Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price
Journal entry worksheet Record the construction costs. Note: Enter debits before credits. Year Debit Credit 2021 General Jour
Journal entry worksheet Record the progress billings. Note: Enter debits before credits. Debit Credit Year 2021 General Journ
Journal entry worksheet 0 2 Record the cash collections. Note: Enter debits before credits. Year Debit Credit 2021 General Jo
Journal entry worksheet Record the gross profit or loss. Note: Enter debits before credits. General Journal Debit Credit Year
Journal entry worksheet Record the construction costs. Note: Enter debits before credits. Debit Credit Year 2022 General Jour
Journal entry worksheet 4 Record the progress billings. Note: Enter debits before credits. Debit Credit Year 2022 General Jou
Journal entry worksheet Record the cash collections. Note: Enter debits before credits. Debit Credit Year 2022 General Journa
Journal entry worksheet Record the gross profit or loss. Note: Enter debits before credits. General Journal Debit Credit Year
Balance Sheet At December 31, 2021 Current assets: Accounts receivable Current liabilities:
Prepare a partial balance sheet to show the presentation of the project a calculations. Round your answers to the nearest dol
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

1.

Particulars

31. Dec. 2021

31. Dec. 2022

31. Dec. 2023

   Cumulative Revenue (WN -1)

     Revenue for the C.Y

(-) Cost incurred during the year

Profit to be recognized

$2,921,875

$4,749,800

$8,500,000

$2,921,875

$2,200,000

$1,827,925

$2,740,000

$3,750,200

$4,000,000

$721,875

($912,075)

($249,800)

Workings:

  1. % of Completion = Costs incurred to date / Total costs ×100

= $2,200,000 / $6,400,000 ×100

= 34.375%

= $4,940,000 / $8,840,000 ×100

= 55.88%

= $8,940,000 / $8,940,000 ×100

= 100%

  1. Contract Revenue     = Contract Price × % of Completion

= $8,500,000 * 34.375%

= $2,921,875

= $8,500,000* 55.88%

= $4,749,800

= $8,500,000* 100%

= $8,500,000

2a. Journal Entries for 2021

Year

General Journal

Debit $

Credit $

2021

Construction in Progress

           To Cash

2,200,000

2,200,000

Accounts Receivable

           To Billing on Construction Contract

2,740,000

2,740,000

Cash

           To Accounts Receivable

2,450,000

2,450,000

Construction in Progress (Profit)

Construction Expense

           To Construction Revenue

721,875

2,200,000

2,921,875

2b. Journal Entries for 2022

Year

General Journal

Debit $

Credit $

2022

Construction in Progress

           To Cash

2,740,000

2,740,000

Accounts Receivable

           To Billing on Construction Contract

2,990,000

2,990,000

Cash

           To Accounts Receivable

2,675,000

2,675,000

Construction Expense

           To Construction Revenue

           To Construction in Progress

2,740,000

1,827,925

912,075

3a.

Balance Sheet as at 2021

Current Assets:

Account Receivables

Cash (2,450,000 – 2,200,000)

Construction in Progress (2,000,000 + 721,875)

290,000

250,000

2,721,875

3b.

Balance Sheet as at 2022

Current Assets:

Account Receivables

Construction in Progress (2,740,000 – 912,075)

Current Liabilities:

Bank Overdraft (2,740,000 – 2,675,000)

315,000

1,827,925

65,000

Add a comment
Know the answer?
Add Answer to:
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to...

    Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT