On February 1, 2021, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,120,000. During 2021, costs of $2,040,000 were incurred with
estimated costs of $4,040,000 yet to be incurred. Billings of
$2,540,000 were sent, and cash collected was $2,290,000.
In 2022, costs incurred were $2,540,000 with remaining costs
estimated to be $3,660,000. 2022 billings were $2,790,000 and
$2,515,000 cash was collected. The project was completed in 2023
after additional costs of $3,840,000 were incurred. The company’s
fiscal year-end is December 31. Arrow recognizes revenue over time
according to percentage of completion.
Required:
1. Compute the amount of revenue and gross profit
or loss to be recognized in 2021, 2022, and 2023 using the
percentage of completion method.
2a. Prepare journal entries for 2021 to record the
transactions described (credit "various accounts" for construction
costs incurred).
2b. Prepare journal entries for 2022 to record the
transactions described (credit "various accounts" for construction
costs incurred).
3a. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2022.
Answer-1:
Calculation of Revenue & Gross Profit to be recognized: | ||||
(Percentage completion method) | ||||
2021 | 2022 | 2023 | Note | |
Contract Price | 8,120,000 | 8,120,000 | 8,120,000 | A |
Cost Incurred during the year | 2,040,000 | 2,540,000 | 3,840,000 | B |
Estimated cost to complete | 4,040,000 | 3,660,000 | - | C |
Cost Incurred to date | 2,040,000 | 4,580,000 | 8,420,000 | D |
(Sum total of the cost incurred during the year) | ||||
Estimated total cost | 6,080,000 | 8,240,000 | 8,420,000 | E=C+D |
Percentage complete | 33.55% | 55.58% | 100.00% | F=D/E |
(Cost Incurred to date/Estimated total cost) | ||||
Total revenue | 2,724,474 | 4,513,301 | 8,120,000 | G=A*F |
Previously recognized revenue | - | 2,724,474 | 4,513,301 | H |
Revenue to be recognized | 2,724,474 | 1,788,827 | 3,606,699 | I=G-H |
Gross Profit to be recognized | 684,474 | (751,173) | (233,301) | J=I-B |
Answer-2a & 2b:
2021 | 2022 | |||||
Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | ||
Costs Incurred | CIP (Work-in-progress) | 2,040,000 | 2,540,000 | |||
Cash | 2,040,000 | 2,540,000 | ||||
Billing | Accounts Receivable | 2,540,000 | 2,790,000 | |||
Billing on CIP | 2,540,000 | 2,790,000 | ||||
Receiving Payments | Cash | 2,290,000 | 2,515,000 | |||
Accounts Receivable | 2,290,000 | 2,515,000 | ||||
Period end adjustments for Revenue | Construction Expense | 2,040,000 | ||||
(Gross Profit entry) | CIP (Work-in-progress) | 684,474 | ||||
Construction Revenue | 2,724,474 | |||||
Period end adjustments for Revenue | Construction Expense | 2,540,000 | ||||
(Gross Profit entry) | CIP (Work-in-progress) | 751,173 | ||||
Construction Revenue | 1,788,827 |
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000 In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000.2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of $3,880,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...