Intro
You've estimated the following cash flows (in $ million) for two mutually exclusive projects:
Year | Project A | Project B |
0 | -28 | -43 |
1 | 30 | 45 |
2 | 40 | 50 |
Attempt 1/5 for 10 pts.
Part 1
What is the crossover rate, i.e., the discount rate at which both projects have the same NPV?
The crossover rate is the discount rate at which both projects have the same NPV:
NPV(A) = NPV(B)
⇔ NPV(A) - NPV(B) = 0
⇔ NPV(A-B) = 0
A | B | C | D | |
1 | Year | Project A | Project B | Difference A-B |
2 | 0 | -28 | -43 | 15 |
3 | 1 | 30 | 45 | -15 |
4 | 2 | 40 | 50 | -10 |
NPV of cash flow differences:
NPVA−B =(CF0,A−CF0,B)+CF1,A−CF1,B1+r+CF2,A−CF2,B(1+r)2=0NPVA-B =(CF0,A-CF0,B)+CF1,A-CF1,B1+r+CF2,A-CF2,B(1+r)2=0
⇔ 15+−151+r+−10(1+r)2=015+-151+r+-10(1+r)2=0
We can use the quadratic formula, trial and error, a financial
calculator or Excel's IRR function to solve for r. Using
Excel:
=IRR(D2:D4)
We then find that the crossover rate is 45.74%, or 0.457.Correct ✓
Part 2
What is project A's NPV at the crossover rate?
Please refer to below spreadsheet for calculation and answer. Cell reference also provided.
Cell reference -
Hope this will help, please do comment if you need any further explanation. Your feedback would be highly appreciated.
Intro You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50 Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV?
1. You must analyze the cash flows of two projects, S and L. Project S: CF0 = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CF0 = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better project? (Note: the better project may not be the one with the higher IRR)
1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...
Consider the following two mutually exclusive projects: Year Cash Flow (X) -$20,800 9,050 9,500 9,000 Cash Flow (Y) 220,800 10,500 8,000 8,900 WN- Calculate the IRR for each project. (Do not round Intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) IRR Project X Project Y What is the crossover rate for these two projects? (Do not round Intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Crossover...
, A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects I and II, with cash flows at t0,1 and 2 as follows: Year t Project I Project II - $10,000 +20,000 +10,000 $10,000 +$40,000 Compute each project's NPV for r=0% and r=10%, where r= discount rate or required rate Based on the cash flow patterns for the two projects and the answer to part a), can we Using the analytical formulation of the intersection of...
14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows of each project: 0 1 2 3 4 A -$50 25 20 20 15 B -$100 20 40 50 60 a. If your discount rate is 6%, what are the NPVs of the two projects? b. What are the IRRs of the two projects? c. Why do IRR and NPV rank the two projects differently? NPV IRR
You are analyzing two mutually exclusive projects with the cash flows shown below. The cash flows are in millions. Both projects are equally risky. Your costs of capital are 12%. Year Project 1 Project 2 0 -$140 -$90 1 $50 $40 2 $45 $35 3 $40 $30 4 $35 $25 5 $30 $20 6 $25 $15 7 $20 $10 8 $15 $5 9 $10 $0 10 $5 -$5 Compute the NPVs of the two projects. b. Compute the IRRs of...
Consider the following cash flows of two mutually exclusive projects for a company. Assume the discount rate for the company is 10 percent. (5pts) Year A B 0 -$1,400,000 -$600,000 1 900,000 300,000 2 800,000 500,000 3 700,000 400,000 a. Based on the payback period, which project should be taken? b. Based on the NPV, which project should be taken? c. Based on IRR, which project should be taken? d. Based on this analysis, is incremental IRR analysis necessary? If...
We have two mutually exclusive investments with the following cash flows: (13 marks total) Year Investment A Investment B 0 –$100 –$100 1 10 50 2 30 40 3 50 30 4 70 20 a. Using a financial calculator, calculate the IRR for each of the investments. State your answers in percentages rounded to two decimal places. (2 marks) b. Calculate the NPV profile for each investment, using the discount rates of 0%, 5%, 10%, 15%, 20%, and 25%. Perform this task in an...
Bruin, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$36,600 –$36,600 1 18,930 6,490 2 14,430 12,990 3 11,930 19,490 4 8,930 23,490 a. What is the IRR for Project A? b. What is the IRR for Project B? c. If the required return is 14 percent, what is the NPV for Project A? d. If...