Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow.
2017 2018
Costs incurred during the year $450,000 $1,100,000
Total costs 1,050,000 50,000
Percentage of completion 30% 96.875%
Billings during the year 500,000 1,400,000
Cash collections during the year 400,000 1,400,000
Assume the Beavis recognizes revenue on the contract over time according to percentage of completion
Required
1. Compute the amounts of revenue and gross profit (or loss) to be recognized in 2017 and 2018. Please label whether it is a profit or loss.
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Davis Construction Company | |||
Workings for Ans to 1 | Calculation of Gross Profit | ||
Particulars | 2018 | 2019 | Note |
Contract Price | 2,000,000 | 2,000,000 | A |
Cost Incurred during the year | 450,000 | 1,100,000 | B |
Estimated cost to complete | 1,050,000 | 50,000 | C |
Cost Incurred to date | 450,000 | 1,550,000 | D |
(Sum total of the cost incurred during the year) | |||
Estimated total cost | 1,500,000 | 1,600,000 | E=C+D |
Percentage complete | 30.00% | 96.875% | F=D/E |
(Cost Incurred to date/Estimated total cost) | |||
Revenue to be recognized | 600,000 | 1,337,500 | G |
(Contract Price*Percentage complete)- revenue previously recognized |
Year 2018: 30% completed. Revenue recognized = 30% x $ 2,000,000 = $ 600,000. |
Year 2019: 96.875% completed. Revenue recognized = 96.88% x $ 2,000,000 – $ 600,000 (previously recognized) = $ 1,337,500. |
Ans to 1 | ||
Gross Profit | 150,000 | 237,500 |
Billings during the year | 500,000 | 1,400,000 |
Collection during the year | 400,000 | 1,400,000 |
2018 | 2019 | |||||
Ans to 2 | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | |
Costs Incurred | CIP (Work-in-progress) | 450,000 | 1,100,000 | |||
Cash | 450,000 | 1,100,000 | ||||
Billing | Accounts Receivable | 500,000 | 1,400,000 | |||
Billing on CIP | 500,000 | 1,400,000 | ||||
Receiving Payments | Cash | 400,000 | 1,400,000 | |||
Accounts Receivable | 400,000 | 1,400,000 | ||||
Period end adjustments for Revenue | Construction Expense | 450,000 | 1,100,000 | |||
(Gross Profit entry) | CIP (Work-in-progress) | 150,000 | 237,500 | |||
Construction Revenue | 600,000 | 1,337,500 |
Workings for Balance Sheet | |
CIP (Work-in-progress) | |
Account | Amount ($) |
Cash | 450,000 |
Construction Revenue | 150,000 |
Balance at the end of 2018 | 600,000 |
Cash | 1,100,000 |
Construction Revenue | 237,500 |
Balance at the end of 2019 | 1,937,500 |
Accounts Receivable | |
Account | Amount ($) |
Billing on CIP | 500,000 |
Cash | (400,000) |
Balance at the end of 2018 | 100,000 |
Billing on CIP | 1,400,000 |
Cash | (1,400,000) |
Balance at the end of 2019 | 100,000 |
Billing on CIP | |
Account | Amount ($) |
Accounts Receivable | 500,000 |
Balance at the end of 2018 | 500,000 |
Accounts Receivable | 1,400,000 |
Balance at the end of 2019 | 1,900,000 |
Ans to 3 | ||
Balance Sheet (Partial) | 2018 | 2019 |
Current Assets: | ||
CIP (Work-in-progress) | 600,000 | 1,937,500 |
Accounts Receivable | 100,000 | 100,000 |
700,000 | 2,037,500 | |
Current Liabilities: | ||
Billing on CIP | 500,000.00 | 1,900,000.00 |
500,000.00 | 1,900,000.00 |
Davis Construction company was a low bidder on a construction project to build and earthen dam...
Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30% 96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. $ Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 450,000 $1,100,000 1,050,000 400,000 1,400,000 300,000 1,500,000 Assume that Beavis recognizes revenue upon completion of the project. Required: Compute the amount of gross profit...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 2021 $458,500 $1,080,000 851,500 495.000 1.285.000 395,000 1,385,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...
Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...
Required information The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,830,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 441,000 $1,130,000 1,029.000 D 415,000 1,415,000 315,000 2,515,000 Assume that Beavis recognizes revenue on...
Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below 2018 2017 $476,eee $1,030,e0e 884,e00 470,000 Costs incurred during the year Estimated costs to complete Billings during the yearr Cash collections during the year 1,260,00e 1,415,00e 370,000 Assume that Beavis recognizes revenue on this...
Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...
Required information SB Problem The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 $ 450,000 $1,108, eee 1,050,000 400,000 1,400,000 300,000 1,500,000 Problem 5-284 Assume...