Question

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000.

In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of $3,840,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.
2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022.

I can't figure out balance sheet for 2022

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

ANSWER

As per the given question,

SOLUTION -1

Computation of % of completion, revenue recognition and Gross Profit - Arrow Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recognized (F) (E * D) Revenue for current period (G) Gross Profit (H)
2021 $2,040,000 $2,040,000 $6,080,000 33.55% $8,120,000 $2,724,474 $2,724,474 $684,474 $2,724,474-$2,040,000
2022 $2,540,000 $4,580,000 $8,240,000 55.58% $8,120,000 $4,513,301 $1,788,827 -$804,474 $8,120,000 - $8,240,000 - $684,474
2023 $3,840,000 $8,420,000 $8,420,000 100.00% $8,120,000 $8,120,000 $3,606,699 -$180,000 $8,120,000 - $8,420,000 - $684,474 + $804,474

SOLUTION- 2A

Journal Entries - Arrow Construction Company - 2021 Event Particulars Debit Credit Construction in Progress Dr $2,040,000.00

3 Cash Dr $2,290,000.00 To Accounts receivables $2,290,000.00 (To record collection from customer) Construction in Progress D

SOLUTION- 2B

Journal Entries - Arrow Construction Company - 2022 Event Particulars Debit Credit Construction in Progress Dr $2,540,000.00

Cash Dr $2,515,000.00 To Accounts receivables $2,515,000.00 (To record collection from customer) 4 Cost of construction Dr $2

SOLUTION -3A & 3B

Arrow construction company
Balance Sheet (Partial)
As on December 31
Particulars 2021 2022
Assets:
Current Assets:
Accounts Receivables
2021 - $2,540,000 - $2,290,000
2022 - $250,000 + $2,790,000 - $2,515,000
$250,000.00 $525,000.00
Cost and Profit in excess of billing
2018 - $2,724,474 - $2,540,000
$184,474.00
Liabilities and stockholder's equity:
Billings in excess of costs and profits
($2,790,000 - $2,540,000 + $804,474 - $184,474)

KINDLY RATE

Add a comment
Know the answer?
Add Answer to:
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000 In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000.2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of $3,880,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT