Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion.
Before the journal entries we have to calculate the gross profit to be booked during the each year first
Contract value = $10000000
Particulars | 2021(in$) | 2022(in$) | 2023(in$) |
Cost incured prior to this year(A) | 0 | 2016000 | 4824000 |
Cost incured during the year(B) | 2016000 | 2808000 | 2613600 |
Cumulative total cost(C=A+B) | 2016000 | 4824000 | 7437600 |
Estimated costs to complete as of year end(D) | 5184000 | 2376000 | 0 |
Total Estimated Cost (E= C+D) | 7200000 | 7200000 | 7437600 |
% of completion(F=(C/E)*100) | 28% | 67% | 100% |
Contract value completed (G=F*10000000) | 2800000 | 6700000 | 10000000 |
Total Revenue recognised in prior years (H) | 0 | 2800000 | 6700000 |
Cost incured during the year (I) | 2016000 | 2808000 | 2613600 |
Gross profit(J=G-H-I) | 784000 | 1092000 | 686400 |
To verify that the claculation is correct we calculate the total profit and cross the figure with sum of profits of three years
Total Profit = $10000000-$7437600 = $2562400
Sum of gross profit of three years = $784000+$1092000+$686400 = $2562400
Hence verified
Now lets journalise the entries
There are 4 set of journal entries common to 3 years and a closing entry for year 3
To make it easier lets put it in a table
Accounts Titles | 2021($) | 2022($) | 2023($) |
Construction in progress (Dr) | 2016000 | 2808000 | 2613600 |
Various accounts (Cr) | 2016000 | 2808000 | 2613600 |
(To record the construction cost) | |||
Accounts receivable (Dr) | 2180000 | 2644000 | 5176000 |
Billings on construction contracts(Cr) | 2180000 | 2644000 | 5176000 |
(To record progres billing) | |||
Cash (Dr) | 1890000 | 2500000 | 5610000 |
Accounts Receivable (Cr) | 1890000 | 2500000 | 5610000 |
(To Record the cash collection) | |||
Cost of construction(Dr) | 2016000 | 2808000 | 2613600 |
Construction in progress(Dr) | 784000 | 1092000 | 686400 |
Revenue from contract(Cr) | 2800000 | 3900000 | 3300000 |
(To record gross profit) | |||
Billing on construction contract (Dr | No entry | No entry | 10000000 |
Construction in Progress(Cr) | 10000000 | ||
(To Close the accounts) | |||
Hence solved
Please free to comment for further clarification and upvote if it was helpful
Thank You
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $2,613,600 0 5,176,000...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $ 2,613,600 0...
Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 5,176,000 5,610,000 Westgate...
Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...