Project S | Project L | |
0 | -1000 | -1000 |
1 | 900 | 0 |
2 | 250 | 250 |
3 | 10 | 400 |
4 | 10 | 800 |
IRR using Excel IRR funiton | 13.49% | 11.74% |
Project S is Better because of Higher IRR of 13.49% and also its more than WACC 11%
2. A company is analyzing two mutually exclusive projects, S and L, with the following cash...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 2 3 Project S - $1,000 $890.56 $250 $10 $10 Project L - $1,000 $0 $250 $400 $799.39 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 Project S -$1,000 $874.54 $250 $10 $10 Project L -$1,000 $5 $260 $400 $799.76 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 3 Project S Project L The company's WACC is 8.5 %. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your $15 -$1,000 $885.82 $250 $5 $1,000 $400 $847.76 $0 $250 answer to two decimal places
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 Project S -$1,000 $862.66 $260 $15 $10 Project L -$1,000 $10 $250 $380 $852.17 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $884.04 $250 $10 $10 Project L -$1,000 $10 $260 $420 $797.68 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $886.38 $250 $15 $10 Project L -$1,000 $0 $240 $400 $843.31 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $875.68 $260 $15 $5 Project L -$1,000 $10 $240 $400 $785.54 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 2 3 Project S Project L - $1,000 $897.60 - $1,000 $10 $240 $260 $ 10 $400 $10 $803.38 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S Project L - $1,000 $892.00 -$1,000 $5 $240 $250 $5 $420 $5 $819.46 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. Grade It Now Save & Continue Continue without saving
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $892.55 $240 $15 $10 Project L -$1,000 $5 $260 $380 $819.40 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.