Question

Problem 1 Tuxedo Company has several processing departments. Costs charged to the Assembly Department for October 2019 totale

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a

Material Conversion costs
Equivalent units    460,000                  439,000
Material Conversion costs
Cost per equivalent unit $      2.25 $                    0.60

Answer b

Cost allocation to units completed and ending work in progress
Cost of units transferred to finished goods $   1,211,250
Value of ending work in work in progress $        87,150

Answer c

Tuxedo company
Cost of Production Report
Whole units Equivalent units-Material Equivalent units-Conversion cost
Units to account for during production
Beginning work in progress          25,000
Started in process        435,000
Total units to be accounted for        460,000
Units to be assigned costs
Completed and transferred        425,000                                425,000 425000
Ending work in progress          35,000                                   35,000                                                14,000
Total units to be assigned costs        460,000                                460,000                                              439,000
Costs
Cost per equivalent unit
Total production costs $                         1,035,000 $                                          263,400
Total equivalent units                                460,000                                              439,000
Cost per equivalent unit $                                   2.25 $                                                0.60
Costs assigned to production
Beginning work in progress $                              45,500
Direct material, Direct labor and Factory Overheads incurred $                         1,252,900
Total costs accounted for $                         1,298,400
Cost allocation to units completed and ending work in progress
Cost of units transferred to finished goods $                         1,211,250
Value of ending work in work in progress $                              87,150
Total costs $                         1,298,400

In case of any doubt, please comment.

Add a comment
Know the answer?
Add Answer to:
Problem 1 Tuxedo Company has several processing departments. Costs charged to the Assembly Department for October...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • P21-4B Ignatenko Company has several processing departments. Costs charged to the Assembly Department for October 2012...

    P21-4B Ignatenko Company has several processing departments. Costs charged to the Assembly Department for October 2012 totaled $1,249,500 as follows. Work in process, October 1 Materials $29,000 Conversion costs 16,500 $ 45,500 Materials added 1,006,000 Labor 90,000 Overhead 108,000 Production records show that 25,000 units were in beginning work in process 40% complete as to conversion cost, 425,000 units were started into production, and 35,000 units were in ending work in process 40% complete as to conversion costs. Materials are...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,288,076 as follows. Work in process, November 1    Materials $79,000    Conversion costs 48,200 $127,200 Materials added 1,594,520 Labor 225,800 Overhead 340,556 Production records show that 34,600 units were in beginning work in process 30% complete as to conversion costs, 662,700 units were started into production, and 24,100 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,286,318 as follows. Work in process, November 1 Materials $78,900 Conversion costs 48,500 $127,400 Materials added 1,593,420 Labor 226,000 Overhead 339,498 Production records show that 34,800 units were in beginning work in process 30% complete as to conversion costs, 662,000 units were started into production, and 24,300 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,293,806 as follows. $78,800 49,000 Work in process, November 1 Materials Conversion costs Materials added Labor Overhead $127,800 1,599,280 225,800 340,926 Production records show that 34,700 units were in beginning work in process 30% complete as to conversion costs, 664,500 units were started into production, and 25,100 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • Problem 16-04A Rivera Company has several processing departments. Costs charged to the Assembly Department for November...

    Problem 16-04A Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,292,384 as follows. Work in process, November 1 Materials $78,900 Conversion costs 48.300 $127,200 Materials added 1,598,460 Labor 225,200 Overhead 341,524 Production records show that 35,200 units were in beginning work in process 30% complete as to conversion costs, 663,700 units were started into production, and 25,900 units were in ending work in process 40% complete as to conversion costs. Materials are...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,288,076 as follows. Work in process, November 1    Materials $79,000    Conversion costs 48,200 $127,200 Materials added 1,594,520 Labor 225,800 Overhead 340,556 Production records show that 34,600 units were in beginning work in process 30% complete as to conversion costs, 662,700 units were started into production, and 24,100 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,289,684 as follows. Work in process, November 1 Materials $78,700 48,100 Conversion costs Materials added Labor Overhead $126,800 1,596,500 225,100 341,284 Production records show that 35,400 units were in beginning work in process 30% complete as to conversion costs, 662,600 units were started into production, and 25,400 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • P16.4A (LO 3, 4), AP Rivera Company has several processing departments. Costs charged to the Assembly...

    P16.4A (LO 3, 4), AP Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2022 totaled $2,280,000 as follows. Assign costs and prepare production cost report. Work in process, November 1 Materials $79,000 Conversion costs 48,150 $ 127,150 Materials added 1,589,000 Labor 225.920 Overhead 337.930 Production records show that 35,000 units were in beginning work in process 30% complete as to conversion costs, 660,000 units were started into production, and 25,000 units were in ending...

  • Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled...

    Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,286,318 as follows. Work in process, November 1 Materials $78,900 Conversion costs 48,500 $127,400 Materials added 1,593,420 Labor 226,000 Overhead 339,498 Production records show that 34,800 units were in beginning work in process 30% complete as to conversion costs, 662,000 units were started into production, and 24,300 units were in ending work in process 40% complete as to conversion costs. Materials are entered at...

  • Problem 3-4A (Video) (Part Level Submission) Rivera Company has several processing departments. Costs charged to the...

    Problem 3-4A (Video) (Part Level Submission) Rivera Company has several processing departments. Costs charged to the Assembly Department for November 2020 totaled $2,313,896 as follows. Work in process, November 1    Materials $78,800    Conversion costs 48,100 $126,900 Materials added 1,622,970 Labor 225,100 Overhead 338,926 Production records show that 34,900 units were in beginning work in process 30% complete as to conversion costs, 659,700 units were started into production, and 24,100 units were in ending work in process 40% complete as to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT