Question

Q.1 Consider 3 projects for 50 years, and interest rate 10%. Use incremental B/C analysis to select project X, Y or Z. Х I O&

0 0
Add a comment Improve this question Transcribed image text
Answer #1

All figures in $'000s

Project X Y Z
Investment $8500 $10000 $12000
Operating & maintenance costs $750 $725 $700
Market value $1250 $1725 $2000
Benefits $2150 $2265 $2500

All projects have equal life of 50 years and interest rate is 10%

(i+1) - 1 i(1+i)n i,n) = (1 + i)-n i= 10% and n=50

We first find the present values of costs and benefits for each project

10%, 50) – MV 50) for project X Present value of costs, C = 1 + OM C4 = 8500 + 750 * 9.915 – 1250 * 0.00852 C = 8500 + 7436.2

10%, 50) for project Y, Present value of costs, Cy=I + OM* %, 50) – MV * Cy = 10000 + 725 * 9.915 – 1725 * 0.00852 Cy = 10000

%, 50) – MV*- 10%,50) for project 2, Present value of costs, C. = I + OM C. = 12000 + 700 * 9.915 – 2000 * 0.00852 C. = 12000

= 1.3385 Benefit - cost ratio for project X, BC, B Benefit - cost ratio for project Y, BCy B. 21317.25 15925.6 22457.475 1717

Benefit - cost ratio for project Z, BC, = C 24787.5 18923.46 = 1.3098

Since benefit-cost ratio exceeds 1,but project X has the highest ratio among the 3 projects

But for incremental benefit-cost analysis,we compare the projects incrementally

We first do incremental comparison between projects Z and Y

B- C-C- incremental Benefit-cost ratio for project Z over Y, BC.-y= 24787.5 - 22457.475 2330.025 18923.46 - 17173.678 1749.78

We now do incremental between projects Z and X

B. - B, incremental Benefit-cost ratio for project Z over X, BC.-- = BC3-1 C: - C, 24787.5 - 21317.25 3470.25 18923.46 – 1592

Based on incremental benefit-cost analysis, project Z is recommended for selection

Add a comment
Know the answer?
Add Answer to:
Q.1 Consider 3 projects for 50 years, and interest rate 10%. Use incremental B/C analysis to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 7 (1 point) In evaluating independent projects, no incremental analysis is necessary between projects. Each...

    Question 7 (1 point) In evaluating independent projects, no incremental analysis is necessary between projects. Each project is evaluated separately from others, and more than one project can be selected. Therefore, the only comparison is with the do-nothing alternative for each project. Question 7 options: True False 10. Given the following time events and incremental cash flow, if the MARR is 12% per year, which alternative should be selected on the basis of rate of return? Assume alternative B requires...

  • Consider the following A and B nvestment alternatives. Given that interest is 12% find X and...

    Consider the following A and B nvestment alternatives. Given that interest is 12% find X and Y? Which project you select? Year Project A($) Project B ($) 0 - 11000 -17000 1 9000 х 2 8000 х 3 7000 15000 NPW Y 12267 Select one: O a. X= 11000, Y=8396, Select B O b. X= 12000, Y=10000, Select A O c. X= 13500, Y=8500, Select B O d. X= 13000, Y=8546, Select A O e. X= 15000, Y=11317, Select A...

  • 4. Apply incremental conventional B/C analysis at an interest rate of 8% per year to determine...

    4. Apply incremental conventional B/C analysis at an interest rate of 8% per year to determine which alternative should be selected. Use a 20-year study period, and assume the damage costs might occur in year 6 of the study period. Alternative A 600,000 50,000 Alternative B Initial cost, S Annual M&O 800,000 70,000 costs, S/year Potential damage 950,000 250,000 costs, $ [Ans. Inc. B/C 1.11]

  • 1.) Projects A and B both have 5 years of life. The initial investments and cash...

    1.) Projects A and B both have 5 years of life. The initial investments and cash flows from these two projects are shown below. Year 0 1 2 3 4 5 Project A -12,300 4,500 4,000 3,500 3,000 2,500 Project B -15,000 6,000 5,000 4,000 3,200 2,400 A.) Use Data Table tool to find the NPVs of both projects when the discount rate is 10%. B.) Use Data Table tool to find the IRRs of both projects C.) Plot the...

  • 1.) Projects A and B both have 5 years of life. The initial investments and cash...

    1.) Projects A and B both have 5 years of life. The initial investments and cash flows from these two projects are shown below. Year 0 1 2 3 4 5 Project A -12,300 4,500 4,000 3,500 3,000 2,500 Project B -15,000 6,000 5,000 4,000 3,200 2,400 A.) Use Data Table tool to find the NPVs of both projects when the discount rate is 10%. B.) Use Data Table tool to find the IRRs of both projects C.) Plot the...

  • Q = -50 400 R = 12.00% AWC = AWB = 3. Use the following table...

    Q = -50 400 R = 12.00% AWC = AWB = 3. Use the following table to select the most profitable alternatives. You have to show the processes for your decision by providing the mathmetical equitions; like X > Y, etc. No written description to explanation is needed. MARR = 8.00% The values in the table represent Incremental IRR between Projects in colunm and row. You have to select on of the mutually exclusive alternatives; "Do Nothing" is not an...

  • D l Question 1 When calculating incremental cash flows, we should include O interest O financing...

    D l Question 1 When calculating incremental cash flows, we should include O interest O financing expenses Q sunk costs opportunity costs | Question 2 2 pts The cash flows that occur just because of a new project are called O marginal cash flows o project cash flos e additional cash flows O incremental cash flows 2 pts D | Question 3 Sun Corp. uses a discount rate of 6% for below-average risk projects, 8% for average-risk projects, and 10%...

  • Consider the following two independent investment projects: Cash flows of project A: 0 1 2 3...

    Consider the following two independent investment projects: Cash flows of project A: 0 1 2 3 T + + 100 -130 50 5 Cash flows of project B: 0 2 3 4 5 + + + + 다. -130 90 40 40 40 40 If management only accepts projects that pay back in 3 years or less, according to the discounted payback period rule, which projects will be selected? Use a discount rate of 10%.

  • 1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55,...

    1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...

  • Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1...

    Consider the following two projects: Discount Rate Project Year 0 Cash Flow -100 -73 Year 1 Cash Flow 40 30 30 Year 2 Cash Flow 50 30 Year 3 Cash Flow 60 30 Year 4 Cash Flow N/A 30 .15 B The payback period for project B is closest to: Select one: A.2.2 years B.2.5 years C.2.4 years D. 2.0 years

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT