Question

Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

Required information

[The following information applies to the questions displayed below.]

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:

2017 2018
Costs incurred during the year $ 469,000 $ 1,050,000
Estimated costs to complete 871,000 0
Billings during the year 480,000 1,270,000
Cash collections during the year 380,000 1,425,000

Assume that Beavis recognizes revenue upon completion of the project.

Required:
Compute the amount of gross profit recognized during 2017 and 2018. (Leave no cells blank - be certain to enter "0" wherever required.)

Gross Profit 2017 ____

Gross Profit 2018 ____

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Gross profit 2017 = 0

Gross profit 2018 = $231,000 [$1,750,000 - 1,519,000 (469,000+1,050,000)]

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...

  • Required information SB Problem [The following information applies to the questions displayed below. Beavis Construction Company...

    Required information SB Problem [The following information applies to the questions displayed below. Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,740,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year $405,000 $1,040,000 945,000 475,000 1,265,000 375,000 1,420,000 Problem 5-286 Assume that Beavis...

  • Required information The following information applies to the questions displayed below.) Beavis Construction Company was the...

    Required information The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,830,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 441,000 $1,130,000 1,029.000 D 415,000 1,415,000 315,000 2,515,000 Assume that Beavis recognizes revenue on...

  • Required information SB Problem The following information applies to the questions displayed below.) Beavis Constru...

    Required information SB Problem The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 $ 450,000 $1,108, eee 1,050,000 400,000 1,400,000 300,000 1,500,000 Problem 5-284 Assume...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. $ Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 450,000 $1,100,000 1,050,000 400,000 1,400,000 300,000 1,500,000 Assume that Beavis recognizes revenue upon completion of the project. Required: Compute the amount of gross profit...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below 2018 2017 $476,eee $1,030,e0e 884,e00 470,000 Costs incurred during the year Estimated costs to complete Billings during the yearr Cash collections during the year 1,260,00e 1,415,00e 370,000 Assume that Beavis recognizes revenue on this...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The pr...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT