Question

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate ConstructionJournal entry worksheet 2 3 4 Record construction costs. Note: Enter debits before credits. Date General Journal Debit CreditJournal entry worksheet 3 4 Record progress billings. Note: Enter debits before credits. General Journal Debit Credit Date 20Journal entry worksheet < 1 2 3 ........ Record cash collections. Note: Enter debits before credits. General Journal Debit CrJournal entry worksheet < 1 2 3 Record gross profit (loss). Note: Enter debits before credits. Date General Journal Debit Cre

0 0
Add a comment Improve this question Transcribed image text
Answer #1

UN WWA 2021 2022 10,000,000 10,000,000 10,000,000 ale Page: No O za @be B Gross Profit / lows) Particular 2023 Contract pricePage. No @ Groes profit (tom) = 2900,000 – 2291000 = $609000 2002 Cost Incuvied to date : 2291000 + 3555000 = $5846000 YercenPage No ③ 2021 2022 2023 | Journal entijes Debit C$) Coedit C$) debitllo) Credit C) debit C4) Gredit (1) costs CIP(work in pr

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10...

  • The journal has to be done for all years! ! Required information (The following information applies...

    The journal has to be done for all years! ! Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...

  • The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for 10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billinga during the year Cash collections during the year 5, 658,000 Westgate...

  • The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...

    The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:     2021 2022 2023 Cost incurred during the year $2,550,000   $4,250,000   $ 1,870,000  Estimated costs to complete as of year-end 5,950,000     1,700,000     0  Billings during the year 2,050,000    4,750,000    3,200,000  Cash collections during the year   1,825,000     4,100,000    4,075,000   Westgate recognizes...

  • Required information (The following information applies to the questions displayed below.) On January 1, 2021, Splash...

    Required information (The following information applies to the questions displayed below.) On January 1, 2021, Splash City issues $380,000 of 8% bonds, due in 15 years, with interest payable semiannually on June 30 and December 31 each year. Assuming the market interest rate on the issue date is 9%, the bonds will issue at $349,051. 2. Record the bond issue on January 1, 2021, and the first two semiannual interest payments on June 30, 2021, and December 31, 2021. (If...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information The following information applies to the questions displayed below.] On July 15, 2021, the...

    Required information The following information applies to the questions displayed below.] On July 15, 2021, the Nixon Car Company purchased 2100 tires from the Harwell Company for $40 each. The terms of the sale were 3/10, n/30. Nixon uses a perpetual inventory system and the net method of accounting for purchase discounts. Required: 1. Prepare the journal entries to record the purchase on July 15 and payment on July 23, 2021 2. Prepare the journal entry for the payment, assuming...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT