Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price
Percentages of completion Choose numerator + Choose denominator % complete to date 2021 2022 2023 $ $ 2,080,000 4,660,000 8,5
wwwuu were curreu. Te LII. A wiecognizes revenue over time according to percentage of completion. Required: 1. Compute the am
Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 2022, and 2023 using the percent
Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percen
PLULUI UE project as of December 31, 2021 3b. Prepare a partial balance sheet to show the presentation of the project as of D
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Percentage of completion=Cost incurred during the year/Total estimated cost
Revenue to be recognized=(Contract price*Percentage of completion)-Revenue already recognized
Gross profit/(loss) to be recognized=(Estimated gross profit/(Loss) *percentage of completion)-Gross profit already recognized
Estimated gross profit/(loss)=Contract price-Total estimated costs
2021 2022 2023
a) Contract price 8240000 8240000 8240000
b) Actual cost to date 2080000 4660000 8540000
(2080000+2580000) (4660000+3880000)
c) Estimated costs to complete 4080000 3720000 0
d) Total estimated costs (b)+© 6160000 8380000 8540000
e) Estimated gross profit/(loss) (a)-(d) 2080000 -140000 -300000
f) Percentage of completion (b)/(d) 33.77% 55.61% 100.00%
g) Revenue to be recognized 2782338 1737662 3720000
(8240000*33.77%)-0 Note:1 (Note:2)
h) Gross profit/(loss) to be recognized 702338 -842338 -160000
(2080000*33.77%)-0 (Note:1) (Note:2)
Note:1
If estmated gross loss appears,then entire loss has to be recognized in that year itself irrespective of percentage of completion method
Hence,loss to be recognized=140000+702338=$ 842338
Revenue to be recognized=Expense to be recognized-loss to be recogized=2580000-842338=1737662
Note:2
Hence,loss to be recognized=-300000+140000=$ -160000
Revenue to be recognized=Expense to be recognized-loss to be recogized=3880000-160000=3720000
Percentages of completion
Year Actual cost to date / Estimated total costs = % complete to date
2021 2080000 / 6160000 = 33.7662%
2022 4660000 / 8380000 = 55.6086%
2023 8540000 / 8540000 = 100.0000%
2021
To date Recognized in prior years Recognized in 2021
a b a-b
Construction revenue 2782338 0 2782338
Construction expense 2080000 0 2080000
Gross profit (loss) 702338 0 702338
2022
To date Recognized in prior years Recognized in 2022
a b a-b
Construction revenue 1737662
(Note:1)
Construction expense 4660000 2080000 2580000
Gross profit (loss) -140000 702338 -842338
2023
To date Recognized in prior years Recognized in 2023
a b a-b
Construction revenue 3720000
(Note:2)
Construction expense 8540000 4660000 3880000
Gross profit (loss) -300000 -140000 -160000
Journal entries:
2-a. Date Account Titles and Explanation Debit Credit
2018 Construction in progress 2080000
Various accounts 2080000
(Construction cost incurred)
Accounts receivable 2580000
Billings on construction contract 2580000
(Billings during the year)
Cash 2330000
Accounts receivable 2330000
(Cash collections during the year)
Construction in progress 702338
Cost of construction 2080000
Revenue from long-term contracts 2782338
(Gross profit and revenue recognized)

Add a comment
Know the answer?
Add Answer to:
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000 In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000.2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of $3,880,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT