1. Computation of amount of revenue and gross profit using percentage of completion method.
Particulars | 2021 | 2022 | 2023 |
Contract price | 8,300,000 | 8,300,000 | 8,300,000 |
Cost incurred during the year | 2,100,000 | 2,600,000 | 3,900,000 |
Estimated cost to complete (A) | 4,100,000 | 3,750,000 | - |
Cost incurred up-to date (Sum of total costs incurred during the year) B | 2,100,000 | 4,700,000 | 8,600,000 |
Estimated total cost (A+B) | 6,200,000 | 8,450,000 | 8,600,000 |
% of completion (Cost incurred up-to date /total cost ) | 33.87% | 55.62% | 100% |
Revenue to be recognized |
(33.87%*8,300,000) =2,811,210 |
(55.62%*8,300,000-2,811,210) =1,805,250 |
(100%*8,300,000-2,811,210-1,805,250) =3,683,540 |
Gross profit /(loss) = Revenue to be recognized -cost incurred during the year | 711,210 | (794,750) | (216,460) |
Bills during the year | 2,600,000 | 2,850,000 | |
Collections during the year | 2,350,000 | 2,575,000 |
2(a)&(b) 2021. 2022
Journal entries | Debit | Credit | Debit | Credit | |
Costs incurred |
CIP To Cash |
2100,000 | 2100,000 | 2600,000 | 2,600,000 |
Billing |
AR To billing on CIP |
2600,000 | 2600,000 | 2850,000 | 2,850,000 |
Receiving payment |
cash To AR |
2,350,000 | 2,350,000 | 2,575,000 | 2,575,000 |
Period end adjustment for revenue (GP) |
Construction expense CIP(WIP) To Construction Revenue |
2100,000 711,210 |
2,811,210 |
||
Period end adjustment for revenue (GL) |
construction expense To CIP(WIP) Construction revenue |
2,600,000 |
794,750 1,805,250 |
||
3.(a) &(b) partial balancesheet
Particulars | 2021 | 2022 |
CA | ||
CIP(WIP) | 2100,000+711,210=2,811,210 | 2,811,210+2,600,000-794,750=4,616,460 |
Accounts receivable | 2,600,000-2,350,000=250,000 | 2,850,000-2,575,000+250000=525,000 |
Total | 3,061,210 | 5,141,460 |
CL | ||
Billing on CIP | 2,600,000 | 5,450,000(2600,000+2850,000) |
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of $3,900,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...