Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price
Prepare a partial balance sheet to show the presentation of the project as of December 31, 20 calculations. Round your answer
Prepare a partial balance sheet to show the presentation of the project as of calculations. Round your answers to the nearest
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
Part 1
2021 2022 2023
Contract price $                                                    8,240,000 $                                                                                 8,240,000 $                                                                                 8,240,000
Actual costs to date $                                                    2,080,000 $                                                                                 4,660,000 $                                                                                 8,540,000
Estimated costs to complete $                                                    4,080,000 $                                                                                 3,720,000 $                                                                                                -  
Total estimated costs $                                                    6,160,000 $                                                                                 8,380,000 $                                                                                 8,540,000
Estimated gross profit
   (actual in 2020) $                                                    2,080,000 $                                                                                   -140,000 $                                                                                   -300,000
Revenue Recognition: 33.77% 55.61%
2021 $2,080,000/$6,160,000 = 33.77% x $8,240,000 $                                                                                 2,782,338
     
2022 $4,660,000/$8,380,000 = 55.61% x $8,240,000 = $4,582,148 – 2,782,338 $                                                                                 1,799,810
2023 $8,240,000-$2,782,338-$1,799,810 $                                                                                 3,657,852
Gross profit (loss) recognized:
2021 $2,782,338-$2,080,000 $                                                                                     702,338
     
2022 ($140,000)-$702,338 $                                                                                  (842,338)
2023 ($300,000)-($140,000) $                                                                                   -160,000
Part 2a and 2b
Year 2021 Year 2022
Construction in Progress $                                                                                 2,080,000 $                                                                                 2,580,000
     Various Accounts $                                                                                 2,080,000 $                                                                                 2,580,000
Accounts Receivable $                                                                                 2,580,000 $                                                                                 2,830,000
     Billing on Construction Contracts $                                                                                 2,580,000 $                                                                                 2,830,000
Cash $                                                                                 2,330,000 $                                                                                 2,555,000
     Accounts Receivable $                                                                                 2,330,000 $                                                                                 2,555,000
Cost of Construction $                                                                                    702,338
Construction in progress $                                                                                 2,080,000
     Revenue from long term contracts $                                                                                 2,782,338
Cost of Construction $                                                                                 2,642,148
Revenue from long term contracts $                                                                                 1,799,810
     Construction in progress $                                                                                     842,338
Requirement 3a and 3b
Year 2021 Year 2022
Current Assets:
Accounts Receivable $                                                                                    250,000 $                                                                                     525,000
Costs and Profit $2,782,338 in excess of billing $2,580,000 $                                                                                    202,338
Current Liabilities:
Billings $5,410,000 in excess of costs less loss $                                                                                     890,000
($4,660,000-$140,000)=$4,520,000
Add a comment
Know the answer?
Add Answer to:
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to...

    Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT