Solution:
Computation of revenue to be recognised and profit or (loss) to be recognised:
(Amounts in $)
Particulars |
2021 |
2022 |
2023 |
Cost incurred during the year |
24,90,000 |
39,84,000 |
20,08,600 |
Cost incurred already (A) |
24,90,000 |
64,74,000 |
84,82,600 |
Estimated cost |
58,10,000 |
18,26,000 |
0 |
Estimated Total Cost (including incurred cost) (B) |
83,00,000 |
83,00,000 |
84,82,600 |
Percentage of Completion (%) (A/B) |
30 |
78 |
100 |
Contract revenue to be recognised (total revenue x % of completion) |
30,00,000 |
78,00,000 |
100,00,000 |
Less: Cost incurred |
(24,90,000) |
(64,74,000) |
(84,82,600) |
Total Profit or (Loss) |
5,10,000 |
13,26,000 |
15,17,400 |
Less: Profit or (Loss) already recognised |
0 |
(5,10,000) |
(13,26,000) |
Profit or (Loss) to be recognised |
5,10,000 |
8,16,000 |
1,91,400 |
Journal Entries:
(Amounts in $)
Date |
Particulars |
Debit |
Credit |
2021 |
(1) Construction Costs: Construction in Progress A/c Dr. To Cash A/c (Being Construction cost incurred during the year) |
24,90,000 |
24,90,000 |
2021 |
(2) Progress Billings: Santa Clara County A/c Dr. Unbilled Contract Receivables (2021) A/c Dr. To Contract Revenue A/c (Being progress billing of contract has been made) |
20,30,000 9,70,000 |
30,00,000 |
2021 |
(3) Cash Collection: Cash A/c Dr. To Santa Clara County A/c (Being cash collected from the client) |
18,15,000 |
18,15,000 |
2021 |
(4) Profit or (Loss) during the year: No Entry needed because it is being already entered by the above entries of revenue and cost incurred. |
N.A. |
N.A. |
Date |
Particulars |
Debit |
Credit |
2022 |
(1) Construction Costs: Construction in Progress A/c Dr. To Cash A/c (Being Construction cost incurred during the year) |
39,84,000 |
39,84,000 |
2022 |
(2) Progress Billings: Santa Clara County A/c Dr. Unbilled Contract Receivables (2022) A/c Dr. To Contract Revenue A/c To Unbilled Contract rec. (2021) A/c (Being progress billing of contract has been made) |
44,44,000 13,26,000 |
48,00,000 9,70,000 |
2022 |
(3) Cash Collection: Cash A/c Dr. To Santa Clara County A/c (Being cash collected from the client) |
39,00,000 |
39,00,000 |
2022 |
(4) Profit or (Loss) during the year: No Entry needed because it is being already entered by the above entries of revenue and cost incurred. |
N.A. |
N.A. |
Date |
Particulars |
Debit |
Credit |
2023 |
(1) Construction Costs: Construction in Progress A/c Dr. To Cash A/c (Being Construction cost incurred during the year) |
20,08,600 |
20,08,600 |
2023 |
(2) Progress Billings: Santa Clara County A/c Dr. To Contract Revenue A/c To Unbilled Contract rec. (2022) A/c (Being progress billing of contract has been made) |
35,26,000 |
22,00,000 13,26,000 |
2023 |
(3) Cash Collection: Cash A/c Dr. To Santa Clara County A/c (Being cash collected from the client) |
42,85,000 |
42,85,000 |
2023 |
(4) Profit or (Loss) during the year: No Entry needed because it is being already entered by the above entries of revenue and cost incurred. |
N.A. |
N.A. |
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...
Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...
The journal has to be done for all years!
! Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10...
Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...
Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...
PLEASE PUT SOLUTION IN THE SAME FORMAT AS THE IMAGE.
THANK YOU!
Exercise 13-3 (Algo) Short-term notes [LO13-2] The following selected transactions relate to liabilities of United Insulation Corporation. United's fiscal year ends on December 31. 2021 Jan. 13 Negotiated a revolving credit agreement with Parish Bank that can be renewed annually upon bank approval. The amount available under the line of credit is $28.0 million at the bank's prime rate. 1 Arranged a three-month bank loan of $8.0 million...
Problem 5-3A Record transactions related to accounts receivable (LO5-3,5-4,5-5) The following information applies to the questions displayed below. The following events occur for The Underwood Corporation during 2021 and 2022, its first two years of operations. Provide service from customers and from services June 12, 2021 Provide services to customers on account for $32,000. September 17, 2021 Receive $17,500 from customers on account. December 31, 2021 Estimate that 45% of accounts receivable at the end of the year will not...