Question

Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

Question 3:

Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:

                                            2017                                    2018

Current year construction costs                                       $3,300,000                             $ 620,000

Estimated remaining costs to complete                              600,000                                   -0-

Current year billings                                                            3,100,000                              1,400,000

Current year collections                                                    3,000,000                                1,500,000

Required: Calculate the following amounts for each method:

              Completed Percentage-of Contract Completion                                   2017      2018    2017    2018

a) Gross Profit                                                                                              $             $           $           $

b) Construction in progress year-end balance                                       $           $            $           $

c) Costs in excess of billings (Billings in excess of costs)                       $           $            $           $

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Schedule showing gross profit (loss) under percentage-of-completion method:
2017 2018
Particulars Amount ($) Amount ($)
Contract revenue                              4,500,000.00                              4,500,000.00
Costs incurred                              3,300,000.00                                 620,000.00
Estimated costs to complete                                 600,000.00
Billings                              3,100,000.00                              1,400,000.00
Cash collections                              3,000,000.00                              1,500,000.00
Percentage of completion = Costs incurred/(Costs incurred+Estimated costs) 3300000/(3300000+600000) -
Percentage of completion 85% 100%
Percentage of contract revenue to be recognised 85% 100%
Contract revenue recognised                              3,807,692.31                                 692,307.69
Less: Contract costs
Costs incurred                              3,300,000.00                                 620,000.00
Total costs                              3,300,000.00                                 620,000.00
Profit on contract                                 507,692.31                                   72,307.69
Construction in progress = Costs +Profit 3300000+507692                                                -  
                             3,807,692.31                                                -  
Costs in excess of billings
= Costs - Billings
3300000-3100000 3300000+620000-3100000-1400000
                                200,000.00                                 580,000.00
Add a comment
Know the answer?
Add Answer to:
Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin...

    Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin began work under contract E2-02, which provided for a contract price of 52,195,000. Other details follow 2017 2018 Costs incurred during the year 5695,310 $1,404,000 Estimated costs to complete, as of December 31921,690 0 Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in...

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract...

    Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract #E2-D2, which provided for a contract price of $2,195,000. Other details follow: 2017 2018 Costs incurred during the year $695,310 $1,404,000 Estimated costs to complete, as of December 31 921,690 –0– Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $ Revenue...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

    Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring: a. costs incurred in the first year, divided by estimated remaining costs to complete the project. b. costs incurred in the first year, divided by estimated total cost of the completed project. c. costs incurred in the first year, divided by estimated gross profit. d. none of the above.    2.As of...

  • Sad Construction Company uses the percentage-of-completion method when total con- struction costs can be estimated. Sad...

    Sad Construction Company uses the percentage-of-completion method when total con- struction costs can be estimated. Sad is building an office building for Porter Company for $10,000,000 with the following details: 12/31/2004 12/31/2005 12/31/2006 Costs incurred to date $2,000,000 $3,500,000 $6,500,000 Estimated costs to complete 6,000,000 4,500,000 1,500,000 Billings to date 6,000,000 8,000,000 10,000,000 Collections to date 3,000,000 5,500,000 10,000,000 Required: 1. Prepare all journal entries for 2004 that Sad should make for this job. 2. Prepare all journal entries for...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT