Question

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion.

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Before the journal entries we have to calculate the gross profit to be booked during the each year first

Contract value = $10000000

Particulars 2021(in$) 2022(in$) 2023(in$)
Cost incured prior to this year(A) 0 2016000 4824000
Cost incured during the year(B) 2016000 2808000 2613600
Cumulative total cost(C=A+B) 2016000 4824000 7437600
Estimated costs to complete as of year end(D) 5184000 2376000 0
Total Estimated Cost (E= C+D) 7200000 7200000 7437600
% of completion(F=(C/E)*100) 28% 67% 100%
Contract value completed (G=F*10000000) 2800000 6700000 10000000
Total Revenue recognised in prior years (H) 0 2800000 6700000
Cost incured during the year (I) 2016000 2808000 2613600
Gross profit(J=G-H-I) 784000 1092000 686400

To verify that the claculation is correct we calculate the total profit and cross the figure with sum of profits of three years

Total Profit = $10000000-$7437600 = $2562400

Sum of gross profit of three years = $784000+$1092000+$686400 = $2562400

Hence verified

Now lets journalise the entries

There are 4 set of journal entries common to 3 years and a closing entry for year 3

To make it easier lets put it in a table

Accounts Titles 2021($) 2022($) 2023($)
Construction in progress (Dr) 2016000 2808000 2613600
Various accounts (Cr) 2016000 2808000 2613600
(To record the construction cost)
Accounts receivable (Dr) 2180000 2644000 5176000
Billings on construction contracts(Cr) 2180000 2644000 5176000
(To record progres billing)
Cash (Dr) 1890000 2500000 5610000
Accounts Receivable (Cr) 1890000 2500000 5610000
(To Record the cash collection)
Cost of construction(Dr) 2016000 2808000 2613600
Construction in progress(Dr) 784000 1092000 686400
Revenue from contract(Cr) 2800000 3900000 3300000
(To record gross profit)
Billing on construction contract (Dr No entry No entry 10000000
Construction in Progress(Cr) 10000000
(To Close the accounts)

Hence solved

Please free to comment for further clarification and upvote if it was helpful

Thank You

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $2,613,600 0 5,176,000...

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $ 2,613,600 0...

  • Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company...

    Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 5,176,000 5,610,000 Westgate...

  • Help In 2021, the Westgate Construction Company entered into a contract to construct a road for...

    Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...

  • [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT