Question

1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55,...

1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%.

(a) Compute NPV and IRR for project A.

(b) Compute NPV and IRR for project B.

(c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated project.

(d) Consider again the 1-year project B. Compute the (annualized) modified IRR assuming a reinvestment rate of 10%.

(e) Convert project A and project B into equivalent annuities (see slide 47).

2. Consider a two-year project with a 50% chance of success and failure. If successful, the project generates 100 per year, if not it generates 20 per year. The project requires an initial investment of 50 and the discount rate is 10%.

(a) What is the expected NPV?

(b) What is the probability that NPV < 0?

(c) Assume you can terminate the project after one year, i.e. after the first cash flow is realized. If you choose to terminate, you are able to recoup 50 (paid at the end of t 1).

i. What is the expected NPV?

ii. What is the probability that NPV < 0?

iii. What is the value of the option to terminate?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans.(a). Net Present Value(NPV) and Internal Rate of Return(IRR) of Project A:

NPV = Present value of Cash inflows - Present value of cash outflows

Cashflow in year 1 (1+r)1 Cashflow in year n NPV = Cashflow in year 2 Cashflow in year 3 (1+r)2 + (1 + r) 3 + ... + (1 + r) -

Here, r is the cost of capital

NPV = $150 $55 $85 |(1 + 5%)1+ (1 + 5%)2 + (1 + 5%)*|- $100

NPV = $166

Internal Rate of Return(IRR) is the return that the project will give if the NPV of the project is zero.

$150 $55 $85 NPV = ((1+r)1+ (1+r)2+(1+r)30 - $

$85 $150 = |a1 + IRR) 1 $55 (1 +IRR)2*(1 +IRR)

On solving, we get IRR of Project A= 99%

Ans. b. NPV and IRR of Project B:

Project B is only a one year project and generates $140 in year 1.

NPV = $140 (1 + 5%) (1 + 50 - $100

= $33

IRR of Project B:

IRR is calculated by keeping the NPV equal to zero.

NPV = 0 = $140 |(1+IRR)

Therefore, IRR of project B is 40%.

Ans. c.

On replicating the project B in the first and second year, we get a new set of cashflows. We can calculate the NPV as in image below:

Replicated Project B: Year -100 Cashflow Reinvestment Final Cashflow Present Value -$100 -$100 $140 -$100 $40 $38.10 $140 -$1

IRR of replicated project B is:

$40 $40 $140 1 NPV = V = (1+r)1+ (1+r)2+(1+r)31 - $11

$40 0 = $40 $140 |(1 + IRR)1 + (1 + IRR)2 + (1+1RR)*|-

therefore, IRR = 40%. Therefore, the replicated project gives the same internal rate of return as the previous project B.

Add a comment
Know the answer?
Add Answer to:
1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. You must analyze the cash flows of two projects, S and L. Project S: CF0...

    1. You must analyze the cash flows of two projects, S and L. Project S: CF0 = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CF0 = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better project? (Note: the better project may not be the one with the higher IRR)

  • Intro You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year...

    Intro You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50   Attempt 1/5 for 10 pts. Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV? The crossover rate is the discount rate at which both projects have the same NPV: NPV(A) = NPV(B) ⇔ NPV(A) - NPV(B) = 0 ⇔ NPV(A-B) =...

  • Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 =...

    Problem 3: A potential CB project has the following cash flows: CFO = -$500, CF1 = $300, CF2 = $200, CF3 = $150. WACC = 6%. Compute the following: V CPT DPB & NFV CPT (EX) A. Payback Period 3. NPV 86.9610 Accept project 2. IRR 16.4634 76 Accept project.

  • Teal Inc. now has the following two projects available: Project Initial CF 1 After-tax CF1 4,800...

    Teal Inc. now has the following two projects available: Project Initial CF 1 After-tax CF1 4,800 3,300 After-tax CF3 8,600 -11,337 -3,092 After-tax CF2 5,450 2,700 2 Assume that Rp = 4.1%, risk premium = 9.6%, and beta = 1.1. Use the chain replication approach to determine which project(s) Teal Inc. should choose if they are mutually exclusive. (Round cost of capital to 2 decimal places, e.g.17.35% and the final answers to o decimal places, e.g. 2,513.) NPV1 generated over...

  • 950 Sweet Inc. has two projects as follows: Project Initial CF CF1 CF2 CF3 CF4 А...

    950 Sweet Inc. has two projects as follows: Project Initial CF CF1 CF2 CF3 CF4 А -2,450 850 1,200 1,900 -3,000 750 1,500 1,050 3,900 Sweet set 2.6 years as a cut-off period for screening projects and the discount rate is 14 percent. Which project(s) will be selected if the company uses the discounted payback period method? (Round intermediate calculations to 5 decimal places, B Project A payback period years Project B payback period years will be selected Neither project...

  • Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you...

    Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you accept or reject the project if the discount rate is 12%? Group of answer choices Flip a coin Reject Accept

  • NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 6...

    NO COMPUTER SOFTWARE IS ALLOWED TO ANSWER THIS QUESTION Consider Table 2 3. Table 2 CF3 CF4 CF2 CF1 CFO Project 75 40 60 110 110 (200) (200) (200) 75 40 60 75 40 60 110 0.80 0.24 2.00 3.60 Interest Tax Shield Additional information for all projects 15% Cost (required return) on unlevered equity (%) Cost of debt capital (%) Corporation tax rate (%) Financing of each project: Debt 10% 20% 100 100 Equit alculate the value of project...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • #1 Questions a) to e) refer to two projects with the following cash flows: Year Project...

    #1 Questions a) to e) refer to two projects with the following cash flows: Year Project B Project A -$200 -$200 80 100 100 100 a) If the opportunity cost of capital is 10%, which of these projects is worth pursuing? Explain. b) Suppose that you can choose only one of these projects. Which would you choose? The discount rate is still 10%. Justify your reasoning. c) Which project would you choose if the opportunity cost of capital were 16%?...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ milion); Project Year Year 2 Year o -$48 - $101 Year 3 $21 $50 Year 4 $14 $27 $20 $40 $62 Tes a What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT