Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000.
In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of $3,960,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Arrow Construction Company
Ans to 1 Calculation of Gross Profit
Particulars 2021 2022 2023 Note
Contract Price          8,400,000          8,400,000          8,400,000 A
Cost Incurred during the year          2,160,000          2,692,000          3,960,000 B
Estimated cost to complete          4,160,000          3,840,000                        -   C
Cost Incurred to date          2,160,000          4,852,000          8,812,000 D
(Sum total of the cost incurred during the year)
Estimated total cost          6,320,000          8,692,000          8,812,000 E=C+D
Percentage complete 34.18% 55.82% 100.00% F=D/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized          2,870,886          1,818,115          3,710,999 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2021: 34.18% completed. Revenue recognized = 34.18% x $ 8,400,000 = $ 2,870,886.
Year 2022: 55.82% completed. Revenue recognized = 55.82% x $ 8400,000 – $ 2,870,886 (previously recognized) = $ 1,818,115.
Year 2023: 100% completed. Revenue recognized = 100% x $ 8,400,000 – $ 2,870,886- $ 1,818,115 (previously recognized) = $ 3,710,999.
2021 2022
Ans to 2a and 2b Journal Entries Debit $ Credit $ Debit $ Credit $
Costs Incurred CIP (Work-in-progress)    2,160,000 2,692,000
Cash    2,160,000     2,692,000
Billing Accounts Receivable    2,692,000 2,942,000
Billing on CIP    2,692,000     2,942,000
Receiving Payments Cash    2,410,000 2,635,000
Accounts Receivable    2,410,000     2,635,000
Period end adjustments for Revenue Construction Expense    2,160,000
(Gross Profit entry) CIP (Work-in-progress)       710,886
Construction Revenue    2,870,886
Period end adjustments for Revenue Construction Expense 2,692,000
(Gross Profit entry) CIP (Work-in-progress)        873,885
Construction Revenue     1,818,115
Workings for Balance Sheet
CIP (Work-in-progress)
Account Amount ($)
Cash                                 2,160,000
Construction Revenue                                    710,886
Balance at the end of 2021                                 2,870,886
Cash                                 2,692,000
Construction Revenue                                   (873,885)
Balance at the end of 2022                                 4,689,001
Accounts Receivable
Account Amount ($)
Billing on CIP                                 2,692,000
Cash                                (2,410,000)
Balance at the end of 2021                                    282,000
Billing on CIP                                 2,942,000
Cash                                (2,635,000)
Balance at the end of 2022                                    589,000
Billing on CIP
Account Amount ($)
Accounts Receivable                                 2,692,000
Balance at the end of 2021                                 2,692,000
Accounts Receivable                                 2,942,000
Balance at the end of 2022                                 5,634,000
Ans to 3a and 3b
Balance Sheet (Partial) 2021 2022
Current Assets:
CIP (Work-in-progress)          2,870,886          4,689,001
Accounts Receivable             282,000             589,000
        3,152,886         5,278,001
Current Liabilities:
Billing on CIP    2,692,000.00    5,634,000.00
2,692,000.00 5,634,000.00
Add a comment
Know the answer?
Add Answer to:
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000 In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000.2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of $3,880,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to...

    Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT