On February 1, 2021, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,400,000. During 2021, costs of $2,160,000 were incurred, with
estimated costs of $4,160,000 yet to be incurred. Billings of
$2,692,000 were sent, and cash collected was $2,410,000.
In 2022, costs incurred were $2,692,000 with remaining costs
estimated to be $3,840,000. 2022 billings were $2,942,000, and
$2,635,000 cash was collected. The project was completed in 2023
after additional costs of $3,960,000 were incurred. The company’s
fiscal year-end is December 31. This project does not qualify for
revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross
profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2021 to record the
transactions described (credit "various accounts" for construction
costs incurred).
2b. Prepare journal entries for 2022 to record the
transactions described (credit "various accounts" for construction
costs incurred).
3a. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2022.
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Arrow Construction Company | ||||
Ans to 1 | Calculation of Gross Profit | |||
Particulars | 2021 | 2022 | 2023 | Note |
Contract Price | 8,400,000 | 8,400,000 | 8,400,000 | A |
Cost Incurred during the year | 2,160,000 | 2,692,000 | 3,960,000 | B |
Estimated cost to complete | 4,160,000 | 3,840,000 | - | C |
Cost Incurred to date | 2,160,000 | 4,852,000 | 8,812,000 | D |
(Sum total of the cost incurred during the year) | ||||
Estimated total cost | 6,320,000 | 8,692,000 | 8,812,000 | E=C+D |
Percentage complete | 34.18% | 55.82% | 100.00% | F=D/E |
(Cost Incurred to date/Estimated total cost) | ||||
Revenue to be recognized | 2,870,886 | 1,818,115 | 3,710,999 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||||
Year 2021: 34.18% completed. Revenue recognized = 34.18% x $ 8,400,000 = $ 2,870,886. | ||||
Year 2022: 55.82% completed. Revenue recognized = 55.82% x $ 8400,000 – $ 2,870,886 (previously recognized) = $ 1,818,115. | ||||
Year 2023: 100% completed. Revenue recognized = 100% x $ 8,400,000 – $ 2,870,886- $ 1,818,115 (previously recognized) = $ 3,710,999. |
2021 | 2022 | |||||
Ans to 2a and 2b | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | |
Costs Incurred | CIP (Work-in-progress) | 2,160,000 | 2,692,000 | |||
Cash | 2,160,000 | 2,692,000 | ||||
Billing | Accounts Receivable | 2,692,000 | 2,942,000 | |||
Billing on CIP | 2,692,000 | 2,942,000 | ||||
Receiving Payments | Cash | 2,410,000 | 2,635,000 | |||
Accounts Receivable | 2,410,000 | 2,635,000 | ||||
Period end adjustments for Revenue | Construction Expense | 2,160,000 | ||||
(Gross Profit entry) | CIP (Work-in-progress) | 710,886 | ||||
Construction Revenue | 2,870,886 | |||||
Period end adjustments for Revenue | Construction Expense | 2,692,000 | ||||
(Gross Profit entry) | CIP (Work-in-progress) | 873,885 | ||||
Construction Revenue | 1,818,115 |
Workings for Balance Sheet | |
CIP (Work-in-progress) | |
Account | Amount ($) |
Cash | 2,160,000 |
Construction Revenue | 710,886 |
Balance at the end of 2021 | 2,870,886 |
Cash | 2,692,000 |
Construction Revenue | (873,885) |
Balance at the end of 2022 | 4,689,001 |
Accounts Receivable | |
Account | Amount ($) |
Billing on CIP | 2,692,000 |
Cash | (2,410,000) |
Balance at the end of 2021 | 282,000 |
Billing on CIP | 2,942,000 |
Cash | (2,635,000) |
Balance at the end of 2022 | 589,000 |
Billing on CIP | |
Account | Amount ($) |
Accounts Receivable | 2,692,000 |
Balance at the end of 2021 | 2,692,000 |
Accounts Receivable | 2,942,000 |
Balance at the end of 2022 | 5,634,000 |
Ans to 3a and 3b | ||
Balance Sheet (Partial) | 2021 | 2022 |
Current Assets: | ||
CIP (Work-in-progress) | 2,870,886 | 4,689,001 |
Accounts Receivable | 282,000 | 589,000 |
3,152,886 | 5,278,001 | |
Current Liabilities: | ||
Billing on CIP | 2,692,000.00 | 5,634,000.00 |
2,692,000.00 | 5,634,000.00 |
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000 In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000.2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of $3,880,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...