Question

Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following informReq 2A Req 2B Req 2c In the journal below, complete the necessary journal entries for the year 2021 (credit Various accountsJournal entry worksheet < 1 2 3 4 Record progress billings. Note: Enter debits before credits. General Journal Debit Credit D

Journal entry worksheet < 1 2 3 4 Record cash collections. Note: Enter debits before credits. Date General Journal Debit CredJournal entry worksheet < 1 2 3 4 Record gross profit (loss). Note: Enter debits before credits. General Journal Debit CreditReq 2A Reg 2B Req 2C In the journal below, complete the necessary journal entries for the year 2022 (credit Various accountsJournal entry worksheet < 1 2 3 4 Record progress billings. Note: Enter debits before credits. Date General Journal Debit Cre

Journal entry worksheet Record cash collections. Note: Enter debits before credits. General Journal Debit Credit Date 2022

Journal entry worksheet < 1 2 3 4 Record gross profit (loss). Note: Enter debits before credits. General Journal Debit Credit

Req 2A Req 2B Req 20 In the journal below, complete the necessary journal entries for the year 2023 (credit Various accountsJournal entry worksheet < 1 2 3 4 Record progress billings. Note: Enter debits before credits. Date General Journal Debit Cre

Journal entry worksheet Record cash collections. Note: Enter debits before credits. Date General Journal Debit Credit 2023

Journal entry worksheet < 1 2 3 4 Record gross profit (loss). Note: Enter debits before credits. General Journal Debit Credit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Computation of revenue to be recognised and profit or (loss) to be recognised:

(Amounts in $)

Particulars

2021

2022

2023

Cost incurred during the year

24,90,000

39,84,000

20,08,600

Cost incurred already (A)

24,90,000

64,74,000

84,82,600

Estimated cost

58,10,000

18,26,000

0

Estimated Total Cost (including incurred cost) (B)

83,00,000

83,00,000

84,82,600

Percentage of Completion (%) (A/B)

30

78

100

Contract revenue to be recognised (total revenue x % of completion)

30,00,000

78,00,000

100,00,000

Less: Cost incurred

(24,90,000)

(64,74,000)

(84,82,600)

Total Profit or (Loss)

5,10,000

13,26,000

15,17,400

Less: Profit or (Loss) already recognised

0

(5,10,000)

(13,26,000)

Profit or (Loss) to be recognised

5,10,000

8,16,000

1,91,400

Journal Entries:

(Amounts in $)

Date

Particulars

Debit

Credit

2021

(1) Construction Costs:

Construction in Progress A/c Dr.

                To Cash A/c

(Being Construction cost incurred during the year)

24,90,000

24,90,000

2021

(2) Progress Billings:

Santa Clara County A/c                               Dr.

Unbilled Contract Receivables (2021) A/c   Dr.

                To Contract Revenue A/c

(Being progress billing of contract has been made)

20,30,000

9,70,000

30,00,000

2021

(3) Cash Collection:

Cash A/c       Dr.

          To Santa Clara County A/c

(Being cash collected from the client)

18,15,000

18,15,000

2021

(4) Profit or (Loss) during the year:

No Entry needed because it is being already entered by the above entries of revenue and cost incurred.

N.A.

N.A.

Date

Particulars

Debit

Credit

2022

(1) Construction Costs:

Construction in Progress A/c Dr.

                To Cash A/c

(Being Construction cost incurred during the year)

39,84,000

39,84,000

2022

(2) Progress Billings:

Santa Clara County A/c                               Dr.

Unbilled Contract Receivables (2022) A/c   Dr.

                To Contract Revenue A/c

                To Unbilled Contract rec. (2021) A/c

(Being progress billing of contract has been made)

44,44,000

13,26,000

48,00,000

9,70,000

2022

(3) Cash Collection:

Cash A/c       Dr.

          To Santa Clara County A/c

(Being cash collected from the client)

39,00,000

39,00,000

2022

(4) Profit or (Loss) during the year:

No Entry needed because it is being already entered by the above entries of revenue and cost incurred.

N.A.

N.A.

Date

Particulars

Debit

Credit

2023

(1) Construction Costs:

Construction in Progress A/c Dr.

                To Cash A/c

(Being Construction cost incurred during the year)

20,08,600

20,08,600

2023

(2) Progress Billings:

Santa Clara County A/c                               Dr.

                To Contract Revenue A/c

               To Unbilled Contract rec. (2022) A/c

(Being progress billing of contract has been made)

35,26,000

22,00,000

13,26,000

2023

(3) Cash Collection:

Cash A/c       Dr.

          To Santa Clara County A/c

(Being cash collected from the client)

42,85,000

42,85,000

2023

(4) Profit or (Loss) during the year:

No Entry needed because it is being already entered by the above entries of revenue and cost incurred.

N.A.

N.A.

Add a comment
Know the answer?
Add Answer to:
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss...

    Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...

  • The journal has to be done for all years! ! Required information (The following information applies...

    The journal has to be done for all years! ! Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10...

  • Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606...

    Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company...

    Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...

  • PLEASE PUT SOLUTION IN THE SAME FORMAT AS THE IMAGE. THANK YOU! Exercise 13-3 (Algo) Short-term...

    PLEASE PUT SOLUTION IN THE SAME FORMAT AS THE IMAGE. THANK YOU! Exercise 13-3 (Algo) Short-term notes [LO13-2] The following selected transactions relate to liabilities of United Insulation Corporation. United's fiscal year ends on December 31. 2021 Jan. 13 Negotiated a revolving credit agreement with Parish Bank that can be renewed annually upon bank approval. The amount available under the line of credit is $28.0 million at the bank's prime rate. 1 Arranged a three-month bank loan of $8.0 million...

  • Problem 5-3A Record transactions related to accounts receivable (LO5-3,5-4,5-5) The following information applies to the questions...

    Problem 5-3A Record transactions related to accounts receivable (LO5-3,5-4,5-5) The following information applies to the questions displayed below. The following events occur for The Underwood Corporation during 2021 and 2022, its first two years of operations. Provide service from customers and from services June 12, 2021 Provide services to customers on account for $32,000. September 17, 2021 Receive $17,500 from customers on account. December 31, 2021 Estimate that 45% of accounts receivable at the end of the year will not...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT