Question

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. The project w
View transaction list 1 Record the entry for costs incurred during the year 2020. 2 Record the entry for billings during the
8 Record the entry for revenue from long-term contracts. 9 Record the entry to close the construction accounts. Note : = jour
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer -

Journal entries :

1.

Date General Journal Debit Credit
2020 Construction in progress $458500
   Cash or Accounts payable $458500

2.

Date General Journal Debit Credit
2020 Accounts receivable $495000
   Billing on construction Contract $495000

3.

Date General Journal Debit Credit
2020 Cash $395000
   Accounts receivable $395000

4.

Date General Journal Debit Credit
2020 Construction in progress $164500
Cost of construction $458500
   Revenue from long-term contracts $623000

5.

Date General Journal Debit Credit
2021 Construction in progress $1080000
   Cash or Accounts payable $1080000

6.

Date General Journal Debit Credit
2021 Accounts receivable $1285000
   Billing on construction Contract $1285000

7.

Date General Journal Debit Credit
2021 Cash $1385000
   Accounts receivable $1385000

8.

Date General Journal Debit Credit
2021 Construction in progress $77000
Cost of construction $1080000
   Revenue from long-term contracts $1157000

9.

Date General Journal Debit Credit
2021 Billing on construction Contract $1780000
   Construction in progress $1780000

Calculation :

2020 2021
Percent complete Actual cost incurred / (Total actual costs + Estimated cost to date) $458500 / ($458500 + $851500) = 35% 100%
Revenue recognized (Total estimated revenue * Percent complete) - Previous revenue recognized ($1780000 * 35%) - $0 = $623000 $1780000 - $623000 = $1157000
Gross profit recognized Revenue recognized - Actual cost incurred $623000 - $458500 = $77000 $1157000 - $1080000 = $77000

Total billings = $495000 ( During Year 2020) + $1285000 (During Year 2021)

Total billings = $1780000

Add a comment
Know the answer?
Add Answer to:
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. T...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The pr...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. $ Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 450,000 $1,100,000 1,050,000 400,000 1,400,000 300,000 1,500,000 Assume that Beavis recognizes revenue upon completion of the project. Required: Compute the amount of gross profit...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below 2018 2017 $476,eee $1,030,e0e 884,e00 470,000 Costs incurred during the year Estimated costs to complete Billings during the yearr Cash collections during the year 1,260,00e 1,415,00e 370,000 Assume that Beavis recognizes revenue on this...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT