11. The public sector is thinking about undertaking one of this two projects, X or Y:

X

Y

Units: thousand of dollars

Benefits

Cost

Benefit

Cost

Year 0

100

1000

Year 1

500

Year 2

500

5000

Calculate the Net Present Value, the Internal Rate of Return and the Benefit/Cost ratio for the two projects using the Social Discount Rate suggested for the federal government for Canada. Which project should the public sector choose according to each of the three methods? Explain your answer.

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
11. The public sector is thinking about undertaking one of this two projects, X or Y:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A large city is considering two transportation projects to address its traffic congestion. The first one...

    A large city is considering two transportation projects to address its traffic congestion. The first one is a light-rail system while the second one is a new highway. Some economic data on both are presented below: Operating cost, First cost, million S millionShyear Project Light-rail system 45 8.5 Highway 73 In addition, the expected benefits from reduction in air pollution are $25 million per year in the case of the light-rail system and $22 million per year in the case...

  • (6) THINKING ABOUT COST-BENEFIT ANALYSIS. When evaluating how much to invest on a project the typical...

    (6) THINKING ABOUT COST-BENEFIT ANALYSIS. When evaluating how much to invest on a project the typical Present Value (PV) formula is used where R is the discount rate, Bt is the benefit, and Ct is cost the associated with the project in year t, and n is the number of years associated with the project a. What is the PV of $1 today? In one year (say March 30, 2017), what is the PV of $1 at b. Suppose that...

  • Public Goods EBE2053/EXERCISE 5 1. A pure public good is: a. one that can easily be...

    Public Goods EBE2053/EXERCISE 5 1. A pure public good is: a. one that can easily be sold by the unit. b. one that is nonrival in consumption. c. one whose benefits are not subject to exclusion. d. both (b) and (c) 2. The marginal cost of providing a certain quantity of a pure public good to an additional consumer after it is provided to any one consumer is: a. zero. b. positive and increasing. c. positive and decreasing. d. positive...

  • 11. NPV versus IRR Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash...

    11. NPV versus IRR Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) -$23,900 -$23,900 13,100 9,300 9,480 10,620 7,890 11,180 Sketch the NPV profiles for X and Y over a range of discount rates from 0 to 25 percent. What is the crossover rate for these two projects?

  • The government of XY Village has been concerned by the toxic air pollution risk in the village and initiated a new...

    The government of XY Village has been concerned by the toxic air pollution risk in the village and initiated a new policy campaign called "Clean Air Better Lives". Two green energy companies in the village, Green Ltd and Clean Air Ltd, proposed projects that can potentially deliver the objective of the campaign. The projects' benefit and cost streams are computed as follows. The discount rate for the projects is 9 %. 5 and 1 2 4 year after Green Benefits...

  • Question 2 Year DKW Inc., has two projects offering Project X and Project Y. They are...

    Question 2 Year DKW Inc., has two projects offering Project X and Project Y. They are mutually exclusive, and both require $350,000 for investment. The cost of capital is 10%. The following table are expected cash flow Project X ($) Project Y ($) 90,000 180,000 90,000 120,000 90,000 60000 90,000 50,000 90,000 50,000 90,000 2.1 Calculate Project X's the internal rate of return (IRR). Use formula of Time Value of Money to illustrate 23 Calculate payback period of both projects,...

  • Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows...

    Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 11%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers to two decimal...

  • 1. The time value of money refers to the fact that money has an opportunity cost,...

    1. The time value of money refers to the fact that money has an opportunity cost, i.e., its reinvestment rate. a. True b. False 2. If the payback period is used as the criterion for assigning priorities to investment projects, the highest priority will be assigned to projects with the shortest payback period. a. True b. False 3. The _______________ is the discount rate that makes the present value of the benefits generated by a project equal to the investment....

  • MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs...

    MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 14%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers...

  • MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs...

    MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 13%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT