1. You must analyze the cash flows of two projects, S and L. Project S: CF0 = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CF0 = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better project? (Note: the better project may not be the one with the higher IRR)
Better project is the one that has higher NPV
Project S:
NPV = -1500 + 800 / (1 + 0.1)1 + 700 / (1 + 0.1)2 + 100 / (1 + 0.1)3 + 600 / (1 + 0.1)4
NPV = $290.73
Project L:
NPV = -1500 + 200 / (1 + 0.1)1 + 600 / (1 + 0.1)2 + 900 / (1 + 0.1)3 + 700 / (1 + 0.1)4
NPV = $331.98
Better project is project L as it has a higher NPV.
IRR is the rate of return that makes NPV equal to 0.
NPV = -1500 + 200 / (1 + R)1 + 600 / (1 + R)2 + 900 / (1 + R)3 + 700 / (1 + R)4
Using trial and error method, let's try R as 18.27%
NPV = -1500 + 200 / (1 + 0.1827)1 + 600 / (1 + 0.1827)2 + 900 / (1 + 0.1827)3 + 700 / (1 + 0.1827)4
NPV = 0
Therefore, IRR of project L is 18.27%
1. You must analyze the cash flows of two projects, S and L. Project S: CF0...
please give a written answer, please do not use excel as it has to be written out. thank you. You must analyze the cash flows of two projects, S and L. Project S: CFO = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CFO = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better...
2. A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 4 $900 $0 $10 $400 $10 $800 Project S $1,000 Project L $1,000 The company's WACC is 1 1%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) $250 $250
Intro You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50 Attempt 1/5 for 10 pts. Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV? The crossover rate is the discount rate at which both projects have the same NPV: NPV(A) = NPV(B) ⇔ NPV(A) - NPV(B) = 0 ⇔ NPV(A-B) =...
Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you accept or reject the project if the discount rate is 12%? Group of answer choices Flip a coin Reject Accept
1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 2 3 Project S - $1,000 $890.56 $250 $10 $10 Project L - $1,000 $0 $250 $400 $799.39 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 Project S -$1,000 $862.66 $260 $15 $10 Project L -$1,000 $10 $250 $380 $852.17 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 2 3 Project S Project L - $1,000 $897.60 - $1,000 $10 $240 $260 $ 10 $400 $10 $803.38 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 3 Project S Project L The company's WACC is 8.5 %. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your $15 -$1,000 $885.82 $250 $5 $1,000 $400 $847.76 $0 $250 answer to two decimal places
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $892.55 $240 $15 $10 Project L -$1,000 $5 $260 $380 $819.40 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.