash Flow of A

20

20

20

20

B

Benefits

100

50

25

25

Costs

50

40

15

15

Net Cash Flow of B

50

10

10

10

Net Cash Flow = Annual Benefits – Annual Costs

a. Calculating the Net Present Value of two alternatives at interest rate of 5%.

NPV of A

NPV = 20 + 20 (P/A, 5%, 3)

NPV = 20 + 20 (2.72325) = 76.45

NPV of B

NPV = 50 + 10 (P/A, 5%, 3)

NPV = 50 + 10 (2.72325) = 77.23

On the basis of the above calculation, we can say that the alternative B is more profitable than the alternative B. The alternative B has more NPV than the alternative A.

Note - all the costs and benefits are in million of dollars

Add a comment
Know the answer?
Add Answer to:
13. The benefits and costs in millions of dollars of two restoration projects are as follows:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Cos...

    Consider the following costs and benefits associated with two treatments, A and B. Costs and benefits are in dollars Costs Treatment Yr 1 Yr2 Yr3 A 100 700 400 B 400 300 200 Benefits Treatment Yr 1 Yr2 Yr3 A 300 400 900 B 500 600 100 A.        Assuming a discount rate of 5% and no discounting applied in Yr 1, calculate the present value of net benefits for each treatment. Ans. B.        If the treatments are stopped after Yr 2, which...

  • You are analyzing two mutually exclusive projects with the cash flows shown below. The cash flows...

    You are analyzing two mutually exclusive projects with the cash flows shown below. The cash flows are in millions. Both projects are equally risky. Your costs of capital are 12%. Year Project 1 Project 2 0 -$140 -$90 1 $50 $40 2 $45 $35 3 $40 $30 4 $35 $25 5 $30 $20 6 $25 $15 7 $20 $10 8 $15 $5 9 $10 $0 10 $5 -$5 Compute the NPVs of the two projects. b. Compute the IRRs of...

  • Look at the table below with benefits and costs of a proposed project over 3 years....

    Look at the table below with benefits and costs of a proposed project over 3 years. What’s the net present value of the project assuming a 5% discount rate? Look at the table below with benefits and costs of a proposed project over 3 years. Year Benefits Costs / 1 2 125 150 250 75 25 3 / 100 / What's the net present value of the project assuming a 5% discount rate? Select one: O a. -$10.6 O b....

  • 11. The public sector is thinking about undertaking one of this two projects, X or Y:...

    11. The public sector is thinking about undertaking one of this two projects, X or Y: X Y Units: thousand of dollars Benefits Cost Benefit Cost Year 0 100 1000 Year 1 500 Year 2 500 5000 Calculate the Net Present Value, the Internal Rate of Return and the Benefit/Cost ratio for the two projects using the Social Discount Rate suggested for the federal government for Canada. Which project should the public sector choose according to each of the three...

  • Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

    Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.1 0.1 The net present value (NPV) of project A is closest to: A. 28.5 B. 56.9 C. 25 D. 22.8

  • 13. NDR is a company that is deciding between three projects, High, Medium, and Low. The...

    13. NDR is a company that is deciding between three projects, High, Medium, and Low. The projects have internal rate of returns (IRR) and cash flows as listed in the table below. Year 3 2 1 Project IRR 12.1% $100 -45 -35-45 A 35 -15 9.0% -$ 50 35 В -9 18 18 7.8% -$25 C Unfortunately, NDR doesn't know what discount rate to use to value the projects in order to calculate the net present values. In which project(s)...

  • An internet company projects the following cash flows shown in the table below (in milions). Usin...

    include cash flow diagram An internet company projects the following cash flows shown in the table below (in milions). Using a Net Present Worth Balancing Equation and a manual iteration process compute the Rate of Return. Cash Flow (millions) 40 Year 0 1-3 4 -28 +15 +30 6-10 An internet company projects the following cash flows shown in the table below (in milions). Using a Net Present Worth Balancing Equation and a manual iteration process compute the Rate of Return....

  • There are two investment projects. Both projects will provide benefits to the city for the next...

    There are two investment projects. Both projects will provide benefits to the city for the next 30 years. The annual rate is 7%. Below are the initial cash outlays and monthly benefits: Ice Cream Shop Alternative Investment ($K) Monthly Benefits 1 0 0 2 3000 24.5 3 6000 58.5 4 9000 76.4 5 12000 85.5 Cookie Shop Alternative Investment ($K) Monthly Benefits 1 0 0 2 3000 28.6 3 6000 50.4 4 9000 65.5 5 12000 72.4 a) Find the...

  • Refer to the table below.             Quantity Cost (in dollars) Fixed Costs (in dollars) Total Costs...

    Refer to the table below.             Quantity Cost (in dollars) Fixed Costs (in dollars) Total Costs (in dollars) Average Total Costs (in dollars per unit) Average Variable Costs (in dollars per unit) Marginal Costs (in dollars per unit) 0 0 40 40 - - - - - - 1 1 40 55 15 55 15 2 35 40 75 17.5 37.5 20 3 60 40 100 20 33.3 25 4 90 40 130 22.5 32.5 30 5 125 40 155...

  • Q5. You have been hired to analyze the costs and benefits of constructing a new power...

    Q5. You have been hired to analyze the costs and benefits of constructing a new power plant for a large corporate campus. The plant will be adjacent to the campus to ensure a reliable power supply, and the alternatives are laid out below. Assume that the upfront construction costs are paid today and that the decadal operation and maintenance costs are paid in year 10. Also assume the timeline of the project is such that you are only concerned with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT